Keywords

1 Introduction

According to planning, there will have 4–5 urban railways in Hanoi. The 3rd route starts from Nhon to Hanoi Station. The project with the full length of 12.5 km contains 9.6 km elevated and 2.9 km underground. Correspondingly, there are 11 elevated terminals and 4 underground terminals. Designed length of the train is 19 to 20 m. The speed is 80 km/h.

The 3rd route has connected stations. In which, the 8th terminal is located in front of University of Transport and Communications, includes main bus station with a large traffic volume. During the construction of the foundation pit for piers of the terminal, Larsen IV steel sheet piles combined with ground anchors were proposed to stabilize the pit.

The 8th terminal at the Nhon – Hanoi Station route is deeper and more complex than others due to the configuration of the terminal that requires appropriate construction methods as well as calculations.

Soil anchors have been applied for deep excavations in many projects all over the world (Briaud and Lim 1999; Weatherby 1998). The anchors are often combined with steel sheet piles to strengthen the excavation (Harris and Bond 2008; Weatherby 1998). They are installed to transfer a tension load in bearing strata that can be soil or rock. The specifications for the soil anchor calculations are sufficient such as BS 8081 (1989), AASHTO LRFD 2007 (SI version) or LRFD 2012.

For transportation projects, the AASHTO LRFD is normally applied. However, projects with the anchors in urban transportation in Vietnam are not mentioned, this paper introduces an example for the soil anchor in the urban railway project.

In the project, Geostructure analysis (Geo5 v19) was used to calculate and audit the steel sheet pile structure with the ground anchors. Using Geostructure Analysis software (Bentley-US) allows the calculation in construction stages, taking into account both internal stability and overall stability of the structure. In which, Sheeting check function is suite for making basic design of the required length of the structure, calculating the internal forces or verifying the cross-sections based on traditional analytical methods.

Plaxis 2D was used to compare to Geo 5 program. Plaxis 2D is one of the most powerful tools for geotechnical engineers. It is a finite element program package specifically intended for the analysis of deformation and stability in geotechnical engineering projects. Although the modeling of the soil itself is an important issue, many projects involving the modeling of structures and the interaction between structures and soils would be analyzed in Plaxis 2D.

2 Designation and Instructions

2.1 General on the Project

The main document is technical design documentation of foundation measures for the project “Pilot Urban Railway in Hanoi: Nhon - Hanoi Station Section” by investor: Hanoi People’s Committee - Hanoi Public Transport and Tram Development Management Board.

In order to construct a pillar platform, design consultant uses Larsen piling method around the pit and proceeds to excavate the soil in the foundation pit, finally build the platform. Due to the large depth of excavated soil, the pile wall near the elevated road has stabilized by the soil anchors (Fig. 1).

Fig. 1.
figure 1figure 1

Cross section of the foundation pit at the 8th terminal

At the 8th terminal, both the 12 m-long-steel sheet piles and the 12 m-long anchors are installed. Spacing between the anchors is 2 m.

2.2 Input Parameters

2.2.1 Traffic Load

Load due to vehicles acting on one side of Thu Le park is calculated with a designed truck with an axial load of 145 kN.

The designed truck is shown in Fig. 2 below. The traffic range is 8.5 m, each separated by 1.2 m. In addition, construction load such as excavator and crane load are also considered. All construction and traffic load are calculated and shown in Table 1. From the calculations, we select q = 42.65 kN/m2 for the excavation design (Fig. 3).

Fig. 2.
figure 2figure 2

The designed truck

Table 1. Traffic load
Fig. 3.
figure 3figure 3

The truck layout

2.2.2 Geological Conditions

There are 4 layers in the scope of calculation. The top layer is DD layer including concrete, brick, sand and clay, thickness is 3.97 m; Made ground layer: backfill, silty sand, thickness is 0.8 m; GU1_s layer: lean clay with some organic, firm to stiff, thickness is 6.7 m; GU3&4 layer: Fat and elastic (CH-MH) + Organic matter, thickness is 2 m. Properties of the layers are described in Table 2.

Table 2. Soil properties

2.3 Materials

2.3.1 Larsen IV

Steel type for Larsen IV is CT3, detail properties are as follow (Table 3):

Table 3. Steel sheet pile properties

2.3.2 Anchor

Geometric features of anchor cables: Use 2 cables 15.2 mm (Tables 4 and 5).

Table 4. Anchor ground features
Table 5. Anchor properties

2.3.3 Scopes of the Calculation

  • Checking of the sheet piles L = 12 m in construction stages

  • Checking of the ground anchors

3 Analytical Analyses

Calculate and check the sheet piles L = 12 m and the ground anchors in construction stages by using Geo5:

  • Stage 1 Pressing the sheet pile (L = 12 m). Excavate to ground anchor elevation +8.508 (Fig. 4).

    Fig. 4.
    figure 4figure 4

    Model of foundation pit in Geostructure analyses in stage 1

  • Stage 2 Install the ground anchors (Fig. 5).

    Fig. 5.
    figure 5figure 5

    Model of foundation pit in Geostructure analyses in stage 2

  • Stage 3 Excavate to bored pile elevation +7.245 (Fig. 6).

    Fig. 6.
    figure 6figure 6

    Model of foundation pit in Geostructure analyses in stage 3

  • Stage 4 Excavate to wale and struts elevation. Install wale and struts at elevation +6.986, frame fixed frame support and cofferdam by welded (Fig. 7).

    Fig. 7.
    figure 7figure 7

    Model of foundation pit in Geostructure analyses in stage 4

  • Stage 5 Excavate to bottom blinding concrete elevation +2.953 (Fig. 8).

    Fig. 8.
    figure 8figure 8

    Model of foundation pit in Geostructure analyses in stage 5

4 Numerical Analyses

Numerical analyses were performed to study the lateral movement and forces of the steel sheet piles. Mohr-Coulomb model is used in the analyses in order to simulate the behavior of the soil layers. Figure 9 shows mesh of the excavation domain in the final stage of the construction with the construction load at one side of the excavation pit.

Fig. 9.
figure 9figure 9

Deformed mesh at final stage of the construction

5 Results

5.1 Analyses Results

  • Stage 1 Press sheet piles (L = 12 m). Excavate to the ground anchor elevation +8.508 (Fig. 10).

    Fig. 10.
    figure 10figure 10

    Diaphragm of bending moment, shear force and displacement at stage 1

  • Stage 2 Install the ground anchors (Fig. 11).

    Fig. 11.
    figure 11figure 11

    Diaphragm of bending moment, shear force and displacement at stage 2

  • Stage 3 Excavate to bored pile elevation +7.245 (Fig. 12).

    Fig. 12.
    figure 12figure 12

    Diaphragm of bending moment, shear force and displacement at stage 3

  • Stage 4 Excavate to wale and struts elevation. Install wale and struts at elevation +6.986, frame fixed frame support and cofferdam by welded (Fig. 13).

    Fig. 13.
    figure 13figure 13

    Diaphragm of bending moment, shear force and displacement at stage 4

  • Stage 5 Excavate to bottom blinding concrete elevation +2.953 (Fig. 14).

    Fig. 14.
    figure 14figure 14

    Diaphragm of bending moment, shear force and displacement at stage 5

5.2 Checking for Steel Sheet Pile

Maximum bending moment and shearing force values will be used to check the cross section of the sheet piles (Table 6).

Table 6. Maximum values in the sheet piles

Cross section of piles ensures the bearing capacity. At the same time, the horizontal displacement of the pile is small, meets the allowable displacement of the anchor pile wall.

5.3 Checking for Ground Anchor

The anchor force values during the construction stages analysed in Geo5 and Plaxis are shown in Table 7.

Table 7. Anchor force

The length of the ground anchors L = 12 m, meet the requirements of bearing capacity.

6 Discussions

The procedure for deep foundation design using the steel sheet piles in combination with the ground anchors was presented in detail. Based on the results, the following conclusions can be drawn:

  • The calculated results are quite compatible in Geo5 and Plaxis.

  • The bending moments and shear forces in Plaxis agreed with the calculated results in Geo5 for each construction stage.

  • The displacements at the toe of steel sheet pile tend to be larger and at the head of sheet pile are smaller in Plaxis compare to Geo5.

  • The internal force values in Geo5 are more conservative than in Plaxis.

The differences between analytical and numerical analyses in the lateral movement of the sheet piles and the ground anchors can be explained by the differences of modulus parameters. In details, the moduli used in Geo5 were deformation moduli that were determined by the in-situ tests. Meanwhile, the moduli used in Plaxis were elastic modulus obtained from laboratory tests.

7 Conclusions

Both analytical and numerical analyses can be used successfully in analyses of steel sheet pile for deep excavation. The results of those analyses show good agreement in the internal forces of the piles for stages of construction.

Analytical analysis with the sheeting check function can be easily used with in-situ tests. Meanwhile, numerical analysis with sophisticated boundary conditions should be used in routine design and construction of steel sheet pile excavation.

This paper summarized the results of calculating internal force and displacement of steel sheet pile in stages and the method of anchored auditing in the soil applied to deep foundation in urban works.