Finite element modeling methods of steel-concrete composite structure with overlap slab were investigated. A two-step finite element method was presented. It was applied to analyze an extra long span composite bridge. The conversion of structure system and the mechanical behavior of the bridge were analyzed with two different construction methods. The stresses of steel beams, precast slabs and in-situ-place concrete under the total load were compared. The results show that steel-concrete composite structure with overlap slab has many advantages, the construction method that the top in-situ concrete and the concrete in construction joints are cast respectively is rather reasonable than the one that the top in-situ concrete and the concrete in construction joints are cast at the same time, and the two-step finite element method is affective to such large-scale structures.
Article PDF
Similar content being viewed by others
Avoid common mistakes on your manuscript.
References
LAM D, ELLIOTT K S, NETHERCOT D A. Parametric study on composite steel beams with precast concrete hollow core floor slab[J]. Journal of Constructional Steel Research, 2000, 54(2): 283–304.
LÄÄNE A, LEBET J P. Available rotation capacity of composite bridge plate girders under negative moment and shear [J]. Journal of Constructional Steel Research, 2005, 61(3): 305–327.
YE Mei-xin, HUANG Qiong. Study of steel structure accidents[J]. Journal of the Changsha Railway University, 2002, 20(4): 6–10. (in Chinese)
NAKAMURA S, MOMIYAMA Y, HOSAKA T, et al. New technologies of steel/concrete composite bridges[J]. Journal of Constructional Steel Research, 2002, 58(1): 99–130.
YE Mei-xin, HUANG Qiong. Damage detection of high-speed railway steel-concrete composite beam[J]. Journal of Central South University: Science and Technology, 2005, 36(4): 704–709.(in Chinese)
Brozzetti J. Design development of steel-concrete composite bridges in France[J]. Journal of Constructional Steel Research, 2000, 55(1/3): 229–243.
HAENSEL J. Composite bridge design: The reanimation of steel bridge construction[J]. Journal of Constructional Steel Research, 1998, 46(1/3): 54–55.
SHIM C S, LEE P G, CHANG S P. Design of shear connection in composite steel and concrete bridges with precast decks[J]. Journal of Constructional Steel Research, 2001, 57(3): 203–219.
YE Mei-xin, ZHANG Ye-zhi. Behavior of steel-concrete composite beams under the action of negative moment[J]. China Railway Science, 2001, 22(5): 41–47.(in Chinese)
MARÍ A, MIRAMBELL E, ESTRADA I. Effects of construction process and slab prestressing on the serviceability behaviour of composite bridges[J]. Journal of Constructional Steel Research, 2003, 59(2): 135–163.
RYU H K, CHANG S P. Ultimate strength of continuous composite box-girder bridges with precast decks[J]. Journal of Constructional Steel Research, 2005, 61(3): 329–343.
YE Mei-xin, ZHANG Ye-zhi. Concrete-steel truss composite girder and shear connectors[J]. Journal of the China Railway Society, 1999, 21(1): 67–71.(in Chinese)
LUO Ru-deng, YE Mei-xin. Study calculation of deflection of composite girders under action of negative moments[J]. China Railway Science, 2001, 22(5): 61–64. (in Chinese)
ZHANG Ye-zhi. Analysis on responses of continuous composite beams in high-speed railways[J]. Journal of the China Railway Society, 2002, 24(6): 84–88. (in Chinese)
Author information
Authors and Affiliations
Corresponding author
Additional information
Foundation item: Project(2001G022) supported by the Science and Technology Development Program of Railways Department, China
Rights and permissions
About this article
Cite this article
Ye, Mx., Huang, Q. & Wu, Qq. Analysis of steel-concrete composite structure with overlap slab of Xingguang bridge. J Cent. South Univ. Technol. 14, 120–124 (2007). https://doi.org/10.1007/s11771-007-0024-1
Received:
Accepted:
Issue Date:
DOI: https://doi.org/10.1007/s11771-007-0024-1