Keywords

1 Introduction

Flood risk assessment (FRA) integrates two distinct parts: (a) estimating flood probability of certain return periods and the flood discharge of particular magnitude and (b) assessing the variable dimensions of flood risk , hydrogeomorphic mechanisms of floods , flood controlling strategies, and real-time actions to be taken before during the floods (Hall & Penning-Rosewell, 2011). Floods are basically extreme hydrological phenomena, and it, generated by natural and anthropogenic causes, represents a classic example of the “pulsed type of disturbance” in the fluvial system (Kinghton, 2014). The term “flood ” has a range of meanings, including (1) hydrological floods with different magnitude and inconstant flow frequency in connection with climate change; (2) floods as hazard and vulnerability , damaging, and livelihoods; and (3) consequences of floods on the components of environment and landscape change (Baker, 1994). A flood event may occur due to large streamflow magnitude as such as that the flow rate exceeds the capacity of the main channel at a location (i.e., the flow exceeds the bankfull discharge) or may occur for a lower streamflow rate when the flow happens at a time when the channel is fully or partially obstructed, as can occur with ice jam or as a result of debris flow in the channel (Burn et al., 2017). The floods of Indian rivers are very important hydrogeomorphic hazard , and the monsoon floods are inevitable and recurrence event because flooding is the natural mechanism (intensified by human activities) by which excess runoff water is discharged through channels, and occasionally it overflows in the floodplains (Kale, 2003; Sinha et al., 2012). In West Bengal, floods are natural as well as man-made hazards which cause considerable damages, particularly in the populated areas of lower Damodar River Basin . The main concern is economic impacts of floods (triggering poverty at village level) including costs due to loss of, or damage to, property, infrastructure damage or destruction, loss of crops and livestock, and lost wages and productivity due to more disruptions.

The flood account of Damodar River, hydrometeorology, nature of annual monsoon floods , structural measures of flood mitigation, changing flood dynamics and floodplain morphology, fluvial aggradation and degradation, dam-controlled environmental flow, role of human on flood hydrology and geomorphology, and impact of flood in agrarian society were previously studied and discussed in details by Glass (1924), Kirk (1950), Pramanik and Rao (1952), Bagchi (1977), Saha (1979), Sen (1985), Roy and Mazumdar (2007), Majumder et al. (2010a), Bhattacharya (2011), Ghosh (2011), Choudhury (2012), Lahiri-Dutt (2012), Lahiri-Dutt and Samanta (2013), Bera and Mistri (2014), Rajbanshi (2015), Ghosh and Mistri (2015), Ghosh and Guchhait (2016), Verma et al. (2017), Das et al. (2017), Chattopadhyay et al. (2020), Mahata and Maiti (2020), Ghosh and Illahi (2020), Ghosh et al. (2021, 2022a), and Hoque et al. (2022). Before dam construction, the floods were very violent in nature (exceeding 18,000 m3s−1 peak flow) and devastating in this funnel-shaped basin, damaging economic assets and livelihood to a large extent, and it was renowned as the “Sorrow of Bengal.” In the 1950s, the DVC (Damodar Valley Corporation) had been introduced the first multipurpose river valley project of India to boost up the regional economy of eastern India and to manage annual flood peaks. Carrying more than 75 years of legacy the DVC has partly achieved the objectives of planning, but the lower segment of the Damodar River (two bifurcated branches – Mundaswari and Damodar/Amta channel) is still vulnerable to recurrent flood hazard during peak monsoon rainfall or tropical depression. At present, elevated embankments and large dams have progressively altered the morphology and hydrology of the fluvial system to a great extent, and the problems of ecological degradation, water pollution, water security, downstream flood hazard , reservoir siltation, drainage congestion, degradation of palaeochannels or spill channels (i.e., floodways of fan-delta), and declining carrying capacity of channel (accommodating diminutive bankfull discharge) are the key issues.

The assessment of flood hydrological dynamics and risk is an essential part of water resource management, especially in a dam-controlled river. Flood forecasting model, a tool of FRA, only makes sense if its results reach as many of the affected people as possible in a suitable form (Sharma et al., 2022). At present, the application of flood and river analysis software and machine learning process in the field of flood hydrology and river flow simulation/hydrodynamic model is a popular practice to develop better flood management at spatial scale (Correia et al., 1998; Leandro et al., 2009; Albano et al., 2017; Mojaddadi et al., 2017; Teng et al., 2017; Sharma et al., 2022). The HEC-RAS (Hydrologic Engineering Center’s River Analysis System ) developed by the US Army Corps of Engineers is a toolkit (an open-source software, https://www.hec.usace.army.mil/software/hec-ras/) of hydrologists and river scientists that allows the user to perform one-dimensional steady flow, one- and two-dimensional unsteady flow calculations, sediment transport/mobile bed computations, and water temperature/water quality modelling (Goodarzi & Eslamain, 2022). The application of HEC-RAS software for flood simulation and floodplain inundation was successfully executed by Horritt and Bates (2002), Merwade et al. (2008), Gibson et al. (2010), Pender and Neelz (2011), Sarhadi et al. (2012), Khattak et al. (2016), Dasallas et al. (2019), Kumar et al. (2019), Farooq et al. (2019), Ongdas et al. (2020), Pathan and Agnihotri (2020), Mawasha (2021), and Rana and Suryanarayana (2021). In numerous studies, HEC-RAS one-dimensional (1D) or two-dimensional (2D) hydrodynamic models are used to simulate flood flows, environmental flows, spatial coverage of floodplain inundation , flood depth, sediment transport along channel, flow velocity in respect of variable discharge, culvert flow design, spatial variability of water quality, and scour phenomenon at bridge piers (Tate & Maidment, 1999; Goodell, 2005; Knebl et al., 2005; Lee et al., 2006; Parsa et al., 2013; Mawasha, 2021). Alongside the floods of Indian rivers (viz., Krishna, Yamuna, Teesta, Mahanadi, Dwarkeswar, Bhagirathi-Hooghly etc.) and unsteady flow simulation were assessed using the hydrodynamic models of HEC-RAS (Mandal & Chakrabarty, 2016; Kumar et al., 2017; Patel et al., 2017; Surwase et al., 2020; Pathan & Agnihotri, 2020; Jagadesh & Veni, 2021; Malik & Pal, 2021; Rana & Suryanarayana, 2021; Ghosh et al., 2022b). It is essential to mention that in the Damodar River the hydraulic routing of extreme floods , 1D/2D flood simulation, 1D-2D coupled LISFLOOD-FP model, and TELEMAC-2D model were analyzed by Sanyal et al. (2013, 2014a, b), Sanyal (2017), and Singh et al. (2020, 2021).

These studies already show that the HEC-RAS software makes it possible to determine how high the water surface will be in the floodplain during specific discharge and which areas are affected by it (Goodarzi & Eslamain, 2022). The study of an inundation area (an area of land subject to flooding ) and the evaluation of its water surface level are the most important part of each flood risk management project (Ogras & Onen, 2020). For floodplain modelling and visualization of input or output data, HEC-RAS is designed in order to model the hydrologic engineering properties of river flow and to import/export data to ArcGIS platform to facilitate the decision-making (Ogras & Onen, 2020). To improve the flood management system of riparian terrain, the utmost vital tool of HEC-RAS software is to check the magnitude of flood risk and vulnerability of flood-prone region, determining the critical floodplain boundaries of maximum flood flow. As the river floodplain zoning maps provide valuable hydrologic information, such as flow area, frictional loss, Froude number, hydraulic conveyance, critical hydraulic depth, flood depth, and area of flood prevention in flood zones, it is decisive to place the maps in the first step of flood management (ShahiriParsa et al., 2016). Observing the potentiality of HEC-RAS , the present study aims to assess the dam-induced changes in the occurrence of extreme floods , floodplain inundation during unsteady flows, and the associated floodplain risk of variable return period discharge (2-year, 5-year, 10-year, 25-year, 50-year, and 100-year floods ) in the lower part of Damodar River Basin . Heavy rainstorm event of monsoon climate, runoff yield of different terrain (hard rock or alluvium), and flash floods have inevitable in situ uncertainty with a physical open system, but if the current estimates of flood flow or bankfull discharge or carrying capacity of Damodar River can be deduced, then an idea of flood risk can be derived with some statistical perception.

2 Geographical Settings of Study Area

The Damodar River Basin (DRB) covers a basin area of 23,370 km2 in Jharkhand and West Bengal. Its latitudinal extension ranges from 23° to 23° 22′ 10″ N, and the longitudinal extension ranges from 87°28′23″ to 88°01′00″ E. The 541-km-long stretch of Damodar starts its journey from the Khamarpat Hill (altitude 1062 m from mean sea level) of Chandwa, Palamu district (Jharkhand). The main tributaries of upper catchment are Barakar, Konar, Gobai, Jamuniya, Haharo, Garhi, Bhera, and Uttala. Below the Durgapur Barrage, the River receives the last tributary, named Sali. Following almost linear channel pattern (eastern ward slope), the river takes a sharp 90 southward turn at Palla (24 km east of Bardhaman town). At Paikpara, Jamalpur the main river bifurcates into two distributaries (Mundeswari at west and Damodar/Amta channel at east), and the Amta channel joins the Bhagirathi-Hooghly River at Falta, Howrah (48.3 km south of Kolkata). From the elbow of 90 turn several spill channels and palaeochannels (old distributaries of Damodar) are observed showing the topographic signature of fan-delta formation (prograding towards east and southeast direction) and palaeofloodways of monsoon months. Below the bifurcation point both channels, Mundeswari and Damodar/Amta channel, is confined within embankments , but bankfull discharge and monsoonal overflow make this floodplain or active fan-delta a flood-prone region of West Bengal which includes agriculturally dominated blocks of Pursura, Tarakeswar, Khanakul I and II, Jangipara, Udaynarayanpur, and Amta I and II. The main hydrologic concern is the lower fluvial system of Damodar River which extends from 22° 35′ 42″ to 23° 09′ 30 N″ and 87° 51′ 08″ to 88° 00′ 31″ E.

The DRB  (Fig. 13.1) is located in the topographic transitional zone (break of slope) of the Chhotangapur Plateau (west) and the Bengal Basin (east), following three major south-north trend basement faults – (1) Chhotanagpur Foothill fault, (2) Pingla Fault, and (3) Khandaghosh-Garhmayna fault (Ghosh & Guchhait, 2015; Mahata & Maiti, 2019). In the upper part of Damodar, the slope is 1.86 m km−1 for the first 241 km, and for the next 167 km, it is 0.57 m km−1, and in the lower part, it is only 0.16 m km−1 (Mahata & Maiti, 2019). The upper part of the basin (upstream of Durgapur) is covered mainly by granite and gneiss of the Archean, Gondwana sandstone and shale, and Recent channel alluvium, whereas the lower part (downstream of Durgapur) is characterized by the deposits of tertiary sediments, Early-Late Pleistocene laterites and Late Pleistocene – Recent alluvium (Mahata & Maiti, 2019). Since Oligocene (34–23 Ma BP), influenced by several marine transgression and regression periods, the vast load of plateau sediments was deposited by the fluvial system of Damodar, and it filled up the western shelf zone of the Bengal Basin in the subaerial and subaqueous tropical palaeoenvironment (Mahata & Maiti, 2019). By process of avulsing channels, sheet flow and debris flow the total fan-delta of Damodar (below Panagrah, Paschim Bardhaman) prograded into the shallow marine condition of the Bengal Basin. Downstream of Panagrah, the topography of lower Damodar River is subdivided into three distinct fan-deltaic parts – (1) Early Pleistocene to Late Pleistocene Panagarh fan-delta (trending east), (2) Late Pleistocene to Early Holocene Memari fan-delta (trending southeast), and (3) Late Holocene to Recent active fan-delta (trending south) (Acharyya & Shah, 2007; Mahata & Maiti, 2019) (Fig. 13.1).

Fig. 13.1
An area map of the Damodar River Basin along with the Western Sub-basin of the Bhagirathi-Hooghly River Basin. It represents rivers or streams, sites of dams, barrages, and basin boundaries on A L O S A W 3 D 30 D E M. A color gradient scale for elevation in meter from low 1 to high 1363, and a scale in kilometer are present at the left bottom.

Location map of Damodar River Basin (including sites of dams, barrage, and weir) on ALOS AW3D30 DEM, along with associated western sub-basins of Bhagirathi-Hooghly River System

The most significant part of the basin is large-scale modification of channels by installing large dams, and to understand the anthropogenic impact on fluvial system, the DRB is a practical example from India. Perceived in 1945, following the model of the Tennessee Valley Authority (TVA), the Damodar Valley Corporation (DVC) was designed in 1948 under the guidance of Dr. Meghnad Saha and W.L. Voorduin who had been provided the total framework of multipurpose Damodar Valley Project, named “Preliminary Memorandum on the Unified Development of the Damodar River.” DVC was aimed to integrate the people, water, cropland, and mineral resources in a single thread of sustainable development with a holistic approach (Kirk, 1950; Saha, 1979). Firstly, it was decided to build eight large dams at eight sites, viz., (1) Tilaiya, Maithon, and Balpahari dams on the Barakar River; (2) Bokaro dam on Bokaro River; (3) Konar on Konar River; and (4) Aiyer, Bermo, and Panchet on Damodar River (Chandra, 2003). Finally, DVC decided to build only four dams at first phase, viz., Tilaiya (1953), Konar (1955), Maithon (1957), and Panchet (1959) (Table 13.1). After that, in 1974 one more reservoir, Tenughat, on the Damodar River was built. The Durgapur Barrage, built in 1955, is one of the important river impoundments because it finally releases incoming excess runoff water which has potentiality to flood in the lower floodplain of Damodar. Eight large dams would be able to reduce peak discharge of 28,321 m3s−1 (resulting from a rainstorm of 50.8 cm at the upper catchment) to 7080 m3s−1 at Rhondia, having total flood reserve of 6500 million m3, but five dams only provide a maximum storage capacity of 3591 million m3 (Bhattacharya, 2011). Now DVC flood-controlling system provides a flood benefit of only 162.56 mm of surface runoff to the lower part of the basin, in place of 452 mm as advocated by the committee (Ghosh & Guchhait, 2016). Living on the active floodplain of Damodar and its structural modifications for protection against floods and for utilization of regional resources and wealth has aggravated the problem of hydrological risk factor to inundation (Table 13.1).

Table 13.1 Overview and salient features of the dams in the Damodar River Basin

3 Methodology

The present study incorporates selected quantitative methods and techniques used in flood hydrology which deals with hydrometeorological aspects of flood , alluvial channel dynamics, flood routing and flood stage identification, hydraulic and engineering dimensions of floods , holistic flood risk assessment, and integrated flood management . Alongside, the methods of fluvial hydrology (Ward, 1978; Garde, 2006) include estimation of channel planforms and geometric dimensions (viz., width, depth, slope, sinuosity, sediment, channel roughness, etc.) and river hydraulics (viz., flow pattern, regime, hydrograph, and discharge anomalies). Along with the techniques of flood prediction and modelling, the aim of flood hydrologic assessment is providing assistance and preliminary information to manage active floodplain zones and vulnerable flooded areas with the help of 1D or 2D hydrodynamic model and advanced geo-spatial tools.

3.1 Data Collection

The primary spatial information of study area was mostly collected from the topographical sheets (73 M/7, M/11, M/12, M/15, M/16, N/13, and 19 A/4) of SOI (Survey of India). The topographic and hydrological information of DRB were collected from the book, entitled “The Planning Atlas of the Damodar Valley Region,” which was written by Chatterjee (1969). The up-to-date daily rainfall, gauge data, and reservoir discharge data were retrieved from the official website (https://www.wbiwd.gov.in/) of IWD (Irrigation and Waterways Department, Government of West Bengal). In this study the main river gauge data (gauge level in metre) was collected for the four IWD monitoring stations – (1) Rhondia (23° 22′ 56″ N, 87° 29′ 35″ E), (2) Edilpur (23° 13′ 40″ N, 87° 49′ 12″ E), (3) Jamalpur (23° 02′ 39″ N, 87° 58′ 56″ E), (4) Champadanga (22° 50′ 24″ N, 87° 58′ 12″ E), and (5) Harinkhola (22° 50′ 22″ N, 87°54′ 16″ E) (Fig. 13.2). The daily IWD reservoir discharge data were collected for the Durgapur Barrage (23° 38′ 35″ N, 87° 18′ 11″ E). The historical flood data and annual peak flow data of the DRB were collected from the research paper of Glass (1924), annual flood report of IWD (1959 and 2000), the books of Bhattacharya (2011) and Rudra (2018), and the research papers of Das et al. (2017) and Majumder et al. (2010b). The basin map of Damodar was prepared from the data repository of HydroSHEDS (Hydrological data and maps based on Shuttle Elevation Derivating at multiple scale). HydroRIVERS has been extracted from the gridded HydroSHEDS core layers at 15 arc-second resolution. The surface geology, lineaments, drainage, and other geomorphic information and thematic maps were retrieved from the web portal of the Geological Survey of India (www.bhukosh.gsi.gov.in). Monthly and annual rainfall data were retrieved from the CHRS (Center for Hydrometeorology and Remote Sensing ) data portal (www.chrs.eng.uci.edu) which provided gridded precipitation data of resolution 0.04° × 0.04° (4 × 4 km). The rainfall data belongs to PERSIANN (Precipitation Estimation from Remotely Sensed Information using Artificial Neural Networks) CCS (Cloud Classification System) algorithm, which relates to variable threshold cloud segmentation (Nguyen et al., 2019). Alongside, another 0.25° × 0.25° resolution gridded rainfall data was collected from the official website of the Indian Meteorological Department (www.imdpune.gov.in). The land use and land cover (LULC) information were collected from the web portal of ESRI 2020 Land Cover Downloader (https://www.arcgis.com/home/item.html?id=fc92d38533d440078f17678ebc20e8e2#overview) where the analysis was done using the Sentinal – 10 m resolution imagery (2017–2021). The ALOS Global Digital Surface Model (AW3D30) digital elevation data of 30 m resolution was collected from the web portal of Open Topography. The Japan Aerospace Exploration Agency (JAXA) releases the global digital surface model (DSM) dataset of AW3D30 with a horizontal resolution of 30-meter mesh (1 arcsec). The dataset of surface water occurrence (SWO) was gathered from the web portal (www.global-surface-water.appspot.com/download) of the Joint Research Centre’s Global Surface Water Dataset (1984–2020) which was prepared to analyse the seasonal occurrence of inundated areas and permanent water bodies. National level hydrological modelling framework (National Remote Sensing Centre, Hyderabad) provides the database of evapotranspiration, surface runoff, and soil moisture on a daily basin of 5.5 km grid resolution in India (www.bhuvan.nrsc.gov.in/nhp). In this study, all databases are analysed and spatially mapped in the ERDAS Imagine 2014, ArcGIS 10.4, HEC-RAS 6.2, and XLSTAT (Table 13.2).

Fig. 13.2
An area map of the lower Damodar River Basin, West Bengal. It marks five important sites: Durgapur Barrage, Rhondia, Jamalpur, Harinkhola, and Champadanga, along with their satellite view photos.

Important sites of river gauge stations and Durgapur Barrage in the lower Damodar River Basin (West Bengal)

Table 13.2 Important sources of secondary database

4 Methods

4.1 Basics of 1D-Hydrodyanmic Model

One-dimensional (1D) hydrodynamic model in flood simulation assumes that the phenomenon of peak streamflow can be defined satisfactorily as unsteady or steady flow (with certain geometry and boundary conditions of channel) in a space of single dimension. 1D flood model was elaborated and applied by numerous workers (Horritt & Bates, 2002; Merwade et al., 2008; Leondro et al., 2009; Pender & Neelz, 2011; Betsholtz & Nordlof, 2017; Dasallas et al., 2019). 1D- hydrodynamic model is based on the Bernoulli (energy equation) and Saint-Venant equations (mass and moment conservation) for steady and unsteady flows in open channels, respectively. Betsholtz and Nordlof (2017) mentioned the following assumptions behind 1D flood simulation:

  • The fluid is incompressible. Where the density of fluid is constant, the volume should be proportional to the mass.

  • It is assumed that the water flows follow a longitudinal direction.

  • In pressure distribution along a channel, the hydrostatic and vertical accelerations are overlooked.

  • Vertical variations in flow and velocity are ignored.

  • The water depth is much lower than the wave lengths.

  • The average channel bed slope is small.

  • Manning’s equation estimates the value of bed friction for the steady flow condition.

  • The flow is the continuous function of the velocity and the water surface elevation H.

To simplify the calculation, the computing system of HEC-RAS assumes a horizonal water surface at each cross-section normal to the direction of flow such that the momentum exchange between the channel and the floodplain boundaries can be neglected (Dasallas et al., 2019). Kumar et al. (2017) and Dasallas et al. (2019) mentioned the following derivatives of 1D model (Fig. 13.3):

$$ {Y}_2+{Z}_2+\frac{\alpha_2{V}_2^2}{2g}={Y}_1+{Z}_1+\frac{\alpha_1{V}_1^2}{2g}+{h}_e $$
(13.1)

where Y 1 and Y 2 = flow depth of water (m), Z 1 and Z 2 = elevation of the main channel inverts (m), V 1 and V 2 = average velocity (m s−1), α 1 and α 2 = velocity weighting coefficients, g = gravitational acceleration (m s−2), and h e = energy head loss (m).

Fig. 13.3
A schematic diagram represents the 1 D hydrodynamic model with label parts energy grade line, water surface, channel bottom, datum, water surface elevation 1 and 2. The height from the bottom to the lower water surface is W S subscript 2 and 1, the height of the water surface is alpha subscript 2 of, V subscript 2 to the power 2, over, 2 G, and the height between the upper water surface and energy grade line is h subscript e.

A schematic diagram of 1D hydrodynamic model (where α 1 and α 2 = velocity weighting coefficients; V 1 and V 2 = average velocity; g = gravitational acceleration; h e = energy head loss; WS1 and WS2 = water surface elevation)

De Saint Venant (1871) derived the following equations which is now used in HEC-RAS (Stelling & Verway, 2005; Fan et al., 2017):

$$ \frac{{\partial A}_t}{\partial t}+\frac{\partial Q}{\partial x}={q}_{\textrm{lat}} $$
(13.2)
$$ \frac{1}{gA}\ \left\{\frac{\partial Q}{\partial t}+\frac{\partial }{\partial x}\ \left(\frac{Q^2}{A}\right)\right\}+\frac{\partial \zeta }{\partial x}+\frac{Q\left|Q\right|}{K^2}=0 $$
(13.3)

where A t = cross-sectional area (m2), t = time (s), Q = discharge (m3 s−1), x = position along the channel axis (m), q lat = lateral discharge per unit length of channel (m2 s−1), A = flow-conveying cross-sectional area (m2), ζ = water level above a selected horizontal reference plane (m), and K = channel conveyance (m3 s−1). In its simplest form, Eq. (13.3) may be reduced to the familiar steady flow conveyance relationship

$$ Q=K\sqrt{I} $$
(13.4)

with the conveyance K expressed as

$$ K= CA\sqrt{R}\ \textrm{or}\ K=\frac{1}{n}{AR}^{2/3} $$
(13.5)

where K is a function of Chezy resistance coefficient, hydraulic radius, cross-sectional area, and Manning’s friction coefficient.

The set of Eqs. (13.2) and (13.4) forms the so-called kinematic wave approximation for flood propagation, which, after substitution of (13.4) into (13.2) and neglecting the lateral flow term, can be further simplified to the form

$$ \frac{\partial Q}{\partial t}+\textrm{c}\frac{\partial Q}{\partial x}=0 $$
(13.6)

with a flood wave celerity c (m s−1) expressed as

$$ \textrm{c}=\frac{1}{b_s}\frac{dQ}{dh} $$
(13.7)

4.2 Steps in Flood Inundation Model of HEC-RAS

The HEC-RAS 6.2 version software includes extreme number of hydrologic applications, mainly (1) steady and unsteady flow modelling, (2) analysis of both subcritical and supercritical flow regimes, (3) design of culvert and bridge, (4) bridge scour computation, (5) analysis of floodplain and channel area encroachment, (6) multiple profile computations, (7) sediment transport/movable bed modelling, (8) reservoir and spillway analysis, (9) X-Y-Z (pseudo 3D) graphics of the river system, (10) levee overtopping, etc. (Hicks & Peacock, 2005; Stelling & Verway, 2005; Merwade et al., 2008; Pramanik et al., 2010; Sarhadi et al., 2012; Sanyal et al., 2014b; Kumar et al., 2017; Patel et al., 2017; Teng et al., 2017; Pathan & Agnihotri, 2020; Singh et al., 2020). The goal of the flood inundation modelling is to evaluate the possible flood extent in a river reach using the basic functions of RAS Mapper in HEC-RAS to create a 1D model of a river system. To assist the decision makers or planners, the thematic maps of 1D hydrodynamic model is very significant to recognize the inundated areas of different flow regimes for mitigating floods , protection of cropland and settlements, and adapting flood-controlling measures in reality. Flood inundation mapping needs high-resolution DEM (digital elevation model) or DTM (digital terrain model) database to maintain accuracy at field scale, and comparing the DEM of water with the DEM of ground the area of flooding is determined at all points where the water surface is above the ground surface (Merwade et al., 2008). The details of workflow and modeler application guide can be found in the technical document of US Army Corps of Engineers (2020). In this study the following steps are taken to execute 1D hydraulic model for flood inundation mapping (Merwade et al., 2008; Kumar et al., 2019):

  1. 1.

    Design steady flow (e.g., 2-year, 5-year, 15-year, and 25-year flood ) is firstly estimated using a calibrated popular hydrologic model (log-Pearson Type III distribution), and an unsteady flow database is collected from the daily discharge data of a gauge station for a specific period.

  2. 2.

    The requirement of channel geometric data includes width, elevation, shape, length, location, geomorphic shape, boundary condition (Manning’s coefficient), and slope. River floodplain data (digitizing main and tributary mid-channel part, left-right banks, channel confluence/bifurcation junction, and floodplain span) is firstly needed. The consecutive maximum numbers of downstream cross-sections (covering boundary of floodplain) are developed, creating river transects in DEM or DTM.

  3. 3.

    Step 1 (design steady or unsteady flow) and step 2 (channel geometry) are then processed in HEC-RAS to deduce water surface elevations (WSE) along the channel. Other hydraulic parameters are obtained by calibration.

  4. 4.

    The DEM is subtracted from the water surface to obtain a water-depth map. The area with positive values in the water-depth map gives the flood inundation map of different design flows.

  5. 5.

    Other main outputs of HEC-RAS modelling water velocity of design flows, flow area, cross-sectional view of WSE, and energy grade line slope.

4.3 Risk and Flood Frequency Analysis

For any hydrologic design, the estimation of risk and reliability is very essential task, and the hydrological risk can be used to fix the return period for a given design life, reflecting level of risk (Vogel & Castellarin, 2017). The probability of flood occurrence in any one year (event) is p = 1/T, and the probability of x occurrences in n years is B (n, p). According to Vogel and Castellarin (2017), “the probability (at least one incidence in n events) is called risk which is defined as the probability that one or more events will exceed a given magnitude within a specified binomial distribution.”

$$ \textrm{Risk}=1-{\left(1-1/T\right)}^n $$
(13.8)
$$ \textrm{Reliability}={\left(1-p\right)}^n={\left(1-1/T\right)}^n $$
(13.9)

Nearly in all series of natural floods , the log-Pearson Type III (LPT3) distribution (similar to normal or Gaussian distribution) is applied as a commonly used frequency distribution for annual peak streamflow. The mean in LPT3 distribution is approximately equal to the logarithm of the 2-year peak discharge. The standard deviation is the slope of the line, and the skew is shown by the curvature of the line. The probability density function (PDF) of log-Pearson Type III distributed random variable is given by Rao and Hamed (2019):

$$ \textrm{f}\left(\textrm{x}\right)=\frac{1}{\alpha \textrm{x}\varGamma \left(\beta \right)}\ {\left[\frac{\log \left(\textrm{x}\right)-\gamma }{\alpha}\right]}^{\beta -1}{\textrm{e}}^{-\left\{\frac{\log \left(\textrm{x}\right)-\gamma }{\alpha}\right\}} $$
(13.10)

where f(x) = the probability density function, x = the variable in a Pearson III distribution (range γ < x < ), α and β = distribution location and scale parameters, and Γ = gamma function.

The distribution function of LPT3 distribution is given by the following equation (Rao & Hamed, 2000):

$$ \textrm{f}\left(\textrm{x}\right)=\frac{1}{\alpha \textrm{x}\varGamma \left(\beta \right)}\ \int_0^{\textrm{x}}\frac{1}{\textrm{x}}\ {\left[\frac{\log \left(\textrm{x}\right)-\gamma }{\alpha}\right]}^{\beta -1}{\textrm{e}}^{-\left\{\frac{\log \left(\textrm{x}\right)-\gamma }{\alpha}\right\}}\ dx $$
(13.11)

If \( y=\frac{\log \left(\textrm{x}\right)-\gamma }{\alpha } \) is substituted in equation, then we can get the equation

$$ \textrm{f}\left(\textrm{x}\right)=\frac{1}{\varGamma \left(\beta \right)}\ \int_0^y\frac{1}{\textrm{x}}\ {\left[y\right]}^{\beta -1}{\textrm{e}}^{-y}\ dy $$
(13.12)

In general form, the LPT3 distribution can be written as

$$ {Q}_{\textrm{LPT}}={Q}_{\textrm{avg}}+{K}_T{S}_l $$
(13.13)

where Q LPT = logarithm of predicted discharge, at return period T, Q avg = average of annual peak discharge logarithms, K T = a function of return period (frequency factor) and skew coefficient, and S l = the standard deviation of logarithms of annual peak discharge. K T can be written as

$$ {K}_T=\frac{2}{C_S}\ \left[{\left\{\frac{C_S}{6}\ \left(u-\frac{C_S}{6}\right)+1\right\}}^3-1\right],{C}_S>0 $$
(13.14)

where u is the standard normal variate corresponding to a probability on non-exceedance of P = 11/T and C S is skew coefficient.

4.4 Other Hydrological Estimates

Daily runoff (Q Run) of the ungauged basin can be calculated using NRCS-CN (Natural Resource Conservation Service Curve Number ) method. Surface runoff for a particular rainstorm event is controlled by spatial pattern of land use–land cover (LULC) and hydrologic soil groups (HSG) which produce unique curve number (0–100) for a grid or a basin. An area-weighted average curve number is used for the entire catchment of Damodar to study the runoff effectively. The quantitative expressions of NRCS-CN method (Zade et al., 2005; Viji et al., 2015) can be written as

$$ {Q}_{\textrm{Run}}={\left(\textrm{Rainfall}-0.3\ {S}_t\right)}^2/\left(\textrm{Rainfall}+0.7\ {S}_t\right) $$
(13.15)
$$ {S}_t=25,400/ CN-254 $$
(13.16)

where S t is potential maximum retention or recharge capacity after runoff begins (after 5 days antecedent rainfall condition).

In this study, the empirical formulae of flood peak potential (Q fpp) are used to assess the probable maximum discharge of Damodar River, taking upper catchment basin area (19,920 km2) from the Rhondia gauge station. Alongside, other hydrological estimates and indices related to flood hydrology are given in Table 13.3. It is needed to mention that two nonparametric methods (Mann-Kendall and Sen’s slope estimator) were used to detect the significant trends of annual rainfall and annual peak discharge. The Mann-Kendall statistical test (M-K Test) and Sen’s slope (Kamal & Pachauri, 2019; Saikia & Konwar, 2020) are used here to quantify the significance of trends in hydrometeorological time series (viz., annual rainfall and annual peak discharge). Positive values of Kendall T (tau) indicate increasing trends, while negative T values show decreasing trends. In this study, significance levels α = 0.01 and α = 0.05 were used. At the 5% significance level, the null hypothesis of no trend is rejected if |T| > 1.96 and rejected if |T| > 2.576 at the 1% significance level. Alongside estimating statistically significant range of peak discharge, the confidence interval (CI) at 99% significance is applied here:

$$ CI={X}_{\textrm{mean}}-3\sigma /\sqrt{n}\ \textrm{to}\ {X}_{\textrm{mean}}+3\sigma /\sqrt{n} $$
(13.17)
Table 13.3 Important quantitative indices of flood hydrology

5 Results

5.1 Analysis of Flood Climate

The terms “flood climate” (Hayden, 1988) and “flood hydroclimatology” (Hirschboeck, 1988) include detail focus on the regional climate and atmospheric activity which promotes recurrent flood condition in connection with changing climate of the regions. Tropical climate, including monsoon climate of India, has high potentiality of torrential rainfall within a short period, which can instigate massive flood flows of Indian rivers. The flood climate of India can be designated as Tszo type (Hayden, 1988) in which barotropy (T), seasonal basis (s), intertropical convergence zone, (z) and organized convective activity at synoptic scale (o) are key determinants (Ghosh, 2013). The rainfall maps (Fig. 13.4) of DRB and associated basins (1990–2020) express that trend of mean annual rainfall increases from west to east direction and the maximum annual rainfall of the eastern basin varies from 1662 to 1977 mm (minimum annual rainfall of western basin: 790–1309 mm). In monsoon months (June–October), the rivers experience floods annually after a spell of heavy rainfall (150–300 mm within 3–4 days) because this amount of rainfall yields a gigantic volume of runoff in respect of catchment’s physical characteristics. Today’s climate is occurring in an atmosphere that’s been made warmer, wetter/humid and more energetic. Due to global warming input of more heat energy to atmosphere promotes more moisture in the air. It is learned that for every degree of warming, the atmosphere can hold around 7% more moisture (Climate Signals, 2022), and more rainfall comes in short with intense downpours, which has increased the risk of flash floods in India. The 2010 report by the Ministry of Environment and Forests, Government of India stated that India’s average temperature has risen by around 0.7 °C during 1901–2018. Due to climate change the summer monsoon precipitation (June–September) over India has also weakened by around 6% from 1951 to 2015 with notable decrease of annual rainfall (but increase of extreme rainfall event for a short period) over the Indo-Gangetic Plains (Sahoo & Bhaskaran, 2016). Interestingly, in the world, the number of rainy days is declining, while intense rainfall events of 10–15 cm per day are escalating (Chattopadhyay et al., 2020). This means that more amount of water is pouring downs in lesser time, and it creates maximum level of flood risk in the tropical region. In a nutshell, climate change has extreme impacts in India: (a) rise in average temperature, (b) trend of no rain for long period, (c) sudden burst of excessive heavy rainfall, and (d) occurrence of extreme weather hazard , like flash floods of Himalayas and monsoon floods of Ganga and Brahmaputra Basins.

Fig. 13.4
The four areal distribution maps of Damodar River Basin. It represents annual mean rainfall for the years 1990 in a, 2000 in b, 2010 in c, and 2020 in d. The color gradient scales for rainfall in millimeters range from 1309 to 1977 in a, 790.2 to 1662 in b, 802.8 to 1635 in c, and 1120 to 1710 in d, and scales in kilometers are present at the bottom left.

Areal distribution of mean annual rainfall (decreasing trend from west to east) in 1990 (a), 2000 (b), 2010 (c), and 2020 (d) over the Damodar River Basin and other associated basins

Alongside, the tropical depressions and cyclones are another factor of heaviest rainfall and flood in India. The lower Ganga basin, including DRB , experiences west-north-westwards tracks of depressions and cyclones from the head of the Bay of Bengal to the Chhotangapur Plateau, causing heavy rainstorms and downpours throughout the region of West Bengal and Jharkhand. Tropical cyclone activity (development of depression and cyclonic storm) during late monsoon period shows an upward trend and also exhibits El Nino Southern Oscillation (ENSO) of 2–5 years’ time scale over the Bay of Bengal (Sahoo & Bhaskaran, 2016). Track of cyclone and depression is very much linked to occasional extreme floods of DRB , because in many cases (viz., floods of October 1978, June 1981, September 2000, September 2009, August 2016, and May 2021), the path of cyclonic activity moved from downstream to upstream direction (southeast to northwest) along the entire basin. In between 1986 and 1995, the track was mostly northward and then westward from the Bay of Bengal, and it covered the DRB and its associated basins. During 2006–2015, most cyclones moved northward. A key fact of DRB is that during cyclonic rainfall (moving southeast to northwest), the lower basin (West Bengal) is already saturated with high moisture, and alongside when the cyclone reaches at the upper basin (Jharkhand), the region also experiences heavy rainfall (110–230 mm in3–4 days) due to high topographic lift (>600 m from mean sea level) causing the excessive concentrations of runoff (later flood flow) in the fluvial system of Damodar and Barakar (Fig. 13.5).

Fig. 13.5
A map of the Damodar River Basin represents the annual mean rainfall from 2011 to 2020 and river networks. Five cyclone or depression paths in June 1981, August 2016, September 2009, May 2021, and October 1978 are mentioned with arrows. A color gradient scale in millimeters from low 802.821 to high 1634.52 and a scale in kilometers are displayed.

Tracks of tropical cyclones and depressions over the rainfall region of Damoadar River Basin

W.W. Hunter (1876), in his Statistical Account of Bengal, described Damodar floods as harka ban (flash flood ) having floodplain inundation depth of 1.5 m in the lower basin. Floods in the DRB have been presented as an aberrant and unpredicted behavior of the river, making “river training,” “river control,” “taming,” and “harvesting” of it very problematic and of then critical for a decade (Majumder et al., 2010b). In documentation, the great floods of Damodar were almost recurrent phenomena at past – 1770, 1855, 1866, 1873–1874, 1875–1876, 1884–1885, 1891–1892, 1897, 1900, 1907, 1913, 1927, 1930, 1935, 1943, 1959, 1978, 2000, 2011, 2016, and 2021 (Majumder et al., 2010b). Bardhaman town and its adjoining region were completely flooded in 1770, 1855, 1913, and 1943 having discharge of more than 16,000 m3s−1. To save the land from flood , the embankment was stated to build between 1866 and 1873 under the leadership of Maharaja Kirti Chand of Bardhaman. After independence of India, the flood hydrology of the Damodar catchment was getting more importance in view of India’s first multipurpose river valley project being undertaken in the basin adapting the model of Tennessee Valley Authority (TVA). The extensive studies of Glass (1924), Kirk (1950), Pramanik and Rao (1952), Chatterjee (1967), Bhalla (1969), Sinha and Rao (1985), and Bhattacharya (2011) made few conclusions regarding the unique characteristics of flood climate in the DRB :

  1. 1.

    Key driver of each miserable flood is the torrential rainfall over the upper catchment. Total mean rainfall on the whole catchment producing floods generally varies from 76.2 mm in 3 days to a maximum of about 304.8 mm in 6 days. It is assumed that a maximum extreme rainfall of 508 mm in the first half of the monsoon season and 127 mm in the latter half with runoff coefficient of 90%.

  2. 2.

    An intensive rainstorm giving more than 330.2 mm of mean rainfall over the upper catchment may occur once in about 65 years and one giving more than 381 mm once in about 120 years. A storm giving 457.2 mm rainfall in 6 days of which 330.2 mm may fall in 3 days and 177.8 mm in a day may be assumed as the maximum that is likely to occur over the upper catchment.

  3. 3.

    A rainstorm magnitude equal to or greater than 304.8 mm occurs once in 100 years and greater than 355.6 mm in 250 years. Further, a storm rainfall giving 411.48 mm is likely to be equaled or exceeded only once in 1000 years. Between 1891 and 1980, 1 day maximum rainfall recorded as 124.71 mm and 7 days maximum rainfall recorded as 312.93 mm in the DRB .

Pre-dam historical data and analysis (Glass, 1924; Pramanik & Rao, 1952) is very much needed to understand and predict the flood condition. The following lessons are learnt from the past records (Table 13.4):

  1. 1.

    The maximum recorded 3-day rainfall was about 254 mm at pre-dam period. That rate of rainfall for the Damodar catchment of 18,648 km2 work out to an average rate of peak discharge 18,264 m3s−1 at Raniganj.

  2. 2.

    High discharge at Rhondia (exceeding 5663 m3s−1) on any date is very highly correlated with the rainfall recorded on the date and the preceding 2 days. It is formulated a regression trendline between rainfall (R, inches) of July to October with the corresponding seasonal flow (D, cusec) expressed during pre-dam period: D = 0.65 R–8.68.

  3. 3.

    Discharge of the Damodar River at Rhondia on any day is very much correlated with the following: (a) rainfall of preceding day (0.73), (b) rainfall of preceding 2 days (0.80), and (c) rainfall of preceding day and discharge of preceding day (0.82). Two linear relationships are established: (a) D = 4.35 (R −1 + R −2) + 0.9703 and (b) D = 71.70 R −1 + 14.6787.

  4. 4.

    From 1909 to 1917 it was observed that 3–8 days continuous mean rainfall of 68.58–299.72 mm produced a peak flood discharge range of 6060–18,406 m3s−1 at Raniganj (table).

Table 13.4 Historical record of seven rainstorms and resulting flood flows in the Damodar River at Raniganj

It was estimated that Damodar catchment received monsoon rainfall (June–October) of 855.57–1043.55 mm and Barakar catchment received monsoon rainfall of 840.54–1079.81 mm annually (Ghosh & Mistri, 2015). In between 1950 and 2000, the Jharkhand division of DRB received mean annual rainfall of 1091 mm, and the part of West Bengal receives 1167 mm. CHRS data of 2001–2020 period shows that mean normal annual rainfall of upper catchment ranges in between 1219 mm (western part) and 1923 mm (eastern part), reflecting an increasing trend of annual rainfall than previous (Fig. 13.6a). Rainfall trends in the DRB over the period of 46 years (1970–2015) reflect summer monsoon rainfall accounting for around 80% of total rainfall and increasing rainfall trend in post-monsoon season (Chattopadhyay et al., 2020). Total DRB receives quite same annual rainfall in between 1970 and 2015, and it is increasing from past record, reflecting high chance of flood risk : (1) Damodar catchment – 1298 mm (14.4–18.3% positive change); (2) Barakar catchment – 1267 mm (11.7–19.1% positive change); and (3) lower Damodar catchment – 1339 mm (12.1–16.6% positive change). Mann-Kendall test and Sen’s slope reveal a significant increasing trend in annual rainfall: (1) 1.64–3.78 mm year−1 in the Barakar catchment, (2) 0.85–2.32 mm year−1 in the Damodar catchment, and (3) 0.46–4.80 mm year−1 in the lower Damodar catchment (Table 13.5).

Fig. 13.6
The five maps represent, A: the mean annual rainfall from 2001 to 2020 over the upper catchment of Damodar River Basin along with a color gradient scale for mean rainfall in millimeters, and B to E: flood events in September 2000, 2006, 2007, and 2011 over the upper catchment of Damodar, along with the color gradient scales for 17 to 23 September 2000, 21 to 24 September 2006, and 22 to 25 September 2007, and 14 to 16 August 2011 cumulative rainfall in millimeters. The values and dates of peak discharge recorded at Rhondia are mentioned at the bottom.

Spatial distribution of rainfall over the upper catchment of Damodar: (a) mean normal rainfall distribution of period 2001–2020 in the upper catchment of Damodar, showing west–east increasing trend, (b) an event of maximum 290 mm rainfall (September, 2000) generated streamflow of 6387 m3s−1, (c) an event of maximum 268 mm rainfall (September, 2006) generated streamflow of 7035 m3s−1, (d) an event of maximum 203 mm rainfall (September, 2007) generated streamflow of 8883 m3s−1, and (e) an event of maximum 235 mm rainfall (August, 2011) generated streamflow of 5211 m3s−1

Table 13.5 Summary of rainfall record (1970–2015), M-K Test, and Sen’s slope in the DRB

Now, the analysis is concentrated on the post-dam records of flood events which reflect the spatial concentration of 3–4 days flood producing rainfall and the resultant peak discharge at Rhondia. The mean annual rainfall (2001–2020) of the upper catchment varies from 1219 to 1923 mm (Fig. 13.6a) which is exceptionally extortionate, signifying high moisture laden basin area. Four distinct maps of flood events are taken into consideration to depict the moisture condition over the upper catchment during short period of heavy rainfall:

  • Seven days (17th–23rd September, 2000) continuous rainfall of 34–290 mm was received in the Damodar and Barakar catchment due to tropical depression (Fig. 13.6b). The most intense rainfall of 251–290 mm was recorded around the Panchet and Maithon reservoirs. That period of cumulative rainfall generated maximum peak discharge of 6387 m3 s−1 at Rhondia on 23rd September, 2000.

  • Four days (21st–24th September, 2006) rainfall varied from 52.5 to 268 mm, and the Damodar catchment received alone cumulative rainfall of 201–268 mm (Fig. 13.6c). After DVC flow regulation on 24th September, 2006, the recorded peak discharge was 7035 m3s−1.

  • Four days period (22nd–25th September, 2007) of 50–203 mm rainfall (Fig. 13.6d) generated maximum peak discharge of 8883 m3s−1 at Rhondia. The region around Panchet and Maithon reservoirs contributed more than 151 mm rainfall within 4 days.

  • From 14th to 16th August, 2011, the upper catchment received rainfall of 48–235 mm (Fig. 13.6e), and more than 101 mm rainfall was recorded over the Damodar catchment within 3 days. During that rainfall event, the Durgapur Barrage was compelled to release maximum peak discharge of 5211 m3s−1 on 16th August, 2011.

Finally, an exponential relationship between peak discharge (Q peak) and 3–4 days cumulative rainfall of upper catchment (R cum) is established on the basis of post-dam flood records:

$$ {Q}_{\textrm{peak}}=2213.1{\textrm{e}}^{0.0038\ {R}_{\textrm{cum}}}\left({R}^2=0.6838\right) $$
(13.18)

From this empirical relationship a forecast of flood-generating rainfall is developed for 2-year, 10-year, 50-year, and 100-year floods (design flood developed using log-Pearson Type III distribution) in the DRB :

  1. 1.

    2-year flood (3254 m3s−1): 205 mm rainfall

  2. 2.

    10-year flood (6676 m3s−1): 304 mm rainfall

  3. 3.

    50-year flood (9417 m3s−1): 360 mm rainfall

  4. 4.

    100-year flood (11,969 m3s−1): 412 mm rainfall.

5.2 Impact of Dam on Hydrological Variability

Few significant studies (Glass, 1924; Bhattacharya, 2011, Ghosh & Mistri, 2015; Ghosh & Guchhait, 2016; Karim & De, 2019; Singh et al., 2019) revealed the dam-induced changes in annual hydrograph, streamflow , and maximum flood discharge of the Damodar River. Here, a number of important hydrologic observations are presented to know the flood hydrological variability of a dam-controlled river. Annual hydrograph (Fig. 13.7a) of pre-dam (1934–1957) and post-dam (1958–2015) shows a marked shifting of peak monsoon flow from August to September due to flow regulation of DVC dams. To maintain flood storage of first half monsoon, the DVC dams are now compelled to release excess water during 2nd half of monsoon. It also reflects the changing period of flood occurrence: (1) pre-dam maximum likelihood of flood event was August, and (2) post-dam maximum likelihood of flood event is September. Due to dam-controlled flow regulation, the average monthly peak flow is now reduced up to 28.94% from the previous natural condition (decreased from 1238 to 879 m3s−1). Mean monthly discharge of Damodar River was regulated by DVC dams since 1958. Pre-dam pre-monsoon base flow was near about 12.16 m3s−1, but dam regulation has maintained a base flow of 34.41 m3s−1 (Fig. 13.7b). Under natural condition, the mean monsoon peak discharge was greater than 1500 m3s−1 in a number of cases, but that value has reduced significantly in post-dam period.

Fig. 13.7
A: a line graph of mean monthly discharge, cumecs versus months from January to December. It plots 2 lines for pre-dam and post-dam. The pre-dam has the highest peak of 1230 in August. B: a marked variableness of mean discharge, cumecs versus date from 1 January 1934 to 1958 for the pre-dam period and from 1 January 1958 to 1979 for the post-dam period. The curves have spikes. 4 horizontal lines represent a confidence interval at 99% significance level at 1646 and 1071 cumecs in the pre-dam period and 1684 and 658 cumecs in the post-dam period.

(a) Annual hydrograph of pre-dam and post-dam period based on mean monthly discharge and (b) marked variableness of mean discharge during pre-dam and post-dam period, delimiting confidence intervals of discharge

In natural condition, the Damodar River had high potentiality to cause violent flood flow. Between 1934 and 1948, the highest recorded average peak discharge was 14,767 m3s−1 on 10 October, 1941 (Fig. 13.8a). Another peak discharge of 18,123 m3s−1 was recorded on 12th August, 1935. Pramanik and Rao (1952) estimated that in the pre-dam period, a maximum discharge of 28,317 m3s−1 could be likely exceeded once in about 850 years. From 1823 to 1942, 12 times the peak discharge of flood events reached beyond 10,000 m3s−1 and during 5 times the river experienced discharge beyond 17,000 m3s−1. A significant variation of annual peak discharge time series is observed. Since 1823, 13 times the annual peak discharge or extreme flood flow crossed 10,000 m3s−1 in the Damodar River, reflecting violent nature of flood . In pre-dam period (1933–1957), calculated CI (at 99% significance level) varied from 6055 to 10,459 m3s−1 (range – 4404 m3s−1) which is considered an exceptional high flow as compared to present condition (Fig. 13.8b). Since 1958, the DVC dams have effectively reduced CI which now ranges between 2790 and 4511 m3s−1 (range – 1721 m3s−1), reducing the maximum likelihood flood flow up to 53.92–56.87% in the river. Importantly the post-dam time series shows a positive growth trend (1958–1978 and 1979–2015) which matches with increasing trend of annual rainfall in the DRB since 1970 (as discussed in pervious section). M-K test is performed on two separate time series (N = 21 and N = 37), separated on the basis of maximum 1978 flood flow (10,919 m3s−1); Kendall tau (0.1238 and 0.2012) shows significant (rejecting null hypothesis and accepting alternative hypothesis, i.e., slope is not zero at 0.05 significance level) but weak time series trend (Table 13.6). The positive Z value, 0.75492 and 1.7395. expresses an increasing trend of annual peak discharge with time. Sen’s slope of two time periods is expressed as: (i) 44.487 m3s−1 per year (1958–1978) and (ii) 46.639 m3s−1per year (1979–2015).

Fig. 13.8
The two spike graphs represent the peak discharge in cumecs versus years from 1823 to 1957 for pre-dam and from 1957 to 2015 for post-dam periods. A: horizontal lines for confidence interval at 99% significance level are plotted at 10459 and 6055 cumecs in the pre-dam period and 4511 and 2790 cumecs in the post-dam period. B: horizontal lines for mode and Q values are plotted in the pre-dam and post-dam periods. The values for S D, skewness, mean, median, mode, and maximum are present for pre-dam and post-dam periods.

(a) Erraticism between natural annual peak flow regime and dam-induced changes in annual peak flow, delimiting marked variation of confidence intervals, and (b) observed trends of annual peak flow during pre- (decreasing) and post-dam period (increasing), including variations of hydrological statistics

Table 13.6 M-K test and Sen’s slope analysis for post-dam annual peak dishcarge time series

Apart from the annual peak discharge analysis, NRCS-CN output exhibits the spatial variability of curve number (CN) and surface runoff depth in the selected flood events of 2000 and 2006 to portray the regions of maximum water concentration (or excess water coming from which areas in the upstream watershed of Panchet and Maithon dams). The runoff curve number (i.e., CN is an empirical parameter used for predicting direct runoff during a rainfall event) is primary guided by the HSG and LULC which are mapped in the upper catchment of Damodar. GIS analysis suggests that a maximum area of 17,011 km2 (85.39% of total upper catchment area) is categorized as HSG C (viz., loam, sandy clay loam, silt loam, clay loam, and silty clay loam soil textures), and other categories are HSG D (463 km2), HSG C/D (319 km2), and D/D (56 km2). In the catchment, an area of 4948 km2 (24.84% of total upper catchment area) is designated as natural vegetation and forest cover, and the area of cropland and seasonal fallow land covers 9702 km2 (48.71% of total area). Alongside, other LULC classes are designated as waterbodies/rivers (525 km2), grassland (40 km2), scrub/shrub/bushes (2178 km2), flooded vegetation (34 km2), bare land (42 km2), and built-up/settlement (2493 km2), respectively. Using Python programming in ArcGIS 10.4, the weighted CN (0–100) is derived for the upper catchment from the raster database of HSG and LULC. The mean weighted CN of the catchment is 78.57 which signifies quite high runoff potentiality of the hard rock terrain. The CN map reflects the maximum coverage of range 51–75, followed by range 76–100 (Fig. 13.9a). The runoff maps of rainfall events of September, 2000 and September, 2006 exhibit the following findings:

  • First case: The total rainfall, during 13–23 September, 2000, varied widely from 34 to 290 mm (Fig. 13.9b), and it had maximum record (>201 mm) around the adjoining parts of Panchet and Maithon dams. For that amount of 7 days cumulative rainfall that parts of catchment yielded potentially 151–200 mm runoff, having extreme concentration of 201–282 mm runoff at selected pockets. That amount of runoff on a vast region accumulated in the DVC reservoirs, and finally, the dams were compelled to release excess water at the rate of maximum 6387 m3s−1 on 23 September, 2000 in the Damodar River, inundating the lower valleys of Purba Bardhaman, Hooghly, and Howrah districts.

  • Second case: The 4 days total rainfall, from 21 to 24 September, 2006, ranged between 52.5 and 268 mm (Fig. 13.9c), and the torrential rainfall of >151 mm was observed in the hilly tract of Damodar catchment and downstream of Panchet and Maithon dams. That amount of heavy rainfall yielded a runoff range of 10–207 mm, having extreme concentration (>101 mm) around those parts. As a result, on 24 September, 2006, the recorded maximum discharge of Damodar was 7035 m3s−1, causing havoc flood in the low-lying floodplains of Hooghly and Howrah.

Fig. 13.9
The three maps. A: titled N R S C curve number developed for the upper catchment of the Damodar River basin, it represents regions of C N ranging from 0.062 to 100. B: titled surface runoff for the upper catchment of the Damodar River basin, it represents regions of 17 to 23 September 2000 C N-based runoff ranging from 0.0509 to 282 millimeters. C: titled surface runoff for the upper catchment of the Damodar River basin, it represents regions of 21 to 24 September 2006 C N-based runoff ranging from 0.0654 to 207 millimeters.

(a) An important and useful map of weighted NRCS curve numbers developed for the upper catchment of Damodar (including basin area of Barakar River), (b) spatial extent of CN-derived potential runoff (50–282 mm) during the flood event of 17–23 September 2000, and (c) spatial extent of potential runoff (50–207 mm) during the flood event of 21th–24 September 2006

5.3 Flood Frequency and Hydrological Risk

The empirical formulae of predicting maximum flood peaks (Table 13.1) have yielded variable results for the Damodar River (considering 19,920 km2 of catchment area from Rhondia gauge station): (i) Dickens result – 23,474 m3s−1; (ii) Inglis result – 17,455 m3s−1; (iii) world envelope curve result – 26,286 m3s−1; and (iv) envelope curve of Rakhecha and Singh result – 32,121 m3s−1. The maximum recorded flood peak in pre-dam period was 18,406 m3s−1 (1913), and in post-dam period it was 10,919 m3s−1 (1978). So, the observed value is very much close to the result of Inglis empirical formula. In this study, two different time series (annual peak discharge of pre-dam and post-dam) of two stations (Rhondia and Harinkhola) are taken into consideration for flood frequency analysis (FFA) . From the pre-dam (1933–1957) and post-dam (1958–2015) database of Rhondia station, it is estimated that in pre-dam period, i.e., natural condition, there are a greater number of floods above the mean peak discharge (7413 m3s−1) than the post-dam period mean (3650 m3s−1). The curve which fits the annual peak flood discharge data on a log-log paper will not be a symmetrical curve, but a skew curve which unsymmetrical, i.e., points do not lie on the straight line but the line bends off. The general slope of this curve is given by the coefficient of variation (C v), and the departure from the straight line is given by the coefficient of skew (C s). In pre-dam period the smaller value of C v (0.312) indicates occurrence of floods in same magnitude, but large C v (0.592) of post-dam period reflects a range in the magnitude of floods due to dam control. The coefficient of flood (Cf) indicates the general magnitude of the floods above one unit in the particular river; it fixes the height of the nonlinear curve above the base. In pre-dam period Cf was extremely huge, i.e., 5.767, but after dam construction it reduces to 2.855, decreasing (49.50%) the flood curve height significantly.

Distribution of annual peak discharge fits well log-Pearson Type III (LPT3) distribution, as significant in Goodness-of-Fit test, in the case of DRB . The output shows very less deviation of LPT3 predicted flow (Q pred) in respect of observed flow (Q obs), fitting a linear relationship of Q pred = 88.515 + 0.9758 Q obs (R 2 = 0.9757). The hydrological risk, associated with FFA , is assessed here in terms of reoccurrence interval and exceedance of probability measures. The results of FFA exhibit a notable predictability of flood design in respect of pre-dam (1933–1957) and post-dam (1958–2015) probability distribution. The key statistical findings are mentioned as follows:

  1. 1.

    There is a reduction (up to 55.79%) of mean annual peak discharge (Q peak) or flood flow from pre-dam to post-dam period due to the regulated control of DVC dams during the monsoon months. The weighted skewness (C w) of pre-dam period is −0.51074 which was transformed to very high, i.e., 2.234, during post-dam period, signifying high range between flood magnitude. Another LPT3 derived parameter is coefficient of skewness (C s) which is exceptionally very high (3.6962) during pre-dam period, but after dam construction due to flow regulation and flood reserve of reservoirs C s reduces to −0.757. Kurtosis of pre-dam period is 1.776 which changed to 2.625 in post-dam period. In both cases, kurtosis reflects a fat-tailed distribution (leptokurtic), having very high skewness and high degree of peakedness of the flood frequency distribution with high probability of extreme outlier values (i.e., maximum likelihood of flood events).

  2. 2.

    LPT3 shows that the annual peak discharge of less than 5658 m3s−1 (during pre-dam period) occurs with an exceedance probability of greater than 80%, but in post-dam period the 80% exceedance probability of flood occurrence is reduced to only 1897 m3s−1 in the Damodar River. It is noteworthy to mention that an extreme peak flow of 10,919 m3s−1 (observed in 1978) can be occurred having only 1.69% chance (in any one year) at present condition and that flow had 19.34% probability of occurrence during pre-dam period (Fig. 13.10).

    Fig. 13.10
    A dot plot graph of the peak discharge in cumecs versus the return period in years, it plots two dots for pre-dam and post-dam phases of peak values of 18112 cumecs in 26 years and 10912 cumecs in 59 years. The values of flood discharge in cumecs are presented for pre-dam and post-dam phases based on the R T, in years, at the center.

    Variability of LPT3 flood frequency distribution in pre- and post-dam period, showing estimated changes in design floods and return periods

  3. 3.

    Recurrence interval or return period (R T) provides the estimated interval between events of a similar size or intensity of flood . In pre-dam period, a flood flow of 18,112 m3s−1 (observed in 1935) has 26 years R T, and it has 3.846% chance of being exceeded in any one year. The pre-dam flow of 4514 m3s−1 has only R T of 1.08 years (almost regular event), having 92.30% chance of being exceeded in any one year. A 100-year flood , a flood event that has 1% probability or 1 in 100 chances of being equalled or exceeded in any given year, is estimated about 19,018 m3s−1. Alongside, FFA estimates the 2-year flood was 7782 m3s−1 having 50% chance of occurrence in one of given years. It shows the propensity of past furious floods with a maximum likelihood of occurrence in the DRB . For that reason, the DVC had a prime objective to control the abnormal extreme flow under a critical level in the lower Damodar River.

  4. 4.

    The flood regulation system of DVC dams has turned the hydrological regime to a large extent. Now, a maximum flood flow of 10,919 m3s−1 has R T of 59 years, and it has only 1.604% chance of being exceeded in any one year (Fig. 13.11a). At present, annual peak discharge of 1443–1434 m3s−1 has 1.11–1.09 years R T, and it has 89–91% chance of occurrence in any one year. The 100-year flood of post-dam period is estimated about 11,969 m3s−1 (reduction of 37.06% from the pre-dam 100-year flood flow), which has only 1% chance of occurrence in one of given year (i.e., 1 in 100 years). The 2-year flood (50% probability of occurrence) is estimated about 3234 m3s−1, (reduction of 58.44% from the pre-dam 2-year flood flow).

  5. 5.

    FFA at Harinkhola gauge station (1978–2015) reflects the extreme downstream flood flow condition of the Mundeswari River (western bifurcated channel of main Damodar River). The 100-year flood at this station is near about 8058 m3s−1, and the estimated 2-year flood is 2045 m3s−1. The observed maximum flood flow is 6208 m3s−1 (observed in 1978) which has 39 years R T, having 2.6% chance of occurrence in one of the given years. It is observed that there is 80% probability to encounter peak discharge of 1156–1183 m3s−1 in the lower Damodar River (Fig. 13.11b).

Fig. 13.11
Two dot plots cum line graph of the peak discharge in cumecs versus the return period in years and annual exceedance probability in a and b. It has 2 dots for Rhondia and Harinkhola and 2 lines for Log. of Rhondia and Harinkhola. A: the dots and lines intersect at Q equal to 10919 cumecs at Rhondia and 6209 cumecs at Harinkhola with R T equal to 59 and 39 years. B: the dots and lines intersect at Q equal to 1823 cumecs and Q equals 1156 cumec, with an 80 percent probability of occurrence.

(a) Dam-controlled LPT3 distributions of annual peak discharge in relation to return period at Rhondia (Damodar River) and at Harinkhola (Mundeswari River) and (b) comparative analysis of variability in annual exceedance probability of peak discharge at two river gauge stations

5.4 1D Flood Simulation of Unsteady and Steady Flow

“Steady flow” refers to conditions that do not change with time. Mathematically, steady flow implies that (∂h/∂t) = 0, (∂V/∂t) = 0, and (∂Q/∂t) = 0. “Uniform flow” refers to conditions that do not change with space. Unsteady flow equations in open channels with friction define kinematic and dynamic waves. The model is performed on two bifurcated channels of the main Damodar River, viz., Mundeswari River and Damodar/Amta River (Fig. 13.12). In the first case, a database of unsteady flow (observed at Durgapur Barrage) is used in 1D flood simulation. A current low-magnitude flood wave (1410–1811 m3s−1) occurred during June 2021, and a hydrological simulation of discharge and gauge height was retrieved from IWD web database to understand the current flow regime at spatial scale in the platform of HEC-RAS 6.2 version. The hydrograph of early monsoon rainfall shows an escalation of base flow (nearer to 400 m3s−1) to 1811 m3s−1 at a sudden due to release of excess water from the Durgapur Barrage (1 June–6 July 2021) (Fig. 13.13a). The unsteady flow got momentum from 18 June 2021 (846 m3s−1) and it reached peak on 22 June 2021, and then it gradually reduced to 487 m3s−1 on 6 July 2021. A strong relationship between streamflow or daily discharge (Q un) and station gauge height (G h) was observed at Jamalpur and Champadanga gauge stations. With a high coefficient of determination, the stage-gauge height curve of Damodar River followed a power regression positive trend (Fig. 13.13b, c):

  • At Jamalpur gauge station: G h = 9.4998 Q un 0.094

  • At Champadanga gauge station: G h = 3.6743 Q un 0.1705

Fig. 13.12
The area map represents the flood-prone channels of the lower Damodar River basin. The rivers, block boundary, district boundary, and lower Damodar basin are highlighted. The color gradient scale for elevation ranges from low: 0 to high: 41 meters.

Flood prone channels of lower Damodar River Basin (considered in HEC-RAS 1D hydrodynamic model ) on the terrain of 0–41 m elevation, covering the administrative blocks of Purba Bardhaman, Hooghly, and Howrah districts (West Bengal)

Fig. 13.13
A hydrograph and two scatter plot graphs. A: a hydrograph represents the frequency of stream flow with a peak value of 1800 at the Durgapur Barrage. B and C: 2 scatter plot graphs of gauge height h in meter versus stream flow Q in cumecs with h equal 9.4998 Q power 0.094, and R square equal to 0.848 at Jamalpur in b, and h equals 3.6743 Q power 0.1705, and R square equal to 0.7757 at Champadanga, along with 2 horizontal lines for E D L and D L in c.

(a) Schematic hydrograph of period 1 June–6 July 2021 observed at the Durgapur Barrage, (b) stage-streamflow rating curve at Jamalpur gauge station, and (c) stage-streamflow rating curve at Champadanga gauge station

A flood management strategy is deduced from the empirical relationship. From this relationship an estimate of bankfull discharge (critical flow level for downstream inundation or overbank flow) can be established on the basis of danger level (DL) and extreme danger level (EDL) gauge heights at two stations. Alongside, the estimated bankfull discharge (Q bank) reflects the present carrying capacity of channel (Table 13.7). Jamalpur gauge station is a vital location for flood prediction because from this site the main river is bifurcated into Mundeswari channel and Damodar/Amta channel. At this site, Q bank of DL (23.24 m from msl) and EDL (23.54 m from msl) are 3198 m3s−1 and 3326 m3s−1, respectively. The peak flow at Champadanga gauge station determines the flood condition of Hooghly and Howrah districts. At this site, Q bank of DL (12.9 m from msl) and EDL (13.5 m from msl) are 1353 m3s−1 and 1651 m3s−1, respectively. So, from this critical bankfull flow database, the DVC and IWD should regulate the flood flow or peak discharge (maintaining flow under critical level) to save the floodplains from a long period of inundation . During the unsteady flow of June–July 2021 the streamflow did not cross the bank at Jamalpur, but it overtopped the bank DL from 20–24 June 2021 (>1410 m3s−1) at Champadanga, signifying the low carrying capacity of Amta channel and downstream vulnerability of flood .

Table 13.7 HEC-RAS estimated present critical bankfull discharge in the Mundeswari and Damodar channel

1D flood simulation of HEC-RAS exhibits the floodplain inundation depths during a period of unsteady flow at downstream of Harinkhola gauge station (22°50′22.38″ N, 87°54′15.75″ E). From the maps (Fig. 13.14) it is observed that in the floodplain of Mundeswari, the maximum flood depth of certain discharge (20–25 June 2021) varies from 1 to 8 m in the active channel area and the adjoining floodplain. On 22 June 2021 the region around Harinkhola, Udna, and Khanakul experienced inundation depth of greater than 3 m for the discharge of 1811 m3s−1 which had crossed the bankfull discharge of DL and EDL (Table 13.5). The most critical level of bankfull discharge is 1518 m3s−1 at downstream of Harinkhola. The hydrological estimates of downstream and upstream cross-sections reveal in Table 13.8. At upstream cross-section near Gotan, the channel can accommodate maximum flow of 1685 m3s−1 and the flow area is 1057 m2, but at downstream cross-section near Khanakul region, the flow area is recued to 548.11 m2 (48.15% reduction from upstream), and total flow along cross-section is maximum 1457 m3s−1 (13.53% reduction from upstream). Energy grade slope of downstream cross-section is 0.002270 m m−1 which is nearer to 0.00440 m m−1 at upstream (almost double than downstream). For the certain maximum flow, the downstream stream power can reach up to 197.29 N m s−1 (velocity of 2.66 m s−1), having shear stress of 74.26 N m−2, but it is relatively smaller in the case of upstream. The Froude number (F r) of two cross-sections (0.214–0.461) exhibits subcritical flow of lower energy state (slow/tranquil flow regime) during the observed flood event.

Fig. 13.14
A set of six maps represent the regions with flood depth in meters between Harinkhola, Udna, and Khanakul based on an unsteady flow simulation from 20 June 2021 to 25 June 2021 in a to f. A color gradient scale for flood depth in meters is present in all maps at the bottom right.

HEC-RAS 1D floodplain inundation modelling output maps (af) of Mundeswari River (between Harinkhola and Khanakul) based on unsteady flow simulation (20–25 June 2021), noticing observed maximum discharge (1811 m3s−1) on 22nd June, 2021

Table 13.8 HEC-RAS derived hydrologic statistics (unsteady flow) of the cross-sections along Mundeswari River and Damodar/Amta River

In the steady flow 1D flood modelling the post-dam LPT3 designed potential discharges of 2-year R T flood (3254 m3s−1), 5-year R T flood (5324 m3s−1), 10-year R T flood (6676 m3s−1), and 25-year R T flood (8292 m3s−1) are taken into consideration to observe the spatial extent of floodplain inundation along the Mundeswari River. From the maps (Fig. 13.15) it is observed that maximum part of active channel area (38.84 km) can experience a flood depth of 4–8 m in 2-year flood , with floodplain inundation depth of less than 4 m at some parts of Khanakul. During 5-year and 10-year flood event, the depth can reach 4–12 m from the bifurcation point to Khanakul, and it has maximum chance of overbank flow crossing the embankments of Khanakul region. In a 25-year flood , the total channel and active floodplain area can experience flood depth of beyond 8 m, and in between Harinkhola and Khanakul, the depth can exceed 12 m, recognizing the critical site of embankment failure and flood vulnerability (exceeding EDL and EDL).

Fig. 13.15
The four maps represent the 2, 5, 10, and 25 years return period flood inundation in a to d. It highlights the regions with flood depth ranges from 0 to maximum in meters in Harinkhola and Khanakul.

HEC-RAS 1D model derived potential floodplain inundation maps (ad) of Mundeswari River based on steady flow simulation (LPT3 distribution designed 2-year, 5-year, 10-year, and 25-year flood discharge), noticing flood depth of over 12 m during 25-year flood of 8292 m3s−1

In the 1D flood model of unsteady flow, the downstream section (Damodar/Amta channel) of Champadanga gauge station (22°50′22.92″ N, 87°58′11.75″ E) shows marked variation of flood depths (1–8 m) for the streamflow simulation during 1 June–6 July 2021. On 20 June, 2021, due to flow rate of 1410 m3s−1, the flood depth varied from 1 to 4 m below Udaynarayan region, and the active channel part experienced greater than 6 m deep water (Fig. 13.16). On 22nd June, 2021 the flow rate reached up to 1811 m3s-1 and the flood depth exceeded 6 m near Rajbalhat region, and at the downstream of Udaynarayanpur, the depth touched 2–6 m range, across the embanked floodplain. The observed discharge from 20th to 25th June, 2021 had crossed the bankfull limit of DL and EDl (Table 13.5), and the vast region of Joynagar and Udaynaryanpur was flooded. At upstream cross-section near Jamdara, the channel can accommodate maximum flow of 1378 m3s−1 and the flow area is 687 m2, but at downstream cross-section near Udaynarayanpur region, the flow area is recued to 478 m2 (30.42% reduction from upstream), and total flow along cross-section is maximum 1081 m3s−1 (21.55% reduction from upstream) (Table 13.6). Energy grade slope of downstream cross-section is 0.000471 m m−1 which is nearer to 0.000750 m m−1 at upstream. The downstream stream power can reach up to 81.37 N m s−1 (velocity of 1.99 m s−1), having shear stress of 36.47 N m−2, but it is relatively higher in case of upstream. The Froude number (F r) of two cross-sections (0.221–0.285) exhibits subcritical flow of lower energy state during the observed flood event of 1st June– 6th July, 2021.

Fig. 13.16
The six thematic flood depth maps of Damodar or Amta Channel represent the regions with flood depth ranges from 0 to maximum in meters in Rajbalhat, Udaynaryanpur, and Joynagar from 20 June to 25 June 2021 in a to f.

Thematic flood depth maps (af) of Damodar/Amta Channel (between Rajbalhat and Udaynaryanpur) using HEC-RAS 1D floodplain inundation modelling on unsteady flow simulation (20th–25th June, 2021)

In steady flow 1D hydrodynamic model, the Damodar/Amta channel (49.26 m stretch) can experience devasting flood because all LPT3-designed potential discharges of 2-year, 5-year, 10-year, and 25-year flood can exceed the bankfull limit of Champadanga gauge station (Fig. 13.17). In a 2-year flood (3254 m3s−1), the maximum floodplain inundation depth can range from 6 to 8 m from the bifurcation point to Udaynarayanpur. During 5-year and 10-year floods , the depth of flood water can exceed 8 m at downstream of Champadanga. The flood depth can reach beyond 10 m during a 25-year flood along the 34.40 km stretch of Damodar channel. The most vulnerable site of embankment failure and overbank flow is stretch between Rajbalhat and Udaynarayanpur where the flood depth can cross 10 m limit for the discharge of 1811 m3s−1.

Fig. 13.17
The four potential floodplain inundation maps of the Damodar or Amta channel represent the regions with flood depth ranges from 0 to maximum in meters for 2, 5, 10, and 25-year return period flood inundation in a to d.

HEC-RAS 1D model derived potential floodplain inundation maps (ad) of Damodar/Amta Channel based on steady flow simulation (LPT3 distribution designed 2-year, 5-year, 10-year, and 25-year flood discharge), observing flood depth of greater than 12 m during a 25-year flood (8292 m3s−1)

6 Discussion

The DVC has now completed 75 years in 2022, and the authority has experienced a number of success (mainly irrigation water supply and flood control) as well as failure (mainly river metamorphosis and downstream recurrent flood ), but it is worthwhile to mention that the prime objective of DVC was to make the Damodar Valley as an Eden of economic potentiality or “Valles Opima” of India (Kirk, 1950) which was partly achieved. The DVC dams and flood regulation system are now not able to manage sudden peak monsoonal flow to save the floodplains of lower DRB (mainly Purba Bardhaman, Hooghly, and Howrah districts). During late monsoon consecutive torrential rainfall from the tropical depressions or cyclones, the last two terminal dams, Panchet and Maithon, are compelled to release excess water (less capacity of flood storage due to siltation) which recurrently turns into nightmare for the inhabitants of the Damodar fan-delta floodplains. The funnel-shaped basin size, with a wide upper catchment and a narrow bottle-neck location at downstream, has potentiality of phenomenal increase in peak discharge in the lower Damodar River. The DVC dams have successfully reduced the flood heights, i.e., furious peak discharge of greater than 12,000 m3s−1 with short duration, but now the flood peaks are decreased significantly, except flood of September, 1978 (10,919 m3s−1), and the duration of inundation period becomes large. Preliminary report suggested to build eight large dams to moderate maximum peak discharge of 28,000 m3s−1–7079 m3s−1 at Rhondia gauge station, but now five dams (including Tenughat Dam ) only provide flood storage of 3591 million m3 which was only 55% of storage capacity as mentioned in the report. Therefore, the present flood regulation system of DVC does not have full capability to regulate exceptional peak discharge of 100-year flood (11,969 m3s−1).

In the trans-Damodar area of fan-delta (i.e., Late Quaternary – Recent floodplains of Mundeswari and Amta channels), the floods are encountered in each year, and it is mainly caused by the drainage congestion in the channels, tidal influence at outlet, and increasing siltation which promotes reduction of flow area in the active channel part. Hydrometeorological observations exhibit that in late monsoon month (September–October, 2021), the fan-delta region receives more than 251 mm monthly rainfall, reaching high root zone moisture at maximum level (0.351–0.425 m3/m3) and high standardized runoff index (1.51–2.44) in the active floodplains (Fig. 13.18). During that time, the region does not capacity to absorb excessive water coming from high flood discharge (due to 3–4 days rainstorm in the upper catchment), and then, the inundation of floodplains for longer period was an inevitable condition. In addition, the Quaternary floodplains of Damodar fan-delta region have high potentiality of surface runoff in a range of 172–608 mm during the monsoon months, and the free flow is hampered due to tidal inflow from the Bhagirathi-Hooghly River . The miserable flood situation is aggravated by adding of excess water from the DVC canals by breaches, tail discharge, and over toping. The further analysis suggests some following suggestions to improve the flood management strategies of DRB :

  • Intense short spells (usually 3–4 days) of extreme rainfall (150–290 mm) are now very common in each year due to aggravation of extreme climatic events in response to global climate change. A rainstorm magnitude equal to or greater than 304.8 mm may occur once in 100 years. This study has estimated the probable maximum rainfall for a given magnitude of flood : (a) 2-year flood (3254 m3s−1) rainfall, 205 mm; (b) 10-year flood (6676 m3s−1) rainfall, 304 mm; (c) 50-year flood (9417 m3s−1) rainfall, 360 mm; and (d) 100-year flood (11,969 m3s−1) rainfall, 412 mm. Therefore, from the early precise prediction of heavy rainfall (now given by Indian Meteorological Department), the DVC authority can regulate the flows in all reservoirs to reduce the peak flow under 7079 m3s−1 at Rhondia or at the Durgapur Barrage. In this case, a good coordination between DVC and IWD is needed to act on real-time flood forecast for the sake of inhabitants living in the low-lying floodplains of Hooghly and Howrah districts.

  • Reduction of reservoirs’ flood storage capacity, due to excessive siltation, is another problem in the DRB . The Maithon and Panchet reservoirs have lost significant amount of overall storage capacity, viz., 27.4% in Maithon and 15.9% in Panchet, respectively. The sedimentation rates of the reservoirs are depicted as follows: (a) Konar, 1748 m3 km−2 year−1; (b) Maithon, 1076 m3 km−2 year−1; (c) Panchet, 631 m3 km−2 year−1; (d) Tenughat, 716 m3 km−2 year−1; and (e) Tilaiya, 2792 m3 km−2 year−1 (Ghosh et al., 2022a). The sedimentation rate can be managed by installing small check dams in the gullies or streams of upper catchments. Regular dredging of the reservoirs is very much needed to increase the functional longevity of dams and to check flood risk .

  • HEC-RAS 1D hydrodynamic model reveals that present carrying capacity (i.e., critical limit of overbank flow) of Mundeswari and Damodar/Amta channel is near about 1518–1822 m3s−1 and 1353–1651 m3s−1, respectively. It is predicted the floodplain inundation region (flood depth of 1–12 m) in respect to 2-year, 5-year, 10-year, and 25-year flood . The most vulnerable sites of embankment failure and overbank flow are the 27 km long Damodar/Amta channel from Rajbalhat to Udaynarayanpur and 19 km long Mundeswari channel from Udna to Khanakul. If the HEC-RAS 1D model database is calibrated and validated with actual field result or SAR (synthetic aperture radar) flood dataset, the floodplain inundation prediction can be done precisely for a certain streamflow in the river valleys of Hooghly and Howarh districts.

  • Finally, the Damdoar fan-delta region should be saved from drainage congestion during the monsoon months. Construction of marginal embankments , settlements, railways, and dense network of roads have aggravated the miserable flood situation (Fig. 13.19a). Embankments serve the purpose of preventions of floods for the time being but tend to create more problems later. Behind the embankments vested interests grow up encroaching into the active floodplain of the river. Development of additional settlements, roads, and cropland, around the active floodplains, hinders the flow paths of overbank discharge, and it transforms the palaeochannels of Damodar to abandoned channels permanently. It is suggested that if the palaeochannels or abandoned channels are linked with main river, Mundeswari and Damodar/Amta, through sluice gates, then the peak monsoon flow can be distributed along those channels during floods to reduce the rate of peak discharge in main river (downstream of Harinkhola and Champadanga) and to save the low-lying floodplains from recurrent inundation (Fig. 13.19b).

Fig. 13.18
The four hydrometeorological maps of the Damodar fan-delta represent the mean rainfall in September 2021 ranges from 130 to 544 millimeters in a, runoff range from 172 to 608 millimeters in b, standard run-off index in September 2021 ranges from minus 0.795 to 2.44 in c, and root-zone soil moisture in September 2021 ranges from 0.185 to 0.425 in d.

Hydrometeorological maps of the Damodar fan-delta (covering floodplains of Mundeswari and Damodar/Amta channel) – (a) spatial concentration of monsoon rainfall (September 2021), (b) mean runoff potential of monsoon months based on NRCS-CN method, (c) Standard Runoff Index (SRI) map of September 2021 (SRI > 0 means surplus runoff water) and (d) Root-Zone Soil Moisture map of September 2021 (RZSM > 0.40 means excess soil moisture)

Fig. 13.19
2 area maps represent the dense network of rivers or streams, roads, and railways in the floodplain of the Damodar fan-delta region on the left map, and the active flood prone-area and downstream paleochannels, and Mundeswari, and Damodar channels on the right map.

(a) Dense network of roads and railways in the floodplain of Damodar fan-delta region, promoting drainage congestion and (b) downstream palaeochannels and abandoned channels of Mundeswari and Damodar/Amta channel, having the option of reconnecting with the main river through sluice gates

7 Conclusion

Seven decades (completed 75 years) have passed since the partial implementation of the DVC project. The life span of the reservoirs is also coming to an end, and the effectiveness of flood-controlling system is declining. The benefit that was found in the first episode, the level of evil in the next episode is surpassing the inhabitants of lower Damodar valley. The DVC should start to think about the alternative plan to mitigate excess streamflow through construction of another dam or preparation of numerous check dams at upstream. The need of dredging is an immediate task to extend the life span of reservoirs. Alongside the IWD should maintain coordination with DVC during the release of flood water. Alternatively, IWD may think about the rejuvenation of palaeochannels, connecting the old and abandoned courses of Damodar and Mundeswari with the main channel for evenly distribution of the excess streamflow during flood . The current study provides an outlook on the probable maximum rainfall in connection with expected flood discharge and the spatial dimension of the floodplain inundation model, which can be applied to reduce flood risk . The future research need to develop a real-time geospatial model of rainfall – streamflow simulation to predict peak discharge for a certain rainfall and the probable region of inundation or overbank flow. Another application of 1D/2D hydrodynamic model is now needed to calculate the flooded areas of different land use categories for estimating the monetary loss and economic vulnerability .