Abstract
In this paper, a multi-objective, multi-period, multi-product stochastic model for a multi-site supply chain planning problem under demand uncertainty is proposed. The decisions to be made include the amounts of product to be produced, the amounts of products to be transported between the different sites and customers as well as the amounts of inventory of finished or semi-finished products. The developed model aims simultaneously to minimize the expected total cost, to maximize the customer demand satisfaction level and to minimize the downside risk. The e-constraint method is applied to solve the considered model and to generate the set of Pareto optimal solutions. This set of Pareto represents the trade-off between the different objective functions. Then, an integrated approach of the Analytic Hierarchy Process (AHP) and the Technique for Order Preference by Similarity to Ideal Solution (TOPSIS) methods is applied in order to select the best compromise Pareto solution. A numerical example is presented to illustrate the proposed approach.
Access provided by CONRICYT-eBooks. Download conference paper PDF
Similar content being viewed by others
Keywords
1 Introduction
In the face of today’s highly competitive markets, manufacturing companies are required to expand their production capacity by adding more sites or outsourcing. Therefore, an integrated planning approach that coordinates the different entities of the multi-site supply chain should be established.
A lot of attention has been made in the literature to treat multi-site supply chain planning problems. Many of these works are dealing with deterministic approaches (Felfel et al. 2014, 2015c, Ayadi et al. 2016). However, real multi-site supply chain planning problems are characterized by many sources of uncertainty such as customer demand. Thus, the assumption that these parameters are deterministic will lead to unrealistic results. So, it is crucial to develop an optimization planning model that takes into account existing uncertainties. Two-stage stochastic programming approach (Birge and Louveaux 1997) is widely used in the literature to deal with optimization problem under uncertainty. In this approach, the first-stage variables include the decisions to be made “here-and-now” before the revelation of the random events. The second-stage variables represent the variables that should be made in a “wait-and-see” mode after the revelation of uncertainty.
The minimization of the cost and the maximization of the profit are widely treated in multi-site supply chain planning problem. One can refer to Moon et al. (2002), Jackson et al. (2003), Lin and Chen (2006) and Felfel et al. (2015b). Nevertheless, other important criteria such as the customer demand satisfaction and the risk of having high total cost should be treated in multi-site supply chain planning problems. It is worthwhile mentioning that the objective functions usually conflict with each other in multi-objective optimization problem. Thus, the solution of this problem consists on a front of Pareto optimal solutions which represents the trade-off between the different objectives.
To solve the multi-objective optimization problem, the task of the decision maker consists on obtaining the front of Pareto optimal solutions and finding the most preferred compromise solution. The selection of a best solution from the front of Pareto can be considered as multiple criteria decision-making (MCDM) problem. A lot of methods have been developed in the literature for MCDM (Vincke 1992) such as AHP, ANP, ELCTRE, PROMETHEE, VIKOR and TOPSIS, etc. The technique for order performance by similarity to ideal solution (TOPSIS) and the analytic hierarchy process (AHP) were successfully applied in different areas such as supply chain management and logistics, manufacturing systems, design, engineering, and other many topics (Behzadian et al. 2012). To gain the benefits of these two methods, an integrated approach of the AHP and TOPSIS methods is applied to rank and to select the best compromise Pareto solution in a multi-objective supply chain planning problem.
The main objective of this paper is to develop a multi-objective, multi-product, multi-period, multi-site supply chain production and transportation model under demand uncertainty. The proposed model aims simultaneously to minimize the total cost, to maximize the customer demand satisfaction and to minimize the downside risk. In order to incorporate uncertainty in the considered model, a two-stage stochastic programming approach is adopted. An integrated approach of AHP and TOPSIS method is adopted to select the best Pareto optimal solution. Indeed, the AHP method is applied to determine the weights of the objectives and the TOPSIS method is used to rank the Pareto optimal solutions. A numerical example is presented to illustrate the proposed approach.
The remainder of the article is organized as follows. In Sect. 2, the problem statement is introduced. Section 3 describes the developed stochastic multi-objective planning model. In Sect. 4, the solution approach is presented. Section 5 details the numerical example and the computational results. Finally, Sect. 6 draws conclusions on this work and suggests future research.
2 Problem Statement
The supply network considered in this paper consists of a manufacturing system including many production sites that cooperate together in order to expand their capacities and competences. The end product is produced through different processes defined as multi-stage. Each production stage may involve more than one site, creating a multi-site supply chain structure. The considered supply chain is managed in a centralized way. The planning horizon contains several time period. Furthermore, finished products are characterized by unstable and uncertain demand. This uncertain demand could lead whether to excessive production and inventory costs or unsatisfied customer.
The objective of the considered multi-site supply chain planning problem is to minimize the total expected costs, to maximize the customer demand satisfaction level, and to minimize the downside risk (DRisk). The total costs include production costs, inventory costs, penalty costs of lost demand, and transportation costs. Model decision variables comprise the amount of product to be produced at each site in each period, the amount of inventory of each finished or semi-finished product that should be maintained on each site in each period, the amount of lost demand as well as the quantity of products to be transported between upstream and downstream sites and customers considering demand uncertainty.
3 Proposed Stochastic Mathematical Model
A multi-objective two-stage stochastic programming model is proposed in this section to deal the considered problem. The first-stage decisions include the quantity of products to be produced at each plant as well as the transportation quantity of products between the different plants. Decisions such as the quantity of products to be delivered to the customer, the inventory level and the lost demand quantity are considered as second-stage decisions. To formulate the mathematical model, we introduce the following indices parameters and decision variables:
Indices | ||
---|---|---|
\(L_{i}\) | Set of direct successor plant of site i | |
\(ST_{j}\) | Set of stages (j = 1, 2, …, N) | |
i, i′ | Production plant index (i, i′ = 1, 2, …, I) where i belongs to stage n and i′ belongs to stage n + 1 | |
s | Scenario index (s = 1, 2, …, S) | |
k | Product index (k = 1, 2, …, K) | |
t | Period index (t = 1, 2, …, T) | |
Decision variables | ||
\(P_{ikt}\) | Production amounts of product k at plant i in period t | |
\(S_{ikt}^{s}\) | Quantity of end of period inventory of product k for scenario s at plant i in period t | |
\(JS_{ikt}^{s}\) | Quantity of end of period inventory of semi-finished product k for scenario s at plant i in period t | |
\(TR_{i - > i',kt}^{{}}\) | Quantity of product k transported from plant i to i’ in period t | |
\(TR_{i - > CUS,kt}^{s}\) | Quantity of product k transported from the last plant i to customer for scenario s in period t | |
\(Dlost_{kt}^{s}\) | Lost demand amounts of finished product k for scenario s in period t | |
\(Q_{i,k}^{{}}\) | Amounts of product k received by plant i for scenario s in period t | |
Parameters | ||
\(cp_{ik}\) | Production unit cost for product k in at plant i | |
\(ct_{i - > i',k}\) | Transportation unit cost of between plant i and i’ for product k | |
\(ct_{i - > CUS,k}\) | Transportation unit cost between the last plants i and the customer | |
\(cs_{ik}\) | Inventory unit cost of finished or semi-finished product k at plant i | |
\(D_{kt}^{s}\) | Demand of finished product k for scenario s in period t | |
DL | Distribution time of the finished products | |
\(pe_{k}\) | Penalty cost of product k | |
\(capp_{it}\) | Production capacity at plant i in period t | |
\(caps_{it}\) | Inventory capacity at plant i in period t | |
\(capt_{i - > i',t}\) | Transportation capacity at plant i in period t | |
\(b_{k}\) | Time needed for the production of a product k [min] | |
\(\pi^{s}\) | The occurrence probability of scenario s where \(\sum\limits_{s = 1}^{S} {\pi^{s} } = 1\) |
Problem formulation
The first objective function (1) aims to minimize the expected total cost (E[Cost]). The occurrence probability π s of each scenario is considered in order to calculate the expected total cost. Equations (2) and (3) attempt to maximize the customer demand satisfaction level (MDS). The third objective function (4) aims to minimize the downside risk (DRisk) where ψ s is a positive variable that measures deviation between the scenario cost value and a target Ω as shown in Eq. (8).
Constraints (6) and (7) provide the balance for the inventory level of products. Constraint (8) represents the inventory balance for the semi-finished products. Constraint (9) provides the balance equation for lost products demand. Constraint (10) gives the balance equations for the transportation between the different production stages. The set of constraints (11)–(13) denote the capacity constraints. Constraint (14) is the nonnegativity restriction on the decision variables.
4 Solution Approaches
4.1 Generation of the Front of Pareto Optimal Solutions
The obtained mathematical formulation can be finally expressed as follows:
The solution of the above problem consists of a set of Pareto optimal solutions. This set of Pareto represents the trade-offs that exist between the considered objective functions. In order generate this set of Pareto, we have applied the e-constraint method proposed by Haimes et al. (1971). This approach was widely used to solve multi-objective supply chain planning problems (Guillén et al. 2005; Franca et al. 2010; Felfel et al. 2015a). The main principle of this technique is to select one of the objective functions to be optimized whereas the other objectives are transformed into constraints with allowable bounds \(\varepsilon_{i}\). In order to generate the entire set of Pareto optimal solutions, the level of \(\varepsilon_{1}\) and \(\varepsilon_{2}\) are changed as follows:
4.2 Selection of the Best Pareto Optimal Solution
The selection of the most preferred Pareto optimal is based on a combination of the AHP method with the TOPSIS method. The analytic hierarchy process method (AHP) is a tool to evaluate and analyze multi-criteria decision-making problem first developed by Saaty (1980). In this paper, this method is used to determine the relative importance of each objective function. In order to obtain these weights, a pairwise comparison matrix is should be developed using Saaty preference scale detailed in Table 1.
Then, the Technique for Order Preference by Similarity to Ideal Solution (TOPSIS), developed by Hwang and Yoon (1981), is conducted to achieve the final ranking of the Pareto optimal solutions based on the weights obtained by the AHP method. In the TOPSIS approach, we calculate the best Pareto optimal solution that has simultaneously the farthest distance from the negative ideal solution and the shortest distance from the ideal solution. The positive ideal solution is a solution that attempts to minimize the expected total cost, to minimize the downside risk and to maximize the customer demand satisfaction level, whereas the negative ideal solution is the opposite of the previous one. For more details concerning each method, one can refer to Ayadi et al. (2016) and Felfel et al. (2017).
5 Illustrative Example
The considered example consists of a multi-site manufacturing network which contains five production stages with eight plants and two finished products. The planning horizon includes eight time periods where the length of each period is one week. It is assumed that the uncertain demand is considered as a set of discrete scenarios generated randomly and associated with known probability. The numerical example is solved using LINGO 14.0 and MS-Excel 2010 on a 32-bit with an INTEL(R) Core (TM) 2Duo CPU, T5670@1.8 GHZ, 1.8 GHZ, 2 GB RAM.
In this paragraph, the e-constraint method is used to solve the multi-objective stochastic supply chain planning problem and to generate the set of Pareto optimal solutions. The obtained set of Pareto drawn in Fig. 1 contains 30 points. It should be noted that every point of the set of Pareto shown in Fig. 1 represents a particular set of supply chain planning decisions.
In order to apply the AHP method, each pair of objective functions is compared pairwise to determine their relative importance using the ratio scale shown in Table 1. It is worth mentioning that expected the total cost is considered more important for the decision maker than the other objective functions. The least important objective is considered to be the DRisk. The relative weights of the different objectives are detailed in the last column of Table 2.
Subsequently, the TOPSIS method is applied to evaluate and select the compromise solution based on the weights obtained by AHP method. The separation distances of each Pareto solution from the positive and negative ideal solution \(D_{j}^{ + }\) and \(D_{j}^{ - }\) respectively, the relative closeness measure \(CC_{j}^{*}\) to the ideal solution, as well as the rank of each Pareto solution are reported in Table 3. According to Table 3, the most preferred Pareto optimal solution is S13 since it has highest \(CC_{j}^{*}\) value of 0.6726.
6 Conclusion
In this paper, a two-stage stochastic, multi-objective, multi-site, multi-period, supply chain production and transportation model is developed. Three objective functions are considered which are the minimization of the expected total cost, the minimization of the DRisk, and the maximization of the customer demand satisfaction level. A front of Pareto optimal solutions is generated for the proposed model by means of the e-constraint method. Subsequently, an integrated approach of AHP and TOPSIS methods is applied in order to select the best Pareto solution. In the first step, the weights of each objective are calculated using the AHP approach. Then, in the second step, the Pareto optimal solutions are ranked by using TOPSIS to find the most preferred solution. As future work, other multi-criteria decision-making approach could be evaluated in order to compare their performance with the proposed integrated approach.
References
Ayadi O, Felfel H, Masmoudi F (2016) Analytic hierarchy process-based approach for selecting a Pareto-optimal solution of a multi-objective, multi-site supply-chain planning problem. Eng Optim 1–17
Behzadian M, Otaghsara SK, Yazdani M, Ignatius J (2012) A state-of the-art survey of TOPSIS applications. Expert Syst Appl 39:13051–13069
Birge JR, Louveaux F (1997) Introduction to stochastic programming. Springer, New York
Felfel H, Ayadi O, Masmoudi F (2014) Multi-objective optimization of a multi-site manufacturing network. Lect Notes Mech Eng 69–76
Felfel H, Ayadi O, Masmoudi F (2015a) A multi-objective multi-site supply chain planning problem under risk and uncertainty. Des Model Mech Syst-II 1:151–160
Felfel H, Ayadi O, Masmoudi F (2015b) A stochastic programming approach for a multi-site supply chain planning in textile and apparel industry under demand uncertainty. Int J Supply Oper Manage 2(3):925–946
Felfel H, Ayadi O, Masmoudi F (2015c) A decision making approach for a multi-objective multi-site supply network planning problem. Int J Comput Integr Manuf. https://doi.org/10.1080/0951192X.2015.1107916
Felfel H, Ayadi O, Masmoudi F (2017) Pareto optimal solution selection for a multi-site supply chain planning problem using the VIKOR and TOPSIS methods. Int J Serv Sci Manage Eng Technol
Franca RB, Jones EC, Richards CN, Carlson JP (2010) Multi-objective stochastic supply chain modeling to evaluate tradeoffs between profit and quality. Int J Prod Econ 127(2):292–299
Guillén G, Mele FD, Bagajewicz MJ, Espuña A, Puigjaner L (2005) Multiobjective supply chain design under uncertainty. Chem Eng Sci 60(6):1535–1553
Haimes YY, Lasdon LS, Wismer DA (1971) On a bicriterion formulation of the problems of integrated system identification and system optimization. IEEE Trans Syst Man Cybern 1:296–297
Hwang CL, Yoon K (1981) Multiple attribute decision making: methods and applications. Springer, New York
Jackson J, Grossmann IE (2003) A temporal decomposition scheme for nonlinear multisite production planning and distribution models. Ind Eng Chem Res 42:3045–3055
Lin JT, Chen YY (2006) A multi-site supply network planning problem considering variable time buckets—a TFT-LCD industry case. Int J Adv Manuf Technol 33(9–10):1031–1044
Moon C, Kim J, Hur S (2002) Integrated process planning and scheduling with minimal total tardiness in multi-plants supply chain. Comput Ind Eng 43:331–349
Saaty TL (1980) The analytic hierarchy process. McGraw-Hill, New York
Vincke P (1992) Multicriteria decision aid. Wiley, New York
Acknowledgements
We would like to acknowledge the financial support provided by the Mobility of researchers and research for the creation of value (MOBIDOC) as well as LINDO Systems, Inc for giving us a free educational research license of the extended version of LINGO 14.0 software package.
Author information
Authors and Affiliations
Corresponding author
Editor information
Editors and Affiliations
Rights and permissions
Copyright information
© 2018 Springer International Publishing AG
About this paper
Cite this paper
Felfel, H., Masmoudi, F. (2018). Integrated AHP-TOPSIS Approach for Pareto Optimal Solution Selection in Multi-site Supply Chain Planning. In: Haddar, M., Chaari, F., Benamara, A., Chouchane, M., Karra, C., Aifaoui, N. (eds) Design and Modeling of Mechanical Systems—III. CMSM 2017. Lecture Notes in Mechanical Engineering. Springer, Cham. https://doi.org/10.1007/978-3-319-66697-6_30
Download citation
DOI: https://doi.org/10.1007/978-3-319-66697-6_30