1 Introduction

Some of the most important applications of repeated loading take place in highway, airport, and railway engineering. In such types of geotechnical structures, the roadbed soil (subgrade soil) behavior depends upon the time-dependent behavior of the repeated loading.

Mitchell [12] pointed out that repeated or cyclic loading of soils may result from a number of natural phenomena or human activities such as vehicular traffic, wind waves, reciprocating machinery, and others.

Conte and Troncone [3] reported that special structures such as silos or fluid tanks subject the soils to loading and unloading stages that repeat themselves more or less periodically over time.

Many forms of time-dependent behavior of repeated loading were suggested by various authors [2, 9, 11].

Barksdale [2] pointed out that the stress pulse can be approximated by a haversine or a triangular function. However, McLean [11] determined the loading time for an equivalent square wave vertical pulse. Huang [9] pointed out that the type and duration of loading used in the repeated load test should simulate that actually occurring in the field, and he recommended the use of a stress pulse in the form of a haversine or triangular loading.

2 Characteristics of loading waveform

For highways and airports, Huang [9] reported that when a wheel load is at a considerable distance from a given point in the pavement, the stress at that point is zero and when the load becomes directly above the point considered, the stress at that point is maximum. Therefore, it is reasonable to assume the stress pulse to be a haversine or triangular loading, the duration of which depends on the vehicle speed tire contact radius as well as the depth of the point below the surface of the flexible or rigid pavement.

Huang [9] reported that a reasonable assumption is that the load has practically no effect when it is at a distance of six times the radius of the circular tire-pavement contact area from the point considered. This means that

$$ d = 12\,{{\frac{a}{s}}}$$
(1)

where d = duration of the load, a = radius of circular tire-pavement contact area, s = vehicle speed.

Huang [9] recommended the use of the following haversine loading given by

$$ L(t^{*} ) = q\sin^{2} \left( {{\frac{\pi }{2}} + {\frac{{\pi t^{*} }}{d}}} \right) $$
(2)

where L(t*) = loading as a function of time, q = load amplitude, t* = time, d = period of repeated load.

For \( t = t^{*} + {d}/{2}, \) it can be shown easily that (see Fig. 1):

$$ L(t) = q\sin^{2} {\frac{\pi t}{d}} $$
(3)

and

$$ {\frac{{{\text{d}}L(t)}}{{{\text{d}}t}}} = {\frac{q\pi }{d}}\sin {\frac{2\pi t}{d}}.$$
(4)
Fig. 1
figure 1

Haversine loading function

3 Duration of loading and rest period

It is well known that the vehicle speed varies a great deal, and the depth of the material may not be known during the design stage. For these reasons, Huang [9] recommended the use of duration of 0.1 s and a rest period of 0.9 s.

It is worth mentioning that the load duration has very little effect on the resilient modulus of granular soils, but it has some effect on fine-grained soils depending on moisture content. Huang [9] stated that the effect of rest period is not known, and it is probably insignificant. However, the effect of rest period of repeated loading on the consolidation process is one of the main objects of this paper, and it will be discussed thoroughly under Sect. 8.

4 Governing differential equation for 1-D consolidation

It is well known that the Terzaghi one-dimensional theory of consolidation under instantaneous loading was borne in 1923 and published in his books in 1925 and 1943 [16, 17]. Terzaghi and Fröhlich [15] extended the Terzaghi theory to various cases of time-dependent loading following a single ramp loading. Olson [13] presented charts for one-dimensional consolidation for the case of simple ramp loading assuming constant coefficient of consolidation. Hsu and Lu [8] extended Olson’s solution of one-dimensional consolidation to those with varying loading-dependent coefficients of consolidation. Conte and Troncone [3] presented analytical solution for the analysis of one-dimensional consolidation of saturated soil layers subjected to general time-dependent loading including the cases of cyclic square wave and trapezoidal loadings. Their solution was in agreement with Baligh and Levadaux [1] for 1-D consolidation for the case of repeated rectangular loading. However, Favaretti and Soranzo [5], Guan et al. [7] and Geng et al. [6] derived some solutions for different types of cyclic loadings. For example, Geng et al. [6] developed a simple semi-analytical method to solve the one-dimensional non-linear consolidation problems with variable compressibility and permeability under cyclic loadings. They presented the Laplace Transform for suddenly imposed constant loading, rectangular pulse cyclic loading, sinusoidal cyclic loading, triangular cyclic loading, and trapezoidal cyclic loading. However, no experimental results were presented for any case of cyclic loadings.

Zimmerer [19] treated also the problem of 1-D consolidation under sinusoidal loading only using finite difference technique. He extended his study to nonlinear 1-D consolidation taking into account nonlinear variation in permeability and density, and allowance was made for geometrical non-linearity.

Razouki and Al-Zayadi [14] extended the consolidation study to time-dependent embankment loading and presented various charts for quick use in practice taking into account anisotropic permeability, various shapes of the embankment loading, various clay layer thicknesses relative to the base width of the embankment and various construction periods.

The governing differential equation adopted in this work is that of Terzaghi and Fröhlich for time-dependent loading as follows (see Fig. 2):

$$ {\frac{\partial u}{\partial t}} = C_{z} {\frac{{\partial^{2} u}}{{\partial z^{2} }}} + {\frac{{\partial u_{e} }}{\partial t}} $$
(5)

where u(z, t) = excess pore-water pressure at the position z and time t, C z  = coefficient of consolidation in vertical z-direction, u e (t) = imposed excess pore-water pressure at time t.

Fig. 2
figure 2

Clay layer a with permeable top and bottom b with permeable top and impermeable bottom

For the case of a haversine wave, as given by Eq. 3 and noting that u e  = L(t) and that \( {{{\partial u_{e} }}/{\partial t}} = {{{{\text{d}}L}}/{{{\text{d}}t}}}, \) the governing differential equation becomes:

$$ {\frac{\partial u}{\partial t}} = C_{z} {\frac{{\partial^{2} u}}{{\partial z^{2} }}} + {\frac{q\pi }{d}}\sin {\frac{2\pi t}{d}}. $$
(6)

It should be noted at this stage that the coefficient of swelling is assumed to be equal to that of consolidation for the purpose of this work. This is quite justified for over consolidated clays as well as for loading/unloading cycles of normally consolidated clays.

5 Analytical solution of governing differential equation

The governing differential Eq. 6 is a non-homogeneous partial differential equation. The solution of this differential equation consists of two parts. The first part of this solution represents the solution of the homogeneous differential equation, while the second part represents the particular integral of the non-homogeneous equation. It is worth mentioning that such an exact analytical solution could not be found in common references on advanced engineering mathematics [4, 10, 18]. However, such a solution is possible to obtain in terms of infinite series of eigenfunctions, but it is somewhat cumbersome to achieve at this stage and it will be devoted to another paper on this subject.

Therefore, it was decided at this stage to develop a numerical finite difference solution for this work to arrive at the behavior of the consolidation process under haversine loading.

6 Numerical solution of governing differential equation

To solve the governing differential equation, the implicit finite difference technique is to be used. For this purpose, the case of a clay layer with permeable top and permeable bottom (PTPB case), having a total thickness of 2H or a clay layer with permeable top and an impermeable bottom (PTIB case) having a thickness of H as shown in Fig. 2, is considered.

Four uniform intervals ∆z are to be used together with a uniform time step ∆t. Thus, the implicit finite difference approximation for the governing partial differential Eq. 6 becomes:

$$ {\frac{{u_{i,n + 1} - u_{i,n} }}{\Updelta t}} = C_{z} {\frac{{u_{i - 1,n + 1} - 2u_{i,n + 1} + u_{i + 1,n + 1} }}{{(\Updelta z)^{2} }}} + {\frac{q\pi }{d}}\sin {\frac{2\pi t}{d}} $$
(7)

where u i,n  = excess pore-water pressure at node (i) and time level (n), u i,n+1 = excess pore-water pressure at node (i) and time level (n + 1), u i−1,n+1 = excess pore-water pressure at node (i − 1) and time level (n + 1), u i+1,n+1 = excess pore-water pressure at node (i + 1) and time level (n + 1).

It can be shown easily that the above equation can be simplified to the following form:

$$ - \beta u_{i - 1,n + 1} + (1 + 2\beta )u_{i,n + 1} - \beta u_{i + 1,n + 1} = u_{i,n} + {\frac{q\pi }{{n^{ * } }}}\sin {\frac{\pi (2m - 1)}{{n^{ * } }}} $$
(8)

where

$$ \beta = {\frac{{C_{z} \Updelta t}}{{(\Updelta z)^{2} }}} = k^{2} \Updelta T_{v} $$
(9)

k = number of uniform intervals ∆z in H, T v  = dimensionless time factor = \( {{{c_{z} t}}/{{H^{2} }}} \), n* = number of uniform time intervals (∆t) within one cycle (d), t = actual time = mt, m = 1,2,3,…

Note that the imposed time-dependent loading was taken at the middle of the time step.

For the case of four uniform intervals ∆z within H (i.e. k = 4), the governing matrix equation becomes for q = unity:

$$ \left[ {\begin{array}{*{20}c} {1 + 2\beta \, } & { - \beta } & 0 & 0 \\ { - \beta } & {1 + 2\beta } & { - \beta } & 0 \\ 0 & { - \beta } & {1 + 2\beta } & { - \beta } \\ 0 & 0 & { - 2\beta } & {1 + 2\beta } \\ \end{array} } \right]\left[ {\begin{array}{*{20}c} {u_{1,n + 1} } \\ {u_{2,n + 1} } \\ {u_{3,n + 1} } \\ {u_{4,n + 1} } \\ \end{array} } \right] = \left[ {\begin{array}{*{20}c} {u_{1,n} + a\sin \,[a(2m - 1)]} \\ {u_{2,n} + a\sin \,[a(2m - 1)]} \\ {u_{3,n} + a\sin \,[a(2m - 1)]} \\ {u_{4,n} + a\sin \,[a(2m - 1)]} \\ \end{array} } \right] $$
$$ {\text{or}}\,{\text{A}}\,{\text{B}} = {\text{C}},{\text{B}} = {\text{A}}^{ - 1} \,{\text{C}} $$
(10)

where a = π/n*.

A = coefficient matrix =\( \left[ {\begin{array}{*{20}c} {1 + 2\beta \, } & { - \beta } & 0 & 0 \\ { - \beta } & {1 + 2\beta } & { - \beta } & 0 \\ 0 & { - \beta } & {1 + 2\beta } & { - \beta } \\ 0 & 0 & { - 2\beta } & {1 + 2\beta } \\ \end{array} } \right]. \)

B = vector of unknown quantities = [u 1,n+1 u 2,n+1 u 3,n+1 u 4,n+1]T.

C = vector of known quantities = [u 1,n  + S u 2,n  + S u 3,n  + S u 4,n  + S]T

$$ S = a\sin \,\left[ {a(2m - 1)} \right]. $$
(10a)

A−1 = inverse of the coefficient matrix.

7 Application

For the clay deposit shown in Fig. 2, the choice of a dimensionless time interval ∆T v of 0.025, together with k = 4, yields according to Eq. 9 a β-value of 0.4. For β = 0.4, k = 4 and n* = 6 (i.e. the period d is divided into six uniform time intervals), it can be shown easily that

$$ A = \left[ {\begin{array}{*{20}c} {1.8 \, } & { - 0.4} & 0 & 0 \\ { - 0.4} & {1.8} & { - 0.4} & 0 \\ 0 & { - 0.4} & {1.8} & { - 0.4} \\ 0 & 0 & { - 0.8} & {1.8} \\ \end{array} } \right], \, A^{ - 1} = \left[ {\begin{array}{*{20}c} {0.5852 \, } & {0.1378} & {0.3398} & {0.0076} \\ {0.1378} & {0.6202} & {0.1529} & {0.0340} \\ {0.0340} & {0.1529} & {0.6541} & {0.1454} \\ {0.0151} & {0.6800} & {0.2907} & {0.6202} \\ \end{array} } \right]. $$

Thus, the solution at any time t can be obtained easily using the inverse matrix given above.

Figure 3 shows the time variation of ‘excess’ pore-water pressure at the bottom of the clay deposit with permeable top and impermeable bottom given in Fig. 2.

Fig. 3
figure 3

Time variation of “excess” pore-water pressure at the bottom of a clay layer with permeable top and impermeable bottom

It is quite obvious that the ‘excess’ pore-water pressure builds up during the loading phase and changes to negative pore-water pressure during the unloading phase. This oscillation continues with some damping until a ‘steady’ state is achieved after about eight cycles. This can be supported by the fact that the ratio of positive amplitude of the first cycle of the excess pore-water pressure at the bottom of the PTIB case to that for the second cycle is about 1.136, while this ratio becomes, for example, about 1.048 for the ratio corresponding to the sixth’s and seventh’s cycle. Similarly, Fig. 4 shows the ‘excess’ pore-water pressure isochrones for the PTIB case considered for different values of the dimensionless time factor T v during the loading and unloading phases of the first cycle of the haversine loading. It is quite obvious that during loading, the excess pore-water pressure isochrones are positive changing gradually to negative isochrones during the unloading phase of the haversine loading. Note that the ‘excess’ pore-water pressure isochrones can be partially negative and partially positive. Figure 5 shows the time variation of the effective stress during the cycles studied. It is quite obvious from this figure that the effective stress increases, in general, with time but showing some light fluctuation (without changing sign) due to the loading–unloading phases of the cyclic loading. This means that the bearing capacity of the soil increases, in general, gradually with increasing number of cycles of the repeated loading. The rate of increase in effective stress is pronounced initially and dies out thereafter, and a steady state may be achieved after about 8 cycles.

Fig. 4
figure 4

“Excess” pore-water pressure isochrones for the PTIB case during the first haversine loading cycle

Fig. 5
figure 5

Time variation of effective stress at the bottom of a clay layer with permeable top and impermeable bottom due to haversine repeated loading

8 Effect of rest period

To study the effect of rest period on the one-dimensional consolidation process under repeated loading, the haversine loading wave shown in Fig. 6 is considered. It is obvious from this figure that the duration of the haversine loading–unloading phase is given by (d), while the rest period is given by (R). Thus, this repeated loading is a periodic function given in the fundamental period as follows:

$$ L(t) = \left\{ {\begin{array}{*{20}c} 0 & {{\text{for}}\,\,0 \le t \le {R}/{2}} \\ {q\sin^{2} {{\pi }/{d}}\left( {t - {R}/{2}} \right)} & {{\text{for}}\,\,{R}/{2} \le t \le d + {R}/{2}} \\ 0 & {{\text{for}}\,\,d + {R}/{2} \le t \le d + R} \\ \end{array} } \right.. $$
(11)
Fig. 6
figure 6

Haversine repeated loading with rest period (case R/d = 1)

The first time derivative of this loading function representing the rate of imposition of excess pore-water pressure can be written as follows:

$$ {\frac{{{\text{d}}L}}{{{\text{d}}t}}} = \left\{ {\begin{array}{*{20}c} 0 & {{\text{for}}\,\,0 \le t \le {R}/{2}} \\ {{{q\pi }/{d}}\sin {{2\pi }/{d}}\left( {t - {R}/{2}} \right)} & {{\text{for}}\,\,{R}/{2} \le t \le d + {R}/{2}} \\ 0 & {{\text{for}}\,\,d + {R}/{2} \le t \le d + R} \\ \end{array} } \right.. $$
(12)

Thus, the analysis of the one-dimensional consolidation process can proceed as before.

The same case treated earlier (see Fig. 2) was analyzed again but using the haversine loading wave given by Eq. 11 and shown in Fig. 6 assuming R/d = 1 to reveal the effect of rest period on the one-dimensional consolidation process.

Figure 7 shows the time variation of ‘excess’ pore-water pressure at the impermeable base of the clay layer for the case of a haversine loading with a rest period R = d. Included also in this figure are the corresponding data for the cases R/d = 0 and R/d = 2. Note that for the case of zero rest period, the loading/unloading time covers the whole cycle length, while for the case of a rest period R = d or R = 2d, the duration of loading/unloading becomes relatively short relative to the cycle length. Thus, the existence of an ‘effective’ gradient for longer time in the case of zero rest period when compared with that for non-zero rest period might explain why the positive excess pore-water pressure peaks in Fig. 7 increase with increasing R/d ratio. Thus, the increase in the rest period decelerates the consolidation process. It is also worth noting that the maximum absolute value of negative pore-water pressure becomes smaller by increasing the rest period.

Fig. 7
figure 7

Effect of rest period of haversine repeated loading on the time variation of “excess” pore-water pressure at the bottom of a clay layer with permeable top and impermeable bottom

However, the number of cycles required to achieve ‘stationary state’ decreases with increasing the rest period, as it is about 5 for the case of non-zero rest period compared with 8 for R = 0.

Figure 8 shows the effect of rest period on the time variation of effective stress. It is quite obvious from this figure that the effective stress increases with time but with more pronounced fluctuation when compared with the case of no rest period (R = 0). However, the maximum effective stress achieved decreases with increasing R/d ratio, indicating that the consolidation process becomes slower by increasing the rest period. It is also worth mentioning that for non-zero rest period, a ‘steady’ state is achieved after the fifth cycle, indicating that the rest period tends to decrease the number of cycles required to achieve the steady state.

Fig. 8
figure 8

Effect of rest period of haversine repeated loading on the time variation of effective stress at the bottom of a clay layer with permeable top and impermeable bottom

9 Conclusions

The main conclusions of this work can be summarized as follows:

  1. 1.

    Although the haversine loading is always positive, the ‘excess’ pore–water pressure developed during one-dimensional consolidation oscillates changing from positive to negative and vise versa. The absolute value of the amplitude of this excess pressure decreases gradually with time until a steady state is achieved.

  2. 2.

    Regarding the excess pore-water pressure and effective stress, a steady state is achieved after about eight cycles for the case of haversine repeated loading without rest period and after the fifth cycle for non-zero rest period.

  3. 3.

    The effective stress and hence the bearing capacity of the soil increase with time although showing some fluctuations but without changing sign. This fact is independent of the length of rest period.

  4. 4.

    The ‘excess’ pore-water pressure isochrones can be positive, negative or consisting of two parts, namely positive and negative.

  5. 5.

    An increase in the rest period of the haversine repeated loading decelerates the one-dimensional consolidation process. The maximum effective stress for non-zero rest period becomes much less than that for no rest period.

  6. 6.

    The number of cycles required to achieve the ‘steady-state’ conditions decreases with increasing the rest period. Five cycles are sufficient to achieve this state for a non-zero rest period.