1 Introduction

Coal resources are currently the main energy sources in China (Han et al. 2015; Si et al. 2019, 2015). As an essential part of this field, fully bonded bolting method has been widely used in ground geotechnical engineering and underground coal mine engineering (Wang and Wan 2019; Wang et al. 2020; Shan et al. 2019). With the gradual mining of shallow coal resources (Zhang et al. 2019; Wang et al. 2018; Miu and Qian 2009), deep mining has become an inevitable trend of this industry (Zhang et al. 2020a, b; Zhang et al. 2020a, b; Feng et al. 2019). As illustrated in Fig. 1, under the action of deep buried high stress, the surrounding rock cracks develop and damage seriously, which decreases the bearing capacity and significantly increases the deformation sensitivity. As a result, the roadway support get more complex and prone to large deformation instability, which may lead to roof collapse accidents occurring from time to time, restricting the safe and efficient production of mine (Kang 2014). Scholars have gathered novel resources to deal with these severe issues, and proposed the concept of prestressed fully bonded bolting method (Chen et al. 2020; Du et al. 2020; Nie et al. 2020), in which the analysis of the mechanical property is an important part (Meng et al. 2019; Zhou et al. 2017; Chen et al. 2018a, b). Even considering the complex stress of the fully bonded bolt, the bolting support design still lacks theoretical basis and deserves to be further researched (Li et al. 2019).

Fig. 1
figure 1

(reproduced from literature Yang et al. (2020))

Deep buried high stress and large deformation roadway

Research has been accruing to better understand the mechanical characteristics and supporting efficiency mechanism of the fully bonded bolt. Li et al. (2016) had conducted a series of pull-out tests of fully bonded bolts and concluded that the bond strength of the bolt was not a constant, but related to the embedment length. The bond strength was linearly proportional to the uniaxial compressive strength of the grout. Similarly, Yu et al. (2019) analyzed the critical rock bolt embedment length at which yielding or necking occurs together with the friction coefficient at the residual axial stress. They have concluded that when diameter was held constant, the maximum load and corresponding displacement increased as the cement mortar strength surged, but the residual load was still irregular.

Teymen (2017) investigated the effect of mineral admixtures on the grout strength of fully-grouted rock bolts and block punch index considering the compressive strength of the grout on the load bearing capacity. He proposed that mineral admixtures could be used for high-strength and low-cost grout in tunneling applications. Chen et al. (2017) also conducted a number of pull-out tests with a bulbed cable bolt to investigate the cylindrical specimen diameter effect on the bonding capacity and discovered that the bonding capacity increased linearly with specimen diameter up to 356 mm in the unconfined condition. In the same year, Thenevin et al. (2017) conducted a series of laboratory pull-out tests using rock bolts and cable bolts of different materials, and confirmed the influence of confining pressure and embedment length on the pull-out response. Nie et al. (2018) analyzed the performance of the fully grouted rock bolts installed in the jointed rock mass and assumed that the reinforcement area of the reinforcement rock unit could be used to optimize their design. Moreover, they concluded that the reinforcement rock unit induced by grouped rock bolts was heavily influenced by the joint orientations and the rock bolt spacing.

Chen et al. (2018a, b) simulated the pull-out behavior of a plain cable bolt and a modified cable bolt using the commercial numerical code of FLAC2D and found that, compared with plain cable bolts, modified cable bolts could generate more confinement within the rock specimen or confinement medium. Zou and Zhang (2019) investigated the dynamic evolution characteristic of the bond strength at the interface of a bolt and a rock mass under an axial tensile load considering the non-uniform stress of the surrounding rock along the bolts. By analyzing the features of this arrangement, they have proposed a new dynamic bond-slip model.

Before these novel studies, Nemcik et al. (2014) have already presented a numerical modelling of fully grouted rock bolts loaded in tension by implementing a nonlinear bond–slip relationship of bolt–grout interface into a commercial finite difference rock mechanics code. Martin et al. (2013) also studied the bolt-grout interface of fully grouted rock bolts aiming to determine its constitutive law and proposed a semi-empirical formulation of the interface response based on the available data. A few years before this framework was proposed, Martin et al. (2011) came up with a new analytical approach that could predict the mechanical behaviour of fully grouted rock bolts subjected to pull-out tests and verified the feasibility of this method with experimental results obtained via in situ pull-out tests.

Most of the aforementioned studies focus on the laboratory pull-out test and numerical analysis calculation of the fully bonded bolt. The laboratory pull-out test mainly considers the mechanical characteristics of the fully bonded bolting system influenced by different bolt materials, bolt diameter and anchoring agent materials. Some researchers have studied the mechanical properties of the fully bonded bolt with varied bond lengths, and achieved preliminary results. However, there is still a lack of research on the mechanical properties of fully bonded bolt specimens with different bond lengths in the yield stage under laboratorial pull-out experiment. This study aims to explore the mechanical response characteristics of fully bonded bolting specimens with different bond lengths at the yield stage, based on the condition of pull-out experiments. This study comprises a mixed methodology and laboratory experiments and theoretical analysis were carried out to reveal the mechanical law of the fully bonded bolt in the yield stage. The major outcomes presented here provide a certain reference for the design of the fully bonded supporting scheme.

2 Materials and Methods

2.1 Materials

In the first experiment, high-strength seamless steel tubes with varied lengths were used to simulate the bolt hole (Fig. 2). The inner diameter of the steel tube was 30 mm, the outer diameter was 50 mm, and the diameter of the bolt was 22 mm. Therefore, there was an 8 mm hole between the bolt rod and the inner wall of the steel tube to simulate the thickness of the anchor ring. After the bolt was inserted into the steel tube, the gap between the bolt rod and the inner wall of the steel tube was filled with the anchoring agent. All the adopted bolts are all left-lateral, rib-free, and high-strength bolts, with yield strength and tensile strength of 335 MPa, 490Mpa, respectively. The anchoring agent is a kind of prestressed duct grouting agent whose particle size is ultra-fine. The fluidity, bleeding rate, free expansion rate (24 h), initial setting time, and final setting time of the grouting agent used is 20, 1.8–2.0%, 0.18%, 5.6 h, and 16 h, respectively. After mixing with water, the anchoring agent had a high fluidity (water cement ratio was 0.32), and could easily fill the gap between the bolt and the inner wall of the steel tube. The initial setting time of the grouting agent was more than 4 h, and the final setting time was less than 24 h. The uniaxial compressive strength of the growing agent was 52.3 MPa and the uniaxial tensile strength was 2 MPa (Fig. 3).

Fig. 2
figure 2

Schematic diagram of fully bonded bolts specimen

Fig. 3
figure 3

Test results of specimen-grouting material strength and test specimen failure: a compressive test specimen-grouting material. b Tensile test specimen-grouting material

In this pull-out test of fully bonded bolt with varied bond lengths, a total of 20 left-handed, rib-free and high-strength bolts were prepared along with 20 high-strength seamless steel tubes. In addition, five groups of different schemes were set up and four identical specimens were prepared for each group to avoid the dispersion of the test. A total of 20 specimens were involved in the experiment. The steel tube length, anchor rod length and grouting agent dosage used in each group of tests are shown in Table 1. However, it is worth noting that the selection of bond length in the fully bonded bolt specimen is an essential part of this experiment. When the bond length is too large, it makes it challenging to pull out the specimen, so it breaks under pull-out conditions. In order to ensure the rationality of the experimental scheme, the bond length range of fully bonded specimens used in this study is 150–350 mm. These conditions were outlined after referring to Li et al.’s (2016) study (100–400 mm).

Table 1 Experimental scheme and specimen preparation

2.2 Specimen Preparation and Test Method

The preparation and experimental process of the specimen are as follows:

  1. (1)

    First, we inserted the bolt into the bottom of the steel tube. At this stage, the exposed length of the anchor rod is 150 mm.

  2. (2)

    Then, the grouting agent with water material ratio of 0.32 was mixed evenly and poured into the gap between the bolt rod and the steel tube until the space of the whole gap is filled. At this stage, the exposed section of the bot is 100 mm.

  3. (3)

    After the specimen preparation was completed, the grouting agent was kept at room temperature for 28 days to ensure that the final strength of grouting agent can meet the requirements of anchorage.

  4. (4)

    After 28 days of curing, the fully bonded specimens were placed on the MTS pull-out testing machine (Fig. 4). Acoustic emission technology was used to explore the internal failure mechanism of the fully bonded specimen in the failure process. Two acoustic emission probes were installed at a distance of 50 mm from the end of the fully bonded specimen to detect the energy diffusion of crack propagation during the pull-out process. Finally, the pull-out test was carried out. The displacement control program of the MTS Criterion Model 64 during the pull-out test was 15 mm/min Feng (2017).

Fig. 4
figure 4

(reproduced from Feng et al. (2018))

Rendering picture for test equipment: a schematic sketch of MTS Criterion 64. b For MTS Criterion Model 64 testing machine. c Experimental system diagram.

3 Results and Analyses

3.1 Results of Mechanical Properties of Bolt During Pull-out Test

The pullout force–displacement curves of the fully bonded bolt specimen are shown in Figs. 5, 6, 7, 8, 9, with a total of 20 groups. As illustrated, all the pull-out mechanical curves of fully bonded bolt specimens show three stages. The first stage is the elastic stage in which the pull-out force increases linearly with the displacement. The second stage is the yield stage in which the slope of the curve evidently decreases before the peak pull-out force. In this stage, it is easy to detect that the displacement increases, while the drawing force is slowly surging. The third stage is the post-peak stage in which the displacement increases rapidly and the pull-out force decreases at the same speed and that is when the fully bonded bolt is pulled out. As it can be seen in Fig. 5, when the bolt length was 300 mm and the steel tube length was 200 mm, the bolt showed a trend of an approximately linear increase with the pull-out force. When the pulling displacement was 14 mm, the pull-out force reached the peak. Afterwards, it dropped down with the increase of pulling displacement. It should be noted that specimen 1, 2, 4 did not go through the yield stage. It has been observed that their slope of the curve obviously slowed down before the bolt reached the peak pull-out force. In contrast, only specimen 3 experienced the yield stage before reaching the peak force point. It can also be concluded from the failure photos of specimen 1 that when the bolt was pulled out, the grouting agent was also pulled out without any damage. Accordingly, it could be concluded that there was almost no damage between the anchoring agent and the inner wall of the steel tube. At this time, the bolt and anchoring agent were entirely pulled out, and the pull-out force was hardly transmitted to the steel tube itself.

Fig. 5
figure 5

Pull-out test results of the fully bonded bolts specimen. The length of steel tube was 200 mm, the length of bolt was 300 mm, the bond length was 200 mm, and the exposed length of bolt was 100 mm. The detected AE energy specimen was the energy evolution law of specimen 1

Fig. 6
figure 6

Pull-out test results of the fully bonded bolts specimen. The length of steel tube was 250 mm, the length of bolt was 350 mm, the bond length was 250 mm, and the exposed length of bolt was 100 mm. The detected AE energy specimen was the energy evolution law of specimen 2

Fig. 7
figure 7

Pull-out test results of the fully bonded bolts specimen. The length of steel tube was 300 mm, the length of bolt was 400 mm, the bond length was 300 mm, and the exposed length of bolt was 100 mm. The detected AE energy specimen was the energy evolution law of specimen 1

Fig. 8
figure 8

Pull-out test results of the fully bonded bolts specimen. The length of steel tube was 350 mm, the length of bolt was 450 mm, the bond length was 350 mm, and the exposed length of bolt was 100 mm, the detected AE energy specimen was the energy evolution law of specimen 4

Fig. 9
figure 9

Pull-out test results of the fully bonded bolts specimen. The length of steel tube was 400 mm, the length of bolt was 500 mm, the bond length was 400 mm, and the exposed length of bolt was 100 mm. The detected AE energy specimen was the energy evolution law of specimen 1

According to Fig. 6, when the bolt length was 350 mm, the steel tube length was 250 mm, and the displacement was 20 mm. Under these circumstances, the pull-out force reached its peak. The pullout force–displacement curves of the four specimens all went through the tensile yield stage before reaching the peak force point. When the displacement was between 10 and 20 mm (before reaching the peak), the slope of the curve slowed down and showed an upper convex type. Besides, the increase of displacement in this stage did not cause a large-scale increase on the pull-out force. According to the actual yield strength of the bolt, it could be inferred that the displacement growth in this stage was mainly caused by two features: (1) the plastic elongation of the bolt; (2) a small part of the interface debonding near the pull-out end of the bolt. The debonding here refers to the interface between the anchoring agent and the inner wall of the steel tube, which could be seen in Fig. 5. As illustrated, the anchoring agent was pulled out without damage.

According to Fig. 7, when the bolt length was 400 mm, the steel tube length was 300 mm, and the displacement was 35 mm. Under these circumstances, the pull-out force reached the peak force point of 275 kN. Furthermore, all of the four specimens went through a more obvious tensile yield stage before reaching the peak. It should be noted that from the initial yield stage to the peak force, the displacement ranged between 10 and 35 mm, and the four curves were quite consistent, almost without discreteness. From the failure photos of specimen 4, it can be seen that the grouting agent has been damaged, mainly due to the longer yield stage caused by the increase of the bond length. With a longer yield stage, the grouting agent experienced stronger put-out force, which makes it more prone to be damaged.

According to Fig. 8, when the bolt length was 450 mm, the steel tube length was 350 mm, and the displacement was 39 mm. Under these circumstances, the pull-out force reached the peak force point of 280kN. Moreover, from the initial yield stage to the peak force, the displacement ranged between 10 and 35 mm. The grouting agent was also damaged after the bolt was pulled out.

According to Fig. 9, when the bolt length was 500 mm, the steel tube length was 400 mm, and the displacement was 44 mm. Under these circumstances, the pulling force reached the peak force. Among the four specimens, the displacement corresponding to the peak force of specimen 1 reached 50 mm, which further verified that the yield stage became longer with the increase of the fully bond length.

3.2 Results of Acoustic Emission Energy Events During Pull-out Test

Figures 5, 6, 7, 8, 9 show that there is a positive correlation between the amount of energy in the linear growth stage of AE events and the bond length of the fully bonded bolts. This means that the longer the bond length was, the more energy events would occur at the initial stage of the bolt when bearing the pull-out force. The pull-out force also had a directly proportional correlation with the energy peak force point. Under the condition of same pull-out displacement and increased bond length, the mutual shear lag between the bond interface would undertake a stronger adjustment effect, causing the increased energy events detected by AE, and increased energy values. During the yield stage, the energy events of five figures were relatively small as a result of the elongation effect of the bolt when submitted to a larger pull-out force.

4 Discussion

Our experiments have pointed out some interesting rules and phenomena. According to the test results of 20 groups of fully bonded bolting specimens, when their bond length ratio is small (Fig. 5), the bolts’ pull-out force go through a very short yield stage before reaching the peak value. Besides, the bolt is quickly pulled out after the elastic pull-out stage rather than gradually pulled out. With the increase of the bond length (Figs. 6, 7, 8, 9), the pull-out force of the bolt goes through a longer yield stage before the peak force point. This is also the stage in which the slope of the curve before the peak pull-out force is significantly slowed down. That is, the time and the pull-out displacement increase as the bond length surges in the yield stage (Fig. 10), and the bolt is gradually pulled out under the action of the pull-out force. The reason behind this phenomenon is that when the fully bonded specimen is under the same pull-out force, the bond length of the fully bonded specimen widens, leading to greater axial shear reaction generated at the anchorage interface in the stress yield stage, and more anchorage interface with the sudden debond of the anchorage specimen. This correlation results in a longer time of stress yield. With the increase of the fully bonded length, more energy events are likely to occur at the initial stage of the pull-out force, which also affects the energy peak. Under the condition of the same pull-out displacement of the anchor bolt, a stronger mutual shear lag adjustment effect between the bonding interface of the anchorage specimen with longer bond length, would lead to more energy events detected by acoustic emission, also increasing the energy value.

It is worth noting that after experiencing the peak pull-out force, the pull-out force value fluctuates. This is because the failure mode of the anchoring interface is progressive sliding during the pulling process of the anchor bolt. With the increase of bond length, more anchorage interfaces can be used to balance the pulling force. Due to the relationship between the force and reaction force, the pull-out force tends to be higher. The slope of the elastic growth part of the experimental curve of the fully bonded specimen remains the same, but the bond length varies because in the early stage of the pull-out test (linear growth stage) the stressed part of the fully bonded bolting specimen is the exposed end of the bolt. So, this phenomenon is explained by the unaltered exposed length of the bolt in all fully bonded bolting specimens.

Li et al. (2016) studied the critical bond length of fully bonded bolts under different water cement ratio and found that the critical embedded length of anchor bolts is about 36 cm when the water cement ratio is 0.50 (corresponding grouting uniaxial compressive strength (UCS) is 28 MPa), a featured that is related to the embedded length. In this paper, the water cement ratio of specific ultra-fine cement used is 0.32 (UCS is 52.3 MPa). We have conducted a similar experiment and uncovered that when the bond length of the bolt exceeds 400 mm, it does not break, which may be due to the different bond ability between the grouting bond material and the steel pipe. Yu et al. (2019) studied the influence of bolt diameter on the mechanical properties of fully bonded specimens under the same cement mortar strength, but ignored the influence of anchorage bond length from the beginning to the end of the yield stage and also did not consider the progressive failure process of anchorage specimens. We consider that our results fill this literature gap since we carefully emphasized the pull-out mechanical properties of fully-bonded bolts during the whole yield stage under different conditions, e.g., same water cement ratio grouting bond material, bolt diameter, steel pipe diameter, steel pipe inner diameter, and bond lengths.

Our findings may provide guidance for the potential failure of bolt anchorage systems. Høien et al. (2021) proposed that there are three kinds of pull-out forms involved in pull-out tests: (1) pull-out below the yield strength of the bolt steel; (2) pull-out between the yield and ultimate loads, that is, during strain hardening of the steel; (3) steel failure at the ultimate load. We have identified that twenty different groups of bolts will produce corresponding yield deformation after the drawing process, which directly impacts our experimental results. Our research focused on the influence of different fully bond strengths on the mechanical properties of the anchorage system in the yield stage, but we recognized that there’s still a lack of understanding regarding the influence of the bolt yield deformation on the experimental results (Fig. 10).

Fig. 10
figure 10

(Each specimen in the figure is taken from the experimental results of the specimen with smaller dispersion in each group.)

Pull-out test results of the fully bonded bolts specimen with varied bond length.

5 Conclusions

This study aimed to explore the mechanical response characteristics of the fully bonded bolts with varied bond lengths at the yield stage via a pull-out experiment. The research was carried out with a mixed methodology that comprised laboratory experiments and a theoretical analysis that could reveal the mechanical law of the fully bonded bolts in the yield stage. The major outcomes of this research led to the following conclusions:

In the pull-out test of the fully bonded bolt, the mechanical properties of varied bolt lengths in the yield stage varied greatly. When the bond length is short, the pull-out force of the bolt undergoes a short stress yield stage before reaching the peak force. In other words, the fully bonded system quickly reaches the post-peak pull-out stage after going through the elastic pull-out stage. When the bond length increases, the pull-out force of bolt undergoes a longer yield stage as a result of a larger stress anchorage interface. Both the time of yield stage and corresponding pull-out displacement get enlarged, which helps avoiding the premature pull-out of the bolt from causing fully bonded system failure. This conclusion provides a reference for the length selection of fully bonded bolts. That is, when designing the fully bonded support scheme, the length of the bolt (or the length of fully bonded bolts) should be appropriately increased in order to avoid premature debonding failure of bolt under axial tensile force.

It is noteworthy that this experiment only considers the axial pull-out of the fully bonded bolting specimen, and does not consider the lateral stress fluctuation, which is worthy of attention for future studies.