1 Introduction

The execution of maintenance tasks in distribution networks by the power utilities is an important action for managing its assets to enhance the reliability and availability indices of the power energy supply. In the determination of maintenance plans of an equipment, must be taken into account the most suitable maintenance task and the past time since its last performed repair more its physical and operational condition and life cycle (State Grid 2011). The maintenance plan must be determined by considering the status of all equipment in the distribution network because the maintenance plan that is determined by the set of the best individual plans for each equipment cannot be optimum. An efficient maintenance plan to distribution systems is achieved using the coordinated maintenance over all the equipment and their physical and operational conditions for optimally allocating available financial resources.

Distribution networks are vulnerable to different types of failures, which can be internal failures at equipment itself, or failures due to external threats dependent on weather conditions such as wind, lightning and thunderstorms. External-caused failures reduce the equipment life cycle by increasing the frequency of maintenance tasks that result in growth of costs to power distribution utilities.

The realization of preventive maintenance tasks can be used to attenuate the impacts of nature actions and/or equipment aging with the objective to improve the service availability of power energy supply. However, the global cost of this countermeasure can raise the price of this service to values that are unfeasible without the guarantees of uninterrupted power energy supply. Furthermore, the demand for high-quality services (with low interruption indices), which are supervised by regulating agencies, requires that power distribution utilities invest in maintenance programs to preserve the reliability of their networks. In this way, utilities always looking for feasible solutions, technically and economically, able to improve power network reliability. The planning of centered reliability maintenance tasks, which is employed by general electricity industries, is an emerging technique to create feasible maintenance plans able to preserve operational availability of devices and equipment in power energy distribution system (PEDS) by minimizing costs of maintenance tasks and enhancing reliability indices.

Mathematical models and solution techniques for determining centered reliability maintenance plans of equipment in distribution system have been proposed in specialized literature. In Huang et al. (2004), it is proposed a mathematical model to schedule maintenance tasks of distribution network equipment using an objective function to minimize the maintenance costs and financial losses due to energy supply interruptions. In the maintenance optimization model proposed by Li and Brown (2004), the objective function minimizes the average value weighted by the distribution system reliability index. In Yeddanapudi et al. (2008), it is defined the entire risk of the distribution system interruption and development of a coordination model of maintenance resources as an objective function to maximize the risk reduction after the realization of maintenance tasks.

In Piasson et al. (2016), it is proposed a multi-objective optimization model to schedule-centered reliability maintenance tasks in distribution systems. The objective functions model mathematically the costs related with the different maintenance levels of the distribution system equipment and network reliability in analyzed planning horizon. The model constraints are: (a) expected values of availability indices like the system average interruption frequency index (SAIFI) and system average interruption duration index (SAIDI) for each set of consumers; (b) available time in hour for maintenance crews; (c) number of maintenance tasks specified to every type of network equipment and device. The multi-objective genetic algorithm, non-dominated sorting genetic algorithm (NSGA-II), is proposed in the solution of the mathematical model. A binary optimization model to determine the optimum plan of maintenance tasks for each distribution system equipment is proposed in Sittithumwat et al. (2004). The objective is the minimization of the SAIFI index in the main feeder branch. The model constraints are the amount of financial and human resources available to perform maintenance tasks in analyzed planning horizon. In tests with a generic feeder, it is taken into account a constant failure rate and variable failure rate over maintenance tasks for every system equipment that are modeled as fuzzy sets.

A multi-objective optimization model to determine the maintenance plan in distribution system is proposed in Hilber et al. (2007). This model considers annual expected costs of energy supply interruption to consumers and maintenance costs in distribution network (preventive and corrective maintenances). These two objective functions are combined through weighting technique to yield a single-objective function. Availability indices of the energy supply service are not considered in the model that is assumed static, i.e., it is not extended to analysis of failure behavior along time under performed maintenance tasks. The failure rates of equipment are dealt as constant. The relation between system equipment and their reliabilities is examined through an index that matches to expected total interruption costs to consumer in a time interval of one year. Three maintenance task levels are taken into account. The effects of each maintenance task over reliability of network equipment are not totally analyzed. The proposed model is tested under a test system with 178 equipment including circuit breakers, cables, transformers, bus and fuses. The employed solution technique is a particle swarm optimization (PSO) metaheuristic. In Usberti et al. (2015), it is proposed a mathematical bi-objective optimization model that considers costs of maintenance activities and the maximum value for a system average interruption frequency index in planning period. This multi-objective problem, named maintenance resources allocation problem (MRAP), is to define the best compromise of maintenance policies for the network at local and global levels for a given period. The MRAP problems are solved using the concept of ε-constraint by a hybrid genetic algorithm. The solution of these problems provides local solutions and associated trade-off curve. These solutions are optimally combined to solve a global-level multiple criteria optimization problem, revealing the local efficient solutions and associated trade-off curves for a group of networks, providing information to assess the decision on maintenance activities in the network management. Results are presented to one illustrative example and a real-life case study.

The heuristic procedure to specify strategies of maintenance tasks in distribution systems, which satisfy the predefined objectives of availability and reliability indices of power supply service, is proposed in Dehghanian et al. (2013). The strategies of maintenance tasks are ranked based on trade-off between costs and benefits and on exploration of system operator and specialist knowledge.

In this work, it is proposed a generic mathematical model of multi-objective optimization and to solve it, the NSGA-II that provides the plans of centered reliability maintenance task for different equipment of distribution network in different time of the planning horizon. The achieved results allow for distribution utility planning sector to make decisions in order to optimize the use of human and financial resources by indicating which equipment and feeder sections should undergo to different types of maintenance tasks and which maintenance crews should be dispatched to each scheduled task. The mathematical model is comprised by two objective functions: one for modeling the costs of maintenance tasks and another for modeling the system unreliability (unreliability is defined as being the reliability complement), relating their reliability indices per performed maintenance task. The model constraints are system interruption duration and frequency (DIC and FIC) indices per consumption unit, assets’ devaluation of equipment comprising the system and available time of maintenance crews.

The contribution of this work is as follows: (1) A multi-objective model is proposed to schedule maintenance tasks in overhead and radial distribution networks that provides a set of non-dominated solutions aiding the decision making according to requirements and conditions of financial resources of power distribution utilities; (2) the constraints, which take into account the availability indices, are needed to power distribution utilities avoid the fine payment and preserve its image to the consumers; (3) the proposed model requires a reduced database and deals with the failure indices due to the use condition of equipment and devices in distribution network; (4) unlike many literature works, failure external factors related to the adverse weather conditions are taken into account to obtain the reliability in each feeder section, making easy the integration of proposed model with the geographic information system present in modern PEDS; (5) the consideration of the failure rate per component, which is updated over the planning horizon, makes the model constraints simplified, reducing its computational complexity. In comparison with Piasson et al. (2016), the coding of the solutions to the problem has been restructured to reduce the memory capacity required for its storage and to give speed and robustness to the algorithm. In this version of the NSGA-II algorithm, variable recombination and mutation rates are used during their generational cycle.

This paper is organized as follows: Sect. 1 presents the introduction conception about centered reliability maintenance task and literature review; Sect. 2 presents the definition of reliability and failure rates of equipment installed in the distribution network and hypothesis needed to propose a generic multi-objective optimization model for solving the problem of centered reliability maintenance task planning; Sect. 3 presents the proposed methodology to solve the multi-objective optimization model, i.e., the NSGA-II metaheuristic; Sect. 4 presents the achieved results in tests with the computational implementation of proposed methodology in a generic power system to show the robustness and efficiency of proposed solution technique; and Sect. 5 presents the conclusions about achieved results and the proposed methodology.

2 Methodology

In maintenance task planning is taken into account the following network equipment: capacitor banks (BC), sectionalizing switches (CHM), protection switches (CHP) like circuit breakers, fuses and automatic reclosers, distribution transformers (TR), voltage regulators (RT) and primary cable (LN), which includes the feeder and branch conductors, crosspieces and isolators of poles in every section of the primary network. Every equipment can have different types of failure that affect the power system in different ways. This work always deals with the worst scenario to the power system with the failure occurrence over its equipment, i.e., it takes into account a partial, or full, interruption of power energy supply after a failure event (Horton et al. 1990). This approach aims to establish the interruption maximum cost which permits a better analysis of trade-off between costs and benefits of established maintenance plans. For example, if a scenario is expected due to event failure of equipment but other more favorable scenario happens, then the benefits of maintenance task planning are maximized because the trade-off between cost and benefit of established maintenance plan is available to the worst scenario. On the other side, if a favorable scenario is expected but another worst scenario happens, then the cost should raise in comparison with benefits of maintenance plan what can make its execution unfeasible.

In this way, every network equipment can undergo to four levels of maintenance task. These levels are defined as: m1 to the absence of maintenance tasks; m2 as minimum maintenance; m3 as full maintenance; and m4 to the equipment replacement. The m4 maintenance task most severely affects the reliability of equipment and distribution network. The full maintenance task, m3, can recover the reliability of equipment as much as the maintenance task of m4 level, but at a lower cost. Despite the cost, the maintenance task of level m4 still is better because equipment can be out of their economic life cycle and, hence, the replacement by new equipment must be most feasible in a general perspective of the cost–benefit ratio.

2.1 Reliability General Concepts

The most important variable to determine the equipment reliability is the failure rate. In this work, it is assumed that degradation of PEDS equipment is monthly and modeled through parameters that are named as failure rate multipliers. These multipliers determine the expected variations of the equipment failure rate in a certain time period according to programmed maintenance tasks and to their values in previous period. In this way, it is needed to take into account the initial value of failure rate to compute the equipment failure rate in planning horizon of maintenance optimization model. In Horton et al. (1990), the typical values of failure rate for each type of equipment in underground urban network of PEDS are estimated. In Table 1, it is presented the typical values of annual failure rates for transformers, reclosers, fuses and urban feeder cables.

Table 1 Typical values of failure rate for equipment of overhead power distribution system

In the determination of initial failure rates of distribution network equipment (\(\lambda_{e}^{{t_{{{\text{initial}}}} }}\)), it is used the typical values of failure rate (\(\lambda_{e}^{{{\text{typical}}}}\)), as is presented in Table 1, through (1):

$$ \lambda_{e}^{{\mathop t\nolimits_{{{\text{initial}}}} }} = \delta_{e}^{m} \lambda_{e}^{{{\text{typical}}}} $$
(1)

The equipment in real-world distribution networks is in different stages of degradation depending on their age or number of maintenance task preformed, Sittithumwat et al. (2004), IEEE Std. 493-1997 (1998), Usberti et al. (2015) and State Grid (2011). Through (1), it is generated the initial values of failure rates to simulate the possible states of conservation for each equipment of the PEDS. In this way, failure rates are updated where the typical failure rate of an equipment is updated by multiplying the lowest level failure rate (no maintenance) by the time in which the equipment remains without maintenance tasks (tsm). This procedure simulates the degradation that happens in equipment of the PEDS in a certain time interval.

2.2 Mathematical Model

The objective functions of mathematical model are the total costs of maintenance tasks (2) and system unreliability (3). The f2 value is arithmetic mean of unreliability partial index obtained for each time interval, t, of the planning horizon, ph. This value is the average of fault probabilities for each feeder section, weighted by active power loads \(P_{s}\) in the sth feeder section. The lower the value, the better the expected system reliability. In computation of f1, the cost of each maintenance activity, \({\text{Cos}} t\left[ {x_{(e,m)}^{t} } \right]\), for each piece of analyzed equipment, e ∈ E, is updated through the interest rate r because of inflationary expectations:

$$ \begin{aligned} & {\text{Min:}} \\ & \quad f_{1} = \sum\limits_{t = 1}^{ph} {\sum\limits_{e = 1}^{E} {{\text{Cos}} t\left[ {x_{(e,m)}^{t} } \right]\left( {\frac{1}{1 + r}} \right)^{t} } } \\ \end{aligned} $$
(2)
$$ f_{2} = \frac{1}{ph}\sum\limits_{t = 1}^{ph} {\left[ {\frac{{\sum\limits_{s = 1}^{S} {\left( {1 - C_{s} (t)} \right)P_{s} } }}{{\sum\limits_{s = 1}^{S} {P_{s} } }}} \right]} $$
(3)
$$ \begin{aligned} & {\text{Subject to:}} \\ & \quad {\text{DIC}}_{{{\text{month}}}} (t) \le {\text{DIC}}_{{{\text{month}}}}^{\min } \\ \end{aligned} $$
(4)
$$ {\text{DIC}}_{{{\text{quarter}}}} (t) \le {\text{DIC}}_{{{\text{quarter}}}}^{\min } $$
(5)
$$ {\text{DIC}}_{{{\text{year}}}} (t) \le {\text{DIC}}_{{{\text{year}}}}^{\min } $$
(6)
$$ {\text{FIC}}_{{{\text{month}}}} (t) \le {\text{FIC}}_{{{\text{month}}}}^{\min } $$
(7)
$$ {\text{FIC}}_{{{\text{quarter}}}} (t) \le {\text{FIC}}_{{{\text{quarter}}}}^{\min } $$
(8)
$$ FIC_{year} (t) \le FIC_{year}^{\min } $$
(9)
$$ \sum\limits_{e = 1}^{E} {{\text{TMP}}\left[ {x_{(e,m)}^{t} } \right]} + {\text{TMD}}_{e} \left[ {x_{(e,m)}^{t} } \right] + {\text{TME}}\left[ {x_{(e,m)}^{t} } \right] \le T_{{{\text{fact}}}} $$
(10)
$$ T_{e} + t - Tv_{e} \ge 0 $$
(11)
$$ \sum\limits_{t = 1}^{ph} {x_{(e,m)}^{t} } \le M_{e} $$
(12)

where

$$ {\text{DIC}}_{{{\text{month}}}} (t) \le {\text{TME}}\left[ {x_{(e,m)}^{t} } \right] + \left[ {1 - C_{s} } \right]{\text{TMAE}} $$
(13)
$$ {\text{FIC}}_{{{\text{month}}}} (t) \le x_{(e,m)}^{t} + [1 - C_{s} ] $$
(14)
$$ {\text{DIC}}_{{{\text{quarter}}}} (t) \approx \frac{1}{{k_{{{\text{quarter}}}} {\text{DIC}}}}\sum\limits_{t = 1 + 3(q - 1)}^{3q} {{\text{DIC}}_{{{\text{month}}}} (t)} $$
(15)
$$ {\text{FIC}}_{{{\text{quarter}}}} (t) \approx \frac{1}{{k_{{{\text{quarter}}}} {\text{FIC}}}}\sum\limits_{t = 1 + 3(q - 1)}^{3q} {{\text{FIC}}_{{{\text{month}}}} (t)} $$
(16)
$$ {\text{DIC}}_{{{\text{year}}}} (t) \approx \frac{1}{{k_{{{\text{year}}}} {\text{DIC}}}}\sum\limits_{t = 1 + 12(y - 1)}^{12y} {{\text{DIC}}_{{{\text{month}}}} (t)} $$
(17)
$$ {\text{FIC}}_{{{\text{year}}}} (t) \approx \frac{1}{{k_{{{\text{year}}}} {\text{FIC}}}}\sum\limits_{t = 1 + 12(y - 1)}^{12y} {{\text{FIC}}_{{{\text{month}}}} (t)} $$
(18)
$$ C_{s} = \prod\limits_{i = 1}^{Ns} {Cs_{{{\text{consi}}}} } $$
(19)
$$ Cs_{{{\text{consi}}}} (t) = e^{{ - (\lambda_{{{\text{consi}}}}^{s} )}} $$
(20)
$$ \lambda_{{{\text{consi}}}}^{s} = \lambda_{{{\text{main}}}}^{s} + \lambda_{{{\text{quarter}}}}^{s} $$
(21)
$$ \lambda_{{{\text{main}}}}^{s} = \sum\limits_{{e \ne {\text{main}}}}^{{E_{s} }} {\lambda_{e} } $$
(22)
$$ \lambda_{{{\text{external}}}}^{t} = \lambda_{{{\text{tree}}}}^{t} + \lambda_{{{\text{wind}}}}^{t} + \lambda_{{{\text{thunderbolt}}}}^{t} + \lambda_{{{\text{lightning}}}}^{t} $$
(23)
$$ \lambda_{{{\text{eq}}}}^{t} = \lambda_{e}^{t} + \lambda_{{{\text{external}}}}^{t} + \lambda_{{{\text{disc}}}}^{t} $$
(24)
$$ \lambda_{{{\text{eq}}}}^{t + 1} = \delta_{e}^{m} \lambda_{{{\text{eq}}}}^{t} $$
(25)

The constraints’ sets shape the acceptable limits of reliability indices that are established by regulating agencies. In the Brazil, these indices are the monthly, quarterly and annual DIC and FIC as is, respectively, given by (4), (5), (6), (7), (8) and (9); monthly average time available to the utility maintenance crews (10); system equipment, or asset, devaluation (11); and maximum number of maintenance tasks that are allowed for each system equipment (12).

In the calculation of monthly indices, such as DIC and FIC, are considered, respectively, the average time spent by maintenance crews in the execution of a maintenance task that provokes the power energy supply interruption to consumer groups and possible interruptions from fault external in the feeder section and main branch, as in (13) and (14). The calculation of quarterly and annual availability indices is an approximated value from monthly indices in concordance with (15), (16), (17) and (18).

The reliability of any sth feeder section that is limited by protection, or sectionalizing switches, depends upon of reliability index of all consumers’ groups that are connected in this feeder section (19), from the lateral branches and the main feeder branch. The reliability of ith consumer is calculated through a probability density function of Poisson (20), which is the reliability function for distribution transformers, oil switchgears and main feeder branch (21), where the main branch is comprised by all equipment with exception of transformers (22).

The failure rate of a feeder section is comprised by failure rates due to action of external threats (fault rate due to contact of vegetation in the network, wind, thunderstorms and lightning) (23) and by power energy supply loss in substation achieving; thus, the total failure rate as in (24) provides a more realistic behavior of reliability level for equipment installed in PEDS.

3 Solution Technique

The problem model (2)–(12) has a complex nature and is hard to be solved through classical optimization techniques. Among solution techniques found in the literature to solve this type of problem, the NSGA-II has been highlighted as a standard approach to solve multi-objective optimization problem that is very well known due to two important mechanisms of selection operation: fast non-dominated sorting and the crowding distance (Deb et al. 2002). In Fig. 1, it is presented the flowchart of implemented algorithm. The next subsections depict the computational implementation details of some particular stages of this algorithm to solve the proposed mathematical model as given in (2)–(25).

Fig. 1
figure 1

Flowchart of the implemented NSGA-II algorithm

3.1 Coding of the Decision Variables

The chromosome, or representation to a solution of determined maintenance planning, is displayed in Fig. 2. To a given set of equipment E and assuming that for each equipment e of this set there is a set of Me feasible maintenance tasks in the time period t ϵ ph, then every decision making can be modeled by an integer variable representing the set of feasible maintenance tasks, as is given in (26) where “1” means the lowest level (no maintenance) and “3” the highest level (full maintenance), while “4” is the replacement of equipment by new one:

$$ x_{(e,m)}^{t} = \left\{ {m|m = 1,2,3 \vee 4} \right\} $$
(26)
Fig. 2
figure 2

Chromosome coding

3.2 Selection Operator

In NSGA-II, the selection operator uses two specialized mechanisms: fast non-dominated sorting and crowding distance. The fast non-dominated sorting comprises random selection of two, or more, non-dominated solutions located in the Pareto front. The crowding distance operator is applied in estimation of density at solution set that are near to a particular solution of a population in the same Pareto front. To determine this distance, it is computed the smallest distance among analyzed solution, ri, and solutions that belong to set of solution of its neighborhood, for each objective of mathematical model. This distance works as a size estimative of the largest cuboid that includes the solution ri without the inclusion of any solution of population. A solution ri, which is the multi-objective optimization problem solution, overtakes other solution rj whenever:

  • The solution ri is located in a Pareto front below of solution rj; then, ri < rj;

  • Both solutions belong to same Pareto front, but the solution ri has larger crowding distance than rj and, hence, di > dj.

3.3 Genetic Operators

The mutation and crossover rates are variables during the generational cycle of NSGA-II, according to (27) and (28). The initial (\(\rho_{{\text{i}}}\)) and final (\(\rho_{{\text{f}}}\)) mutation and crossover rates are previously specified as well as the iteration number (iter), total number of generations (ng) and value of damping coefficient (\(\beta\)):

$$ \rho_{{{\text{mut}}}} = \rho_{{\text{i,mut}}} + \rho_{{\text{f,mut}}} e^{{\frac{{ - {\text{iter}}}}{{\beta {\text{ng}}}}}} $$
(27)
$$ \rho_{{{\text{cros}}}} = \rho_{{\text{i,cros}}} + \rho_{{\text{f,cros}}} e^{{\frac{{ - {\text{iter}}}}{{\beta {\text{ng}}}}}} $$
(28)

4 Test and Results

The NSGA-II is implemented in general-purpose programming language C+ + . The evaluation of proposed mathematical model and solution technique is performed by analyzing the performance of maintenance plans that are achieved under a distribution test system with 154 equipment.

4.1 Test System

The test system is a feeder with 58 transformers, two voltage regulators, one capacitor bank, one sectionalizing switch, nine fuses, two maneuver switches, 80 cables and one circuit breaker. In “Appendix,” Table 6 shows the data of test system. The topology of the test feeder is shown in Fig. 6. All equipment can be subjected to four maintenance levels, and the planning horizon has 2 years.

4.2 Parameters of the Mathematical Model and NSGA-II

The costs of equipment maintenance tasks are presented in Table 2. These values are mean costs for each type of equipment since, in general, the maintenance costs of every equipment depend on its particular features like manufacturer, nominal power, etc.

Table 2 Cost of maintenance tasks by equipment class (US$)

The failure rate multipliers are equivalent to impacts of maintenance tasks in the equipment reliability. For each equipment are defined four failure rate multipliers, as is given in Table 3, in which the first multiplier (\(\delta_{1}\)) characterizes the degradation due to the absence of maintenance tasks, while the fourth (\(\delta_{4}\)) is equivalent to the replacement of the equipment by new one. The failure rate multipliers to protection and maneuver switches are the same because defects in mechanisms of these equipment affect the network reliability in a similar way and their maintenance tasks comprise basically the visual inspection, components replacement or replacement by new equipment at the end of cycle life, according to ANEEL (2000).

Table 3 Equipment multiplier parameters of failure rates

In Table 4, it is presented the parameters that are used in the execution of NSGA-II and they were adjusted through exhaustive experiments.

Table 4 Parameters of the NSGA-II

4.3 Test Conditions

The network equipment is grouped in feeder sections that allow for isolating the permanent faults in one, or many, simultaneous sections reducing, thus, the number of consumers affected by a fault. This distribution network grouping in feeder section is based on location of protection, and/or maneuver switches that are operated in restoration of the power energy supply to consumers in feeder sections adjacent to a section under fault.

4.4 Achieved Results

The obtained result is presented in Fig. 3 in which the optimum problem solution of maintenance task planning in power distribution network is the set of non-dominated solutions in the first Pareto front (rank1). This front is comprised by the set of non-dominated solutions by initialing in zero cost, without the realization of any maintenance task in distribution network, and by ending in cost needed to replace the most part of network equipment. In a detailed analysis of these results, it is assessed the following set of solutions: “P1” indicates the absence of investment in maintenance tasks; “P3” reveals the maximum investment in maintenance tasks; and “P2” provides the intermediary point. In each one of these solutions, it is verified the progression of the monthly cost of maintenance task (Fig. 4) and the monthly variation of system reliability (Fig. 5).

Fig. 3
figure 3

Pareto front

Fig. 4
figure 4

Monthly cost variation of maintenance tasks that refers to selected solutions in the Pareto front

Fig. 5
figure 5

Variation of reliability indices due to realization of maintenance tasks provided by solutions P1, P2 and P3

In Fig. 5, it is verified that in initial period the distribution network has a very low reliability index, around 0.34, indicating the distribution network vulnerability against interruption events what requires effective countermeasures of maintenance to improve the reliability. Consequently, a large amount of financial resources is needed and must be available in the first months to perform the maintenance tasks (Fig. 4).

The planning of maintenance tasks necessary for each equipment of distribution network in planning horizon for solution “P2” requires a total of 88 maintenance tasks that are divided into three levels: 54 maintenance tasks of level two; 24 of level three; and 11 of level four.

In every feeder section with an amount of consumer groups, one fault in anyone of their equipment activates the protection switches causing the power energy supply interruption to all their consumers. By assuming, the distribution network is comprised by a main feeder branch that provides energy to lateral branches. The fault incidence in a feeder section of the main branch causes the action of its protection devices opening the switches, and, thus, most part of the distribution network remains without power energy supply. Then, it is important to prioritize the feeder sections that comprise the main branch of overhead radial distribution network in the execution of maintenance tasks.

In Fig. 6, the test system is divided into 13 feeder sections limited by protection and maneuver switches where section #1 and section #7 comprise the network main branch and the others are lateral branches. In Table 5, the plans of maintenance tasks to the section #1 referent to the solution “P2” of the Pareto front are presented, while Fig. 6 displays the equipment where must be performed scheduled maintenance tasks according to Table 5. The red colored cycles correspond to the execution of maintenance tasks in branches (LN, CHP, RT, CHM), and blue colored cycles comprise the execution of maintenance tasks in load nodes (TR, BC).

Fig. 6
figure 6

Scheduling of maintenance tasks for the test system

Table 5 Maintenance tasks in the equipment of section #1

The computational cost to achieve results with good quality to this test system with 154 equipment is obtained by spending 1,826 s of computational processing or approximating 30 min. The computer-implemented algorithm is processed using a personal computer with Intel Core i7 processor and 8 GB of RAM.

5 Concluding Remarks

In the proposed formulation, the objective functions are modeled by taking into account the full topology of the distribution network and focusing on achievement of maximum reliability with lower investment cost. In this way, the interruption time of consumers is reduced and reliability and availability indices of power energy supply service are improved. The proposed methodology obtains a set of optimized solutions which allow for developing, with safety and economy, the planning of maintenance tasks in overhead power distribution networks. The achieved solutions provide network reliability diagnostic over its life cycle that is favorable to do better decision making.

The integer coding system, the selection operators by dominance level, the crowding distance and the adaptive operators of crossover and mutation guaranty the efficient performance and convergence of the implemented NSGA-II algorithm for obtaining the optimized Pareto convex curve to planning of maintenance tasks with suitable reliability levels.