Keywords

1 Introduction

Erosion of reservoir banks involves a complex relationship of processes that contribute to the occurrence of different problems related to physical issues directly in the affected areas, as well as social ones, such as the impacts on the activities resulting from human occupation. The main agents of erosion are the wave’s action, the surface runoff and the elevation of the water level (aquifer). Among these agents, the wave represent the most devastating erosive process and occurs mainly in large reservoirs, whose extensive surface area presents significant and propitious fetches to the generation of these waves.

In this work, the Simulating WAves Nearshore (SWAN) spectral wave model was applied on the right margin of Sergio Motta Dam Reservoir (Porto Primavera Dam), Brazil, to simulate waves generated by wind in the reservoir lake.

2 Study Area and Objectives

The Sergio Motta Dam Reservoir (Porto Primavera Dam) is located half way down the Paraná River, on the borders of the states of São Paulo and Mato Grosso do Sul, in Brazil, downstream of the Jupiá dam and upstream of the Itaipu dam (Fig. 1). The drainage area of the basin is 574,000 km2; the reservoir surface and capacity are 2044 km2 and 15.7 km3 respectively (Celeri et al. 2005).

Fig. 1
figure 1

Detail of the study area in the reservoir, where the Simulating WAves Nearshore (SWAN) spectral wave model was applied. Images show the geophysical survey around the breakwaters and the reservoir margin

Between 2009 and 2012 researchers from Brazilian Institute of Technological Research (IPT 2012) conducted several studies and developed an experimental project to protect banks from erosion caused by waves in the reservoir. Three different kinds of submerged breakwaters were installed in 2009, 1.0 km along the shoreline, in five stretches of 100 m length each and with an interval of 100 m between them (Fig. 2).

Fig. 2
figure 2

Types of breakwaters: a, c, e geotextile tube and concrete (sinuos and pyramidal); b, d, f the sonographic survey images show the installed configuration (multiple lines for concrete breakwater and single line for geotextile tube)

The objective of this study is to compare the surface wave modeling results with the performance of the breakwaters installed in the experimental area on the right reservoir margin (IPT 2012) and verify the behavior of the structures in a single side-by-side arrangement.

3 Materials and Methods

3.1 Model Set-Up

The grid implemented in the studied area was generated from the physical contours of the preexisting cartographic base (level contours and reservoir margin line). The grid was built using RFGRID tool of the Delft3D software package. Around the area of the submerged breakwaters the grid is more detailed (presents a higher resolution) in order to enable better representation of the structures. The breakwaters were reproduced in the model exactly in the same position and arrangement installed, according to the sonographic survey images, obtained in 2012. The final grid shows 12,389 cells, with horizontal resolution of 66 × 199 cells.

Bathymetry survey data collected in 2012 were projected onto the model grid using triangular interpolation of the survey points using the QUICKIN tool. The grid and bathymetry of the model are shown in Figs. 3 and 4. Two breakwaters were composed of concrete and the third one of geotextile tubes.

Fig. 3
figure 3

Delft3D model grid and submerged breakwaters contour

Fig. 4
figure 4

Bathymetry interpolated in the numerical grid with their depth and submerged breakwaters contours. 1—geotextile tube; 2—sinuous aligned; 3—pyramidal aligned; 4—sinuous multiple lines and 5—pyramidal multiple lines

The installation arrangements were: breakwaters, side by side, aligned in a single line for geotextile tubes and aligned in multiple lines for the breakwaters made of concrete. All breakwaters were submerged (water column of 0.80 m). The wave parameters were measured in the reservoir previously and the values adopted for the upstream dam model were the same as those specified for the experimental erosion control project, i.e. a 1.5 m wave height, with a period of 5 s. The wind speed used was 10 and 20 m/s with an incidence direction of 180°, considering the true South.

The structures were represented as Dam type obstacles. In this option, the model admits that the transmission coefficient depends on the condition of the wave incident on the obstacle as well as its height. The values used for the transmission coefficients α and β (used in the mathematical formulation when processing the modeling) were 1.8 and 0.1, respectively.

Wave simulations were performed for three scenarios: 1—margin without breakwater to obtain the initial wave condition in the studied section; 2—the same arrangements of breakwaters installed on a segment in the reservoir and 3—different arrangement from the original installed, with simulations for each structure, aligned side-by-side.

4 Results and Discussion

The simulation for scenario 1 considered significant wave heights (Hsig) varying between 0.8 and 1.3 m in the studied area, without structures. Scenario 2 represents the situation after the installation of the breakwaters and the wave heights were reduced to values between 0.6 and 0.8 m and 0.7 and 0.85 m; the winds velocities considered were 10 and 20 m/s, respectively (Fig. 5).

Fig. 5
figure 5

Results from scenario 2 simulation with wind speed of 10 m/s (a) and 20 m/s (b). The color bar shows the significant wave heights reduction (m) after breakwaters. 1—geotextile tube; 2—sinuous aligned; 3—pyramidal aligned; 4—sinuous multiple lines and 5—pyramidal multiple lines

The geotextile tube and pyramidal with multiple lines structures showed the best performance in reducing the significant wave height, with rates of 42%.

Some points were chosen in the numerical grid to measure the values of significant wave heights after the breakwaters for the scenario 2 simulation. The values are show in Table 1.

Table 1 Significant wave height and reduction in the s values (%) obtained in scenario 2

The simulations for scenario 3 considered a different arrangement from the original installed. Only one structure was simulated at a time, repeated side by side in the same extension area.

The significant wave height reduction was evaluated in sections behind the breakwater (considering a grid cell behind the breakwater inside the final grid).

The results show that all the breakwaters, even individually, have reduced the significant wave heights from 1.2 m to values between 0.6 and 0.8 m (Fig. 6 and Table 2).

Fig. 6
figure 6

Significant wave height reduction considering the breakwaters for scenario 3 simulations (wind speed of the 10 m/s). Breakwaters: a sinuous concrete in multiple lines and in a single line; b pyramidal concrete in multiple lines and in a single line; c geotextile. Values displayed on the scale (0.0–0.6 m) show how much the incident wave height has been reduced after the breakwater (difference between the scenarios with and without breakwaters)

Table 2 Significant wave height reduction values (%) obtained in scenario 3

5 Final Considerations

The Simulating WAves Nearshore (SWAN) spectral wave model was applied to simulate waves generated by wind in the reservoir lake of Porto Primavera, Brazil. The results obtained with this study were satisfactory and show the model efficiency in this sort of study. The more significant wave height (m) reductions were obtained whit the geotextile tube and the pyramidal concrete breakwaters (42% of reduction). These results are similar to those verified in the breakwaters installed in reservoir margin and in the hydrodynamic laboratory tests performed at the Institute for Technological Research (Instituto de Pesquisas Tecnológicas—IPT).

Each breakwater has a specific configuration, with different shapes and sizes. When installed side-by-side their performance in response to incoming waves may be adversely affected by their structural differences and different wave incident directions. Simulations for only one type of breakwater, aligned, at first, exhibited better performance when compared to the original configuration installed (different types side-by-side) in the reservoir margin. Even in the individual configuration, differences in performance are observed in the reduction of significant wave height, because the structures are submitted to different wave spectra, with different energies. Breakwaters simulations are recommended prior the implementation in the reservoirs should be considered as an alternative, as it assists in the best planning and management of the work that will be performed, and thus also minimizing costs.