Keywords

1 Introduction

Risk management is an integral part of the management of organizational processes in construction. The peculiarities of risk management in the construction of industrial buildings and structures are the presence of specific factors related to both the technological process, for which the construction object is intended, and constrained construction conditions, dependence on the technological equipment of a particular supplier, as well as the tight deadlines for construction work.

If earlier there was a significant impact of risks associated with the deterioration of the technical condition of building structures due to miscalculations at the design stage or non-compliance with installation technology, now the proportion of risks has increased—errors in estimates, non-compliance and penalties for obligations (mainly temporary) contracts [1].

The risk management process in construction consists of six stages.

The first stage: identification of risks. In particular, the following risks might arise in projects: quality risks; personnel risks; price risks; risks of failure to meet deadlines; risks of strategic decisions; external risks.

Second stage: risk analysis. At this stage, an analysis of the priority of risks and the degree of their impact on the life cycle of the construction project as a whole is carried out.

The third stage: risk measurement. Mathematical and statistical accurate methods commonly used in risk assessment in other industries cannot adequately reflect typical risks in the construction industry.

The fourth stage is risk control. Risk management strategies are adopted as follows: avoidance, reduction, transition to risk, taking risk on yourself.

The fifth stage represents risk monitoring, that is, continuous operational control of the effectiveness of risk management and the adoption of timely measures.

The sixth stage is goal control. After recognizing, analyzing and assessing risks, measures should be taken to control the goals. The whole management process can be divided into subprocesses: determination of the target value, the actual value, comparison of values and analysis of variance [2].

The risk management methodology at the procurement stage was reviewed in [3]. A simple and unified methodology has been successfully tested in determining the systematic risks of the construction of a real construction object.

When determining the risks directly from work on the construction site, the authors [4] proposed a method for calculating: weight factor; weighted average value of risk; exceeding the value of the weighted average risk value; the additional value of exceeding the weighted average risk value; the total amount of risk.

In modern risk management models, the following basic actions are proposed [5]:

risk avoidance (risk prevention, risk avoidance, risk elimination), that is, avoidance of activities that cause the realization of risk. Often the level of this risk is too high, it needs to be brought to an acceptable level; risk minimization (risk reduction, risk optimization and control over it), that is, risk reduction through a system of anti-crisis measures; the use of risk (risk acceptance, risk neglect, risk limitation) is characteristic of minor risks that cannot be eliminated, but with successful management, the realization of this risk makes it possible to increase the profitability of construction.

Risk management in construction mainly depends on intuition, judgment and experience [6]. Formal risk analysis and management methods are rarely used due to lack of knowledge and doubts about the suitability of these methods for activities in the construction industry.

The authors [7] suggest using a construction risk management model (CRMS) based on the method of constructing impact diagrams and Monte Carlo modeling. Alternative risk management strategies include: risk prevention, risk transfer, risk retention, loss reduction, insurance.

As one of the methods for assessing the implementation of risks, a model.

(RMMS) was proposed—a system for implementing the risks of large-scale projects based on the use of the Analytical Network Process (ANP) method to measure the overall effectiveness of risk management in relation to the main risk factors [8].

An approach to decision–making based on fuzzy multiple criteria (FMCDM) was also proposed, in particular for the construction of critical structures such as subways. At the same time, the assessment was carried out on 20 risk factors identified at four sites [9]. To analyze the probability of occurrence of multiple risk factors, the method of direct ranking of fuzzy multiple attributes (FMADR) is used.

Another approach is the use of fuzzy Bayesian networks (FBN) based on the analysis of the risk mechanism to investigate the cause-effect relationships between the stress–strain state of the foundation soil caused by the construction of the tunnel and the variables affecting it [10].

The problem of the impact of failures in construction on the cost of production and on the quality of construction projects was studied by Abdul-Rahman [11].

The security risks at the construction site have a fundamental impact on the lines and construction costs, and the reliability of building structures. Research on this topic was carried out by scientists from China [12], Pakistan [13], North Korea [14].

To assess the risks of increasing the cost and predict the real cost of construction contracts, a method was proposed in terms of a construction cost index [15].

Some opportunities for better risk allocation mechanism and contracting strategies that are based on a trust relationship between the contracting parties were analyzed using the data from the surveys of Canadian developers [16].

When building global facilities, specific risks should also be accounted for:

  • social sustainability (on the example of researching survey data from 120 leading Pakistani experts [17]);

  • political risks for multinational contractors [18];

  • specific risks of geotechnics for underground structures [19] or extreme climatic influences [20].

Minimization of the consequences of the manifestation of the main risks can be carried out using the Cost Contingency Reserve (CCR) for a project. Post-mitigation simulations show that value of CCR is 2.88% of project cost [21].

2 Methodology of Risk-Management of Construction of Industrial Buildings and Structures

All the described studies were taken into account in the process of risk management of the construction of a dry starch production workshop in the Rostov region.

The decision to open the project: “Construction of a starch drying shop with a capacity of 300 tons/day” was made by the management of Amilco in December 2018 in order to expand the production capacity of the enterprise and further release of new products.

At the same time, the design deadlines were extremely tight. In this regard, there were additional risks of errors in design decisions due to lack of time for detailed study.

In addition, the design of building structures had to be developed taking into account the ready-made scheme of engineering communications and ready-made technological equipment, which also increased the risk of errors in the design of structures (Fig. 1).

Fig. 1
figure 1

Technical specification for design—engineering

When searching for a contractor, another non-obvious risk was revealed: due to the reduction in the pace of construction of industrial buildings in Russia, the number of design organizations specializing in this area has also significantly decreased.

The main requirements for the tender among contractors were: experience in the design and construction of industrial facilities, reliability and high quality of the work performed by the counterparty; minimum project implementation time; optimal price/quality ratio; sociability, mobility and quick response to changes while taking into account the wishes of the customer company with the full implementation of the turnkey project; legal and tax audit of the counterparty.

All the considered phases of the project are included in Table 1.

Table 1 Project phases

Similar assessment methods were used when searching for an organization that conducted pre-project surveys (geological, geodetic, environmental and hydrometeorological).

The process of selecting a general contractor for the construction of the facility was carried out at a time when the design was not yet fully completed, and was based not on estimates, but on the prices of enlarged types of work. A tender with enlarged cost indicators was very risky for concluding a contract, so a decision was made:

  • 1. Selection of a general contractor, with the possibility of involving subcontractors by agreement for the full implementation of the project;

  • 2. On the approval of prices for enlarged types of work (i.e. the estimate is not “solid” because there is no full explication of the project).

3 Result of Approbation of Methodology of Determining of Potential Risks of Construction of Industrial Buildings

In addition to the risks that appeared directly in the specified phases of the project (pre-design, design and construction), there are also hidden risks—those whose implementation is possible only at the next stage.

For the customer, the main criterion for evaluating the effectiveness of decision-making and consequently risk minimization was the earliest possible time for putting the workshop into operation.

The mechanism of the relationship of risks at different cycles of the building’s life is presented in the form of a directed graph (Fig. 2), where the initial vertex is risk, the final vertices differ depending on the impact of risks—M (money) is the risk of financial losses, T (time) is the risk of temporary losses, MT is the combined risk of time and material losses.

Fig. 2
figure 2

Oriented graph of the system “Risks of life cycles of a building under construction”

The risks are grouped depending on which stage of the vital cycle of buildings this risk is laid: the pre-project stage (group RI), the project stage (group RII), the project stage (group RII), the construction and operation stage (group RIII).

The types of risks are indicated in Table 2.

Table 2 Types of risks in the construction of an industrial building

The calendar schedule without taking into account the implementation of risks is shown in Fig. 3.

Fig. 3
figure 3

Calendar schedule without taking into account the implementation of risks

The main stages of construction are shown in Fig. 4.

Fig. 4
figure 4

The main stages of the construction of an industrial workshop

4 Discussion of the Method of Risk Management of Building Construction, Using Oriented Graph

The proposed method of risk management of industrial buildings using the graph theory apparatus is relevant and new in comparison with existing methods. Currently, it is possible to assess the possibility of risk manifestation only on the basis of an expert’s subjective assessment based on his experience. And this experience is associated only with a narrow field of work, and cannot be extended to objects with dissimilar specifics.

During the implementation of this project, several risks were realized at once at different cycles of the building’s life, as a result of which:

  • the design stretched from the planned period of 6 months to a year (with the receipt of a positive expert opinion);

  • the construction period has increased from 10 to 19 months.

5 Conclusion

This hierarchy and risk system, as well as the implementation of a risk interaction mechanism in the form of a network graph, allows us to estimate the most likely production dates for construction and design work at the pre-design stage.

Such an assessment can be possible thanks to probabilistic methods, as well as a simplified version: the introduction of a system of coefficients (by analogy with reliability coefficients) that enable to determine the most probable timing of construction and design work.