Abstract
In recent years, Building Information Modeling (BIM) has garnered a great deal of interest due to its benefits in design, generating construction schedules, and monitoring of the building process. In Vietnam, the creation of a construction plan depends on the knowledge and experience of designers, and typically these schedules are created manually. This study proposes a framework for developing a tool with features that suggest construction schedules based on created 3D-BIM models to achieve a fully automated and efficient design process. The framework integrates digital graphic information of building information modeling (BIM) with construction and schedule data, producing construction activity sequences pertinent to each other and the proposed building design. The expected results of conducting research according to this framework are the visible geometric representation and engineering data are merged into a single database that project managers can use to examine and modify the schedule effectively. As a result, resource-intensive activities can be reduced and productivity can be increased.
Access provided by Autonomous University of Puebla. Download conference paper PDF
Similar content being viewed by others
Keywords
- Building information modeling
- Construction schedule
- Automation generation
- Optimization algorithms
- IFC standard classifications
1 Introduction
The industry of architecture, engineering, and construction (AEC) have seen a significant increase in projects, particularly in developing nations like Vietnam. This industry has contributed significantly to each country’s gross directed product (GDP). Besides that, the construction section, which consumes many workers and resources, has been facing potential problems regarding wasting time and cost if construction managers cannot control construction projects effectively.
Building Information Modeling (BIM) has been developed and applied in various aspects of the construction industry with many clear benefits. In addition, BIM contributes throughout the life cycle of construction projects, from initial planning to project completion. Although most respondents viewed BIM as a multidisciplinary tool, their remarks indicated that interoperability concerns between the different BIM platforms in the industry still remain [4]. The majority of survey respondents (91%) felt that the best stages for adopting BIM in sustainable design and construction were schematic design (40%), predesign/program (31%), and design development (20%).
Planning and scheduling play crucial roles in the delivery of a project by optimizing the time and cost components of project management. Specifically, these tasks take a great deal of time and frequently relies on the knowledge and experience of schedulers to generate schedules for construction activities. However, most schedulers generate construction schedules manually, and it takes time to create and adjust them to achieve expected needs. Besides, schedulers conduct construction sequencing design in separate steps, or even other individuals generate it. As a result, there is a need to consume more time to finish them under pressure from relevant parties. Therefore, this study is conducted to present a framework to create a process of automated generation of construction schedules based on 3D Revit models via industry foundation classes (IFC) standard classification and optimization algorithms.
2 Literature Review
Decades of research have gone into the development of automated schedule generation; some of these methods are as follows: knowledge-based, algorithm-based, and model-based approaches.
2.1 Knowledge-Based Scheduling Approach
Several studies were conducted on generating construction schedules; the knowledge-based scheduling approach was designed based on sharing and reusing successful project templates from the past to avoid scheduling difficulties that may arise with repetitive projects [10]. In addition, a system designed to demonstrate the feasibility of producing project schedules from construction templates [6].
2.2 Algorithm-Based Scheduling Approach
Various strategies were employed to address scheduling issues. In the construction industry, the most prevalent algorithm is the Genetic Algorithm (GA). In the 1970s, John Holland developed the Genetic Algorithm, an enhanced heuristic search strategy [9]. It is very beneficial for solving dynamic construction schedule issues. This method is, in principle, inspired by the evolution of natural population genetics, in which it selects the most compatible chromosomes and causes them to mate and cross-pollinate proportionally to form new generations. Selvam and Tadepalli [12] utilized Genetic Algorithm, a programming-based meta-heuristic that modifies methods for scheduling the critical path.
2.3 Model-Based Scheduling Approaches
Widespread adoption has occurred for model-based procedures, which often relate to using model information to carry out advanced operations [5]. This category of techniques enables users to study and manipulate model data to create a schedule and 4D views. This approach may be divided into Computer-Aided Design (CAD)-based methods and BIM scheduling components. On the basis of the integration of a product model, a process model, and complementary information technology (IT) solutions, conducted research is to develop viable new approaches for modeling scheduling activities in the context of building [11].
CAD allows rapid model creation, modification, and analysis. It also has advanced features like 3D visualization, basic calculations, and recording the building's materials, measurements, and positions. CAD-based scheduling methods were developed from these skills. BIM systems feature more advanced functionality like conflict detection, cost calculation, energy analysis, and quantity take-offs than CAD platforms because they contain data-rich, object-oriented models. BIM systems can also integrate with other applications or include add-in tools.
2.4 BIM Technology for the Design Stage
Various studies have researched different benefits of BIM technology and indicate the effectiveness of BIM tools applied in many aspects of construction projects. Typically, designers use Revit to create 3D building models and generate construction schedules related to 3D models in Naviswork. Many studies are conducted to indicate the advanced applications of these tools; however, there is a need for automated generating construction planning.
Moreover, industry foundation classes (IFC) models define geometric shapes, relationships, processes, materials, performance, and other attributes essential for the design, production, construction, and maintenance of buildings using attribute, relationship, attribute set, and quantitative parameter definitions [2]. IFC model libraries are digital representations of standard design components like beams, plates, and columns and resources like steel bars, sand, and building equipment. In addition, IFCs make models reusable, portable, and interoperable [3], and provide a plausible foundation for mapping and exchanging design and construction data within the context of BIM.
2.5 Related Work
The construction industry is rapidly advancing, particularly in the use of Building Information Modeling (BIM) and optimization algorithms. BIM provides a digital representation of a building, and optimization algorithms can help find the best scheduling solution while considering constraints. Several academic studies have been conducted to explore the potential benefits of using BIM and optimization algorithms to generate construction schedules, but there are also limitations and challenges to address as Table 1.
3 Methodology
This study proposes a research framework to develop a construction schedule recommendation tool based on the 3D BIM model and IFC classification, as shown in Fig. 1, and detailed described as follows.
Step 1: Problem Definition: Define the problem and the study's objectives precisely. This includes knowing the construction schedule's needs, such as the required level of detail and the limits that must be considered.
Step 2: Literature Review: Conduct a literature review to obtain information on comparable studies and to establish the current state of knowledge in this field. This includes investigating the application of IFC standard classifications, optimization algorithms, and other pertinent tools and techniques.
Step 3: Data Collection: Collect data from the 3D Revit models that will be used in the research. This data should include information about the models’ items, including their location, size, and purpose.
Step 4: Data Preprocessing: Prepare a data structure that may be used for optimization by preprocessing the data received from the 3D Revit models. This may require converting the data into a format compatible with the optimization algorithm and cleaning or altering the data to eliminate any flaws or inconsistencies.
Step 5: Implementation of IFC Standard Classifications: Implement the IFC standard classifications on the data structure to be compatible with other building information models and can be readily connected with other systems.
Step 6: Development of the Optimization Algorithm: Based on the data structure and IFC classifications, develop an optimization algorithm to determine the construction schedule. The optimization method should take into account the restrictions and objectives specified in the requirements and employ heuristics to create a schedule that satisfies the project's objectives.
Step 7: Framework Integration of the Optimization Algorithm: Integrate the optimization method and any extra tools or modules required to build the final schedule into the framework. In addition to a user interface for inputting data and limitations and reviewing the schedule, the framework should also have a user interface.
Step 8: Testing and Validation: Test and verify the framework to ensure that it provides accurate and reliable schedules that fulfill the criteria. This may involve comparing the framework-derived schedules against those generated manually or by other scheduling tools.
Step 9: Performance Evaluation: Evaluate the performance of the framework by comparing its generated schedules to those prepared manually or by other scheduling tools. This may involve testing the framework's precision, dependability, and effectiveness.
Step 10: Conclusion and Recommendations: Summarize the study's findings and provide suggestions for further research or framework enhancements.
4 Results and Discussion
Based on the above literature review, one common limitation among these studies is the lack of integration of the generated construction schedules with other relevant project information, such as resource availability, cost and safety constraints. These limitations hinder the practical application and acceptance of the generated schedules by construction professionals, as they require a comprehensive and integrated view of all aspects of the project. Moreover, it is crucial to consider other factors that may impact the construction process, such as site conditions and changes in the project scope, to ensure the accuracy and reliability of the generated schedules. The algorithm-based techniques are capable of math-based searching strategies capable of discovering optimum solutions for dynamically resource-constrained scheduling situations. The algorithm-based scheduling approaches function as a complement to conventional scheduling techniques. Knowledge-based approaches may sometimes be prone to inaccuracy, particularly when the templates search engine is poorly built. Consequently, many engineers choose model-based scheduling approaches, comprising one of the following technologies: CAD-based and BIM-based. Design, visualization, and simulation may be simplified by both technologies. However, parametric modeling in BIM is significantly more capable than CAD.
BIM has several novel capabilities that may be used in the context of autonomous schedule creation. Besides, the application of optimization algorithms to solve technical problems is an inevitable trend in the construction industry today. Therefore, integrating optimization algorithms and BIM models to generate construction schedules helps designers save a lot of time and minimize human errors.
The study outcomes are expected to be possible highlight the performance improvements, such as increased schedule quality, reduced creating time, and provide statistical analysis to support these findings. The results section could also present visual representations of the schedules generated by the framework, such as Gantt charts, and compare them to existing schedules for the same projects to demonstrate the improved accuracy and efficiency of the proposed framework. This paper presented a method for developing an add-in for Naviswork that generates the construction schedule automatically based on 3D Revit models. Figure 2 is provided as an illustration of the expected results of this study of conducting research according to Fig. 1.
5 Conclusion
BIM technology has altered the conventional project planning methods used by engineers. BIM enables a more visible and transportable information platform throughout a project's duration, resulting in increased collaboration between all project participants. These capabilities have boosted the job efficiency of AEC industry personnel. In addition, BIM is interoperable with software and plug-ins from other disciplines. Despite these benefits, the BIM’s schedule creation capabilities are nowhere near their full potential. The method of data transmission inside BIM systems remains challenging. In addition, it is necessary to discover a strategy to employ 4D BIM effectively. By merging 3D models and optimization algorithms, it can suggest a project's schedule effectively. Therefore, the proposed framework aims to generate construction schedules based on necessary sources as data, the optimization algorithm, and the simulation model. Finally, it will is tested and validated with an actual construction project to conclude the effectiveness of the proposed framework. Expected results and recommendations related to the proposed framework can be used to further studies.
References
Agrama FA (2014) Multi-objective genetic optimization for scheduling a multi-storey building. Autom Constr 44:119–128
Bai S, Li M, Song L, Kong R (2021) Developing a common library of prefabricated structure components through graphic media mapping to improve design efficiency. J Constr Eng Manag 147(1):04020156
Beetz J, van Leeuwen J, de Vries B (2009) IfcOWL: a case of transforming EXPRESS schemas into ontologies. AI EDAM 23(1):89–101
Bynum P, Issa Raja RA, Olbina S (2013) Building information modeling in support of sustainable design and construction. J Constr Eng Manag 139(1):24–34
Faghihi V, Nejat A, Reinschmidt KF, Kang JH (2015) Automation in construction scheduling: a review of the literature. Int J Adv Manuf Technol 81(9):1845–1856
Fischer Martin A, Aalami F (1996) Scheduling with computer-interpretable construction method models. J Constr Eng Manag 122(4):337–347
Kim K, Park J, Cho C (2020) Framework for automated generation of constructible steel erection sequences using structural information of static indeterminacy variation in BIM. KSCE J Civ Eng 24(11):3169–3178
Liu H, Al-Hussein M, Lu M (2015) BIM-based integrated approach for detailed construction scheduling under resource constraints. Autom Constr 53:29–43
Manoj Kumar DMH, Naveen Upreti, Deepti Gupta (2010) Genetic algorithm: review and application. SSRN
Mikulakova E, König M, Tauscher E, Beucke K (2010) Knowledge-based schedule generation and evaluation. Adv Eng Inform 24(4):389–403
Rat C, Kiiras J, Kähkönen K, Huovinen P (2007) Model based scheduling in building projects—Is it oxymoron?
Selvam G, Tadepalli TCM (2019) Genetic algorithm based optimization for resource leveling problem with precedence constrained scheduling. Int J Constr Manag 1–10
Wang W-C, Weng S-W, Wang S-H, Chen C-Y (2014) Integrating building information models with construction process simulations for project scheduling support. Autom Constr 37:68–80
Acknowledgement
We acknowledge Ho Chi Minh City University of Technology (HCMUT), VNU-HCM for supporting this study.
Author information
Authors and Affiliations
Corresponding author
Editor information
Editors and Affiliations
Rights and permissions
Copyright information
© 2024 The Author(s), under exclusive license to Springer Nature Singapore Pte Ltd.
About this paper
Cite this paper
Le, TT., Tran, DH., Nguyen, T.A. (2024). BIM-Based Framework for Creating Automated Construction Schedules: A Proposed Solution in Vietnam. In: Reddy, J.N., Wang, C.M., Luong, V.H., Le, A.T. (eds) Proceedings of the Third International Conference on Sustainable Civil Engineering and Architecture. ICSCEA 2023. Lecture Notes in Civil Engineering, vol 442. Springer, Singapore. https://doi.org/10.1007/978-981-99-7434-4_41
Download citation
DOI: https://doi.org/10.1007/978-981-99-7434-4_41
Published:
Publisher Name: Springer, Singapore
Print ISBN: 978-981-99-7433-7
Online ISBN: 978-981-99-7434-4
eBook Packages: EngineeringEngineering (R0)