Abstract
Despite possibly higher initial costs, owners and construction management organizations have demonstrated a growing interest in implementing practices that result in improved quality and fewer risks, disputes, and waste on their projects in recent years. Therefore, to solve this problem, a new method that has been considered for design and construction is lean analysis and construction. If this design is aligned with new technologies such as building information modeling (BIM), there will be a huge change in the success of projects. Integrated and synergistic integration of the two phenomena of lean construction (LC) and BIM can reduce errors and losses. The main purpose of the present study is to determine effective parameters of the synergy of LC technique and BIM system and identifying and evaluating the most important application and infrastructure required to apply an integrated model of application of these techniques in construction projects in the country. The data were examined utilizing the combined approach of FAHP and FTOPSIS after determining the relevant capabilities of BIM and LC functions. The results showed that among the identified BIM capabilities, the ability to integrate the database with a weight of 0.201 ranks first, and the standardization function in LC with a similarity index of 0.547 is also the optimal solution. Also, the results showed that based on the similarity index (CCi) illustration of the process of how to form a plan status plan at any time, “The closest solution to the function of teamwork culture, the ability to” assess compliance with the initial objectives of the plan “The closest solution to the function of continuous improvement/construction based on quality and capability” Fast construction and Time and cost optimization “The closest solution to the function of continuous improvement/construction based on quality and capability” Energy consumption “The closest solution to the function of waste and the ability to” Build and control computer scheduling and project budgeting “The closest solution to the function of waste be.”
Similar content being viewed by others
Explore related subjects
Discover the latest articles, news and stories from top researchers in related subjects.Avoid common mistakes on your manuscript.
1 Introduction
In the last three decades, major progress has been achieved in the efficiency and effectiveness of the world manufacturing industry which has now minimized all work components (production space, manpower, production time, investment, and costs); in these industries, significant progress is seen in all productivity indicators compared and compared with classic models (Safa and Kachitvichyanukul 2019; Xu et al. 2022; Lu et al. 2022; Zhang et al. 2021). All these progress to increase productivity in production are not based on fundamental changes or the rapid growth of technology but are the result of the application of new production philosophies that lead to lean production and thinking. Based on this thinking, efforts are made to minimize (Muda) waste in the field of production and reduce the time of processing and operation of the product, thus increasing the added value of production and, at the same time, activities that have no added value. They are removed from the process (Alarcón 1997; Rouhanifar et al. 2021). The fundamental concept of lean thinking lies in eradicating the organization’s loss and value creation (Safa et al. 2020; Rouhanifar and Afrazi 2019; Afrazi et al. 2018). Lean thinking is an attitude to increase continuous productivity and value creation and minimize costs and losses. In this way, the gateway to the land of values can be considered for the customer to eliminate obvious defects, losses, and errors through quick methods, such as concepts and techniques of lean thinking. It is very difficult for design and supervising engineers to balance optimal design and low cost and waste; therefore, to solve this problem, a new method considered for design and construction is the analysis and lean construction. This design has been considered by many researchers and industry owners in recent years (Nazari and Soleimani Ashtiani 2013; Hosseini 2017). If this design is aligned with new technologies such as BIM, there will be a huge change in the success of projects (Aksamija 2010; Luo et al. 2019). The building information modeling (BIM) system is highly efficient in solving problems such as many changes in different stages of construction and lack of integration in project parts, and time and cost management and rework. As a powerful tool, it can be attention that will lead to continuous improvement in the process of design and construction of construction projects. Building information modeling can be defined according to the BIM handbook as follows: “A concept for describing instrumentations, processes, and technologies facilitated by computer science to display a view of building information, performance, planning, construction and finally operation (Eastman et al. 2011; Afrazi et al. 2022; Afrazi and Yazdani 2021; Jahandari et al. 2022; Fan et al. 2020).
In terms of cost and schedule performance indicators, Nguyen and Akhavian (2019) analyzed the efficiency of and synergy between three such trending concepts in the construction sector, namely integrated project delivery (IPD), lean principles, and building information modeling (BIM) (Nguyen and Akhavian 2019). According to Zahraee's (2016) findings, major practices in lean manufacturing in Iranian manufacturing plants include processes and equipment, planning and control, supplier relationships, human resources, and customer interactions. Lean tools such as Kaizen, 5S, setup time reduction, cellular manufacturing, continuous flow, equipment layout, product design simplicity, and error proof equipment are also critical to lean manufacturing deployment, according to the findings of this survey. In another research, Heravi et al. (2020) studied installation of pre-fabricated steel frames (PSFs) of residential buildings. Their results showed that annual energy consumption and CO2 emissions were reduced by 9.2% and 4.4%, respectively. The impacts of adopting value stream mapping (VSM), just in time (JIT), continuous flow, and total productive maintenance (TPM) approaches throughout the manufacture and erection processes of pre-fabricated steel frames (PSFs) of construction projects were explored by Heravi et al. (2019). According to a study conducted by Amany et al. (2020), using the BIM approach in the planning phase reduces time conflicts between expert contractors on the critical path, and the overall delay of the scheduled time achieves zero. Furthermore, confrontations among contractors, whose suspension will provide no motivation and result in daily cost overruns, will be at an all-time low (Amany et al. 2020).
In order to evaluate and identify the most essential applications, capabilities, and infrastructure needed to use the integrated model, this paper attempts for the first time to verify the effective parameters of the synergy between lean construction technique (LC) and building information modeling system (BIM). It has also been thought of applying these techniques to various building projects around the country. By first defining the capabilities of the building information modeling system and the LC functions in infrastructure projects, a coherent framework for problem resolution was first proposed for this purpose. Then, the application of the suggested method to prioritize the capabilities of the building information modeling system was identified, and the impact of the most crucial BIM capabilities on LC functions was investigated, using integrated fuzzy multi-criteria decision-making methods by combining FAHP and FTopsis methods. It was closely looked at and scrutinized.
2 Theoretical Foundations
2.1 Lean Thinking
The fundamental concept of lean thinking lies in eradicating the organization’s loss and creation of value. Lean thinking is an attitude to increase productivity and continuous value creation and minimize costs and losses in project-based projects and organizations (Baradaran et al. 2015). This thinking provides a way to achieve maximum efficiency with fewer resources, equipment, time, and space and to approach them according to the customer’s needs and, at the same time, meet the needs of customers (Tavassoli and Mortahab 2008). The philosophy of this approach is production, generalization to a series of sub-sectors such as JIT-time production methods, total quality management (TQM), six standard deviations, and the like. In 2000, the US Department of Commerce’s National Standards Institute defined lean manufacturing as follows: “Lean manufacturing is a systematic approach that seeks to identify and eliminate waste (non-value-added activities) through continuous improvement and streamlining.” “Proper production is when the customer needs it.” In other words, lean thinking is about focusing on waste disposal, increasing customer value, and streamlining processes (Olson 2003; Pour et al. 2022).
Lean thinking consists of five general guiding principles and how to apply them that lead any company or organization to create a stable and dynamic system that can be fully applied by understanding these principles and then trying to tie them together. Lean methods and techniques achieved a sustainable solution in the purification of the organization and its processes. By understanding these principles carefully and then trying to link them together, managers will be able to fully use lean methods and techniques to achieve a sustainable approach (Jørgensen and Emmitt 2009). These five principles are shown in Fig. 1 (Ohno 1988).
The starting point of lean thinking is the determination of value, which is defined by the end consumer in the context of a given product. Value flow refers to a set of steps of a process (with or without value-added) that starts from the neighborhood of receiving raw materials and continues until the product is completed and delivered to the customer in construction projects (employer) (Razavian et al. 2020; Armaghani et al. 2020). The third principle of lean thinking involves constantly moving for value-creating steps. The fourth principle enables the customer to extract the defined value from the manufacturer (Majedi et al. 2021, 2020). The fifth principle (pursuit of perfection) of lean thinking insists on continuous improvement and believes that to achieve the basic foundations of lean thinking must be the excellence and perfection of all four dimensions. The principle of this type of thinking is value, value flow, value flow movement, and considering increasing customer attraction and continuously changing and improving values by taking into account changes in the demands of consumers and users of value.
2.2 Lean Construction (LC)
The idea and philosophy of lean construction were first applied by Koskela in 1992, considering production methods in the construction industry (Koskela 2000). Lean construction is an attitude and style of construction that has brought many changes to the construction industry; in fact, using the concepts and principles of lean thinking to design the production system in the construction industry with the aim of increasing productivity, minimizing material waste, time and energy spent to produce the maximum possible value, reducing construction time and controlling project cost construction. This thinking is called lean because by identifying and eliminating waste. It can provide a way through which it is possible to perform the maximum operational volume of the project with the least resources (Salem et al. 2006; Afrazi et al. 2017; Safa et al. 2016; Toghroli et al. 2014; Gu et al. 2022). Designing such a production system achieves the goals. The mentioned is impossible except with the cooperation of all the people involved in the project (employer, contractor, managers, final beneficiaries) from the beginning of the project. This is more than just a contractual obligation. Refinement of construction complements traditional construction management by two basic criteria for the success of large projects: (1) the flow of materials, information, value generation in the production system, and (2) the use of different project management patterns and production, in planning, execution, and control. The basic features of lean construction include a clear set of objectives, maximizing project performance for the client at the project level and simultaneous construction design, and the use of optimal and optimal project control over the life of the project from design to delivery. Construction refinement complements traditional construction management by applying the key criteria necessary for the successful completion of large projects, considering and paying attention to the flow of materials and information and the production of value in the production system and various patterns of project and production management (in planning, execution, and control) is Arayici et al. (2011). Looking at the lean construction process, this attitude, the process of planning, engineering, design, construction, production, and delivery of materials (projects) in better compliance with the objectives of project management in transferring maximum value to project owners (Abdelhamid et al. 2008; Afshar et al. 2020; Naghipour et al. 2020). In 2008, the Lean Construction Institute listed the ten key elements shown in Fig. 2 for lean construction.
2.3 Building Information Modeling System (BIM)
Building Information Modeling (BIM) describes tools, processes, and technologies that facilitate building, performance, planning, construction, and operations using digital facilities and readable documents (Eastman et al. 2011). The BIM system is an example of the latest 3D or multidimensional models to simulate the planning, design, construction, and operation of construction projects that help architects and engineers design and build what is to be designed and built. They must first build completely in a virtual environment and overcome those problems if they encounter possible problems at any stage of construction, such as design, implementation or operation (Sacks et al. 2009; Shariati et al. 2019; Davoodnabi et al. 2021).
The BIM system adds three- or two-dimensional modeling components with unique features to two-dimensional maps and related specifications. Its special feature is that each member designed in BIM, in addition to its multidimensional physical nature, has an array of information related to the various activities and tasks of designers and managers (Aksamija 2010; Shariati et al. 2020a). This information relates to the project’s entire life cycle from its initial stages to its completion. It includes items such as the feasibility study stage to the conceptual design, the first- and second-stage studies, procurement, construction, installation and commissioning, operation period, and even the end. In short, BIM is the process of producing and managing building information throughout its life cycle (Kymmel 2008). In addition to creating intelligent connections between different design components, a BIM model allows the study of different design scenarios for all groups virtually (Aksamija et al. 2011). In addition, other design groups, including structural and facility design, are able to see the effects of these scenarios on project productivity by making changes to their model. Finally, contractors are able to design sequences such as execution sequences while designing and developing the building model—experience performance, construction, and installation virtually (Aksamija et al. 2011). The BIM system ensures continuous improvement in design and production and ensures integration in the construction industry by ensuring the transfer of communication from designers to builders (Eastman et al. 2011; Shariati et al. 2021; Tavakkoli et al. 2022).
Design in the construction industry based on the BIM system is one of the best types of building modeling to achieve the issues and topics in sustainable design, which is increasing every day around the world. This modeling is able to present new horizons such as increasing productivity, reducing operating time, and reducing the costs of the full life cycle of a building through optimization methods for the construction industry (Gu and London 2010).
3 BIM and Lean Interaction
Integrated and synergistic integration of two phenomena of lean construction (LC) and building information modeling (BIM) by reducing errors and losses can have a significant impact on increasing productivity in different phases of the project (Oskouie et al. 2012). Image analysis of LC and BIM systems reveals significant similarities between these two phenomena, which provide the interaction between these two loops, facilities management from the design phase to project delivery (Dave et al. 2011). So far, limited research has been conducted to investigate the extent of interaction between lean fabrication and the BIM system. A review of this research shows that there are positive interactions between LC and BIM techniques, and some of these interactions have been identified. This research can be done to analyze the interaction between LC and BIM at the conceptual level, and the study of the synergy of these two technologies by Sacks et al. (2009, 2010) pointed out. Based on their studies on the detailed analysis of the interactions between BIM and Lean, these researchers have concluded that there is a kind of alignment between the two techniques that, if properly understood, can improve construction processes. They showed that the use of the BIM system reduces changes in the construction industry (Kymmel 2008) in research such as Hamdi and Leite (2012), Lu et al. (2012), and Gerber et al. (2010). In addition to examining case studies of the simultaneous use of the concept of Lean and BIM in real construction projects, the existence of synergistic contexts and positive results of combining these two concepts has been pointed out (Nasrollahi 2018; Gerber et al. 2012; Liu et al. 2011; Hamdi and Leite 2012). In their research, Clemente and Cachadinha examined and evaluated the synergy of BIM and Lean techniques in public construction projects. The results of this study showed that in addition to significantly reducing the activities and duration of value-added activities, the implementation of this approach provides a correlation of the interests of all stakeholders in line with a common goal to meet the overall project plan (Clemente and Cachadinha 2013). Based on their studies, Nazari and Soleimani Ashtiani (2013) have proposed a model for the interaction between BIM and LC. The researchers examined the principles of lean thinking based on research by Koskela (2000), Sacks et al. (2009), Oskouie et al. (2012), as well as the capabilities of the BIM system based on research by Eastman et al. (2011) and Sacks et al. (2009). The structure of the interaction of these two concepts is presented according to Fig. 3. In their study, Yongge and Cheng analyzed the applications of the combined method of BIM technology and the concept of lean construction for cost management and value control throughout the life cycle of construction projects (Xu and Qian 2013). In a 2014 paper by Ahuja et al. (2014), how BIM is effective in creating lean construction is shown in Fig. 4. Based on their studies, Bortolotti et al. (2016) have proposed the reduction of repairability and waste to increase construction performance and reliability of the workforce as one of the principles of lean construction and analysis. In their research, the use of BIM and Lean for the requirements of modeling in the design of sanitary construction projects is examined. The purpose of this study is to understand how to model user needs to support decision-making in the design process (Junior et al. 2018). In their research, Carvajal-Arango et al. (2019) examined the relationship between lean construction and sustainable development and evaluated the positive effects of lean practices on sustainability in the construction phase. The results of this study showed that increasing productivity, reducing waste, and reducing cost and time will have the greatest impact on the purification of construction projects (Hamidian et al. 2011).
4 Research Method
The present study, while identifying and evaluating important capabilities in the field of using lean construction (LC) and building information modeling technology (BIM) in construction projects in Iran, provides a model to determine the effect of these two techniques (Shariati et al. 2020b; Zandi et al. 2018). To be, the research method is a quantitative survey that after identifying the capabilities of the BIM technique and LC functions based on a hierarchical combination of fuzzy multi-criteria decision-making method and TOPSIS data are analyzed. The questionnaires in this section are based on pairwise comparisons for analysis with fuzzy hierarchical multi-criteria decision-making methods. For this purpose, after determining the weight of the identified capabilities in relation to BIM by the FAHP method, they are prioritized, and the preferred capabilities in the main functions of LC are determined by the FTOPSIS method. For this purpose, five experts specializing in BIM and LC and working in Iranian construction companies were asked to investigate pairwise comparisons. After extracting pairwise comparisons, the analysis of fuzzy multi-criteria decision-making methods with coding in MATLAB software was used to provide prioritization models based on FAHP and FTOPSIS methods. Tables 1 and 2 show the BIM capabilities and the main functions of LC (research variables), respectively. Codes have been assigned to them to facilitate future steps (Fig. 5).
4.1 Introduction of Fuzzy Hierarchical Analysis (FAHP)
The fuzzy AHP (FAHP) method takes into account the uncertainties and incorrect judgments of experts using linguistic variables or fuzzy numbers (Sedghi et al. 2018; Kordestani et al. 2021; Zhen et al 2022). The fuzzy numbers used in fuzzy decision research are mostly triangular or fuzzy trapezoids. In the first step of the FAHP method, the hierarchy structure of the decision problem is formed using the target levels, criteria, subcriteria, and options. Experts’ views on the importance of the identified factors are then compared using linguistic variables in pairs. To express the importance of each factor, different language variables can be used in the very low to very high range (according to the 9-point range presented in Table 3). The fuzzy membership function for language variables is shown as fuzzy triangular numbers in Fig. 6. Then, the matrix of pairwise comparisons is formed according to Eq. 1 (Patil and Kant 2014).
In the next step, using the geometric averaging method, the fuzzy mean weights of each criterion are determined.
The value of the fuzzy compound expansion for each target relative to the ith index is determined according to Eq. 2:
By performing a fuzzy addition operation on the expansion m:
Degree of preference (degree of feasibility) S2 = (l2, m2, u2) ≥ S1 = (l1, m1, u1) which S1, S2 are obtained according to Eq. 5 is calculated according to Equation
The above equation can be expressed synonymously with Eq. 6:
In Eq. 7, d is the coordinate of the highest point in the interface and collision of the two membership functions, S1µ and S1µ. To compare S1 and S2, it is necessary to calculate both V (S2 ≥ S1) and V (S1 ≥ S2). The degree of the feasibility of a convex fuzzy number (S) is separated from k by another convex fuzzy number (Si; i = 1, 2,…, k) as follows:
Continued vector weights \(W^{\prime}\) are obtained according to Eq. 8:
The vector elements are the calculated definite (non-fuzzy) weight.
Assuming
Finally, the normalized weight vector or the priority vector (W) is obtained according to Eq. 10
The weights of the vector W are the definite (non-fuzzy) relative weights calculated for the comparison matrix.
By repeating this process, the weights of all matrices are obtained. In the last step, by combining the weights of criteria and subcriteria according to Eq. 11, the final weights are obtained.
In this method, the consistency ratio (CR) is calculated, which is a tool that determines the consistency of the initial comparisons obtained from the opinions of experts and shows the extent to which the priorities obtained from the comparisons can be trusted (Deng 1999). Refer to Gogus and Boucher (1998) for details on the relationships and steps to calculate the adjustment rate.
The consistency index (CI) for each matrix is calculated using Eq. 12:
Finally, the CR compatibility rate for each matrix is determined according to Eq. 13. The amount of incompatibility should not exceed 0.1.
4.2 Fuzzy TOPSIS Technique (FTOPSIS)
The TOPSIS method is one of the classic multi-criteria decision-making methods developed by Huang and Yoon. According to this technique, the best option should have the closest distance from the positive ideal solution (PIS) and the farthest distance from the negative ideal solution (NIS) (Shariati et al. 2013). PIS is the answer that has the most profit and the least loss, and NIS is the answer that has the lowest profit and the most cost (Lima Silva and Almeida Filho 2020; Rezamand et al. 2021). In the first step of this method, language variables are used by decision-makers to determine the weight of criteria (n existing criteria C = {C1, C2,…, Cn}) and ranking of options (m possible option A = {A1, A2,…, Am}) determined. For this purpose, the language variables presented in Table 4 and the fuzzy spectrum of 6 options are used. The weights of the criteria are denoted by wj (j = 1, 2,…, n) (Shariati et al. 2022). Then, the weight of the criteria and the ranking of the options are determined according to the opinions of the decision-maker according to Eqs. 14 and 15, respectively (Hwang and Yoon 1981):
Next, according to the number of criteria and options, the fuzzy decision matrix is formed according to Eqs. 16 and 17:
The fuzzy decision matrix (\(\tilde{R}\)) for the options is then normalized using linear scale transformation according to Eq. 18:
Then, the weighted normalized matrix decision matrix (\(\tilde{V}\)) by multiplying the coefficient of importance of the criteria (\(\tilde{w}_{j}\)) normalized fuzzy decision in matrix elements (\(\tilde{r}_{ij}\)) is calculated according to Eq. 21:
where \(\tilde{v}_{ij}\) is obtained according to Eq. 22:
For criteria with positive and negative aspects:
In the next step, the ideal fuzzy positive solution(FPIS,A+) and the ideal fuzzy negative solution (FNIS, A−) are calculated according to Eq. 24:
where \(\tilde{v}_{i}^{ + }\), \(\tilde{v}_{i}^{ - }\) respectively, are the best and worst value of criterion i among all the options and are determined according to Eqs. 25:
The options in A+ and A− indicate completely better and completely worse options, respectively. In other words, for positive (profit) indices, the positive ideal is considered to be the largest value of A+, and the negative ideal is considered to be the smallest value of A−. The sum of the distances of the alternatives from the positive and negative ideal fuzzy solutions (FPIS, A+and FNIS, A−) is calculated according to Eq. 26:
In this equation, Si+ and Si− are the sum of the distances of the options from the positive ideal solution and \(d_{v} \left( {\tilde{v}_{ij} ,\tilde{v}_{j}^{ + } } \right)\), \(d_{v} \left( {\tilde{v}_{ij} ,\tilde{v}_{j}^{ - } } \right)\) the negative ideal solution, respectively. Also, dv(.,.) is the distance of each option from the ideal solutions are positive and negative, respectively. dv (.,.) represents the distance between two fuzzy numbers. For two TFNs (M1 (a1, b1, c1) and M2 (a2, b2, c2)), the distance between the two numbers is equal to:
The relative similarity or relative proximity index for option i (CCi) is then calculated according to Eq. 28:
Finally, according to the similarity index, the options are ranked in descending order. So that options with more similarity index are prioritized. In other words, the best (optimal) option is the one that has the shortest distance with FPIS and the farthest distance with FNIS.
5 Application of the Proposed Framework
The proposed framework is used to evaluate the effect of BIM capabilities on LC functions in construction projects (Arabnejad Khanouki et al. 2011; Afrazi and Dehghani 2014). The decision hierarchy was formed based on the parameters presented in Tables 1 and 2, along with the symbols assigned to each factor (for ease of data analysis), as shown in Fig. 7. There are four levels in the decision-making structure of the present study. The overall goal of the decision-making process, entitled “Investigating the Impact of BIM Capabilities on LC Main Functions in Construction Projects,” is at the first level of the hierarchy. The main factors of BIM capabilities are in the second level, the secondary factors of BIM capabilities are in the third level, and the main functions of LC are in the fourth level of the hierarchy.
5.1 Data Analysis by FAHP Method and Determining the Weight of Main and Sub-Factors (Capabilities)
At this stage, the experts were asked to answer the questionnaire using the language expressions of the FAHP method, to compare a pair of seven main features of BIM and 30 sub-factors related to each of the main factors. After collecting the initial importance (weighting) determined by the experts, the arithmetic mean of these values was calculated to obtain a matrix of two-by-two comparison of the main factors and sub-factors. Arithmetic means matrices of pairwise comparisons are presented.
After obtaining the data in the form of average fuzzy pairwise comparison matrices, the values of the value of the fuzzy compound value (Si), the amount of normalized and normalized weight for each of the mentioned matrices were determined, the results of which are presented in Tables 5, 6, 7, 8, 9, 10, 11 and 12. The normalized weight is considered equal to the final weight and is considered the basis for ranking the capabilities in order to identify and prioritize the preferred items. The results for the final weight of each of the main and sub-capabilities of BIM are presented in descending order in Figs. 8 and 9, respectively (Tables 13, 14).
According to the weight of the main factors in Fig. 8, the ability to integrate the database with a weight of 0.201 is in the first rank. The ability to “use the data model to optimize the design” with a weight of 0.185 has the second rank, and the ability “to schedule and budget along with the sequence of construction operations” with the weight of 0.174 are in the third rank.
The diagrams in Fig. 9 show the weight of the sub-factors of each of the main capabilities. Among the capabilities of design visualization and visualization (P1), according to weighted numerical results, the ability to “visualize the process of how to design a design status plan at any time” P1-3 with a weight of 0.143 first place and the ability to “multidimensional visualization of planning construction” with a weight of 0.124 are in second place. According to Fig. 9(P2), among the capabilities of the scheduling and budgeting program, along with the sequence of construction operations, the capability of “construction and computer control of project scheduling and budgeting” (P2-4) with a weight of 0.272, the ability to “review the construction process” and design assistance (P2-2) with a weight of 0.262 have won second place. According to the results presented in Fig. 9(P3), among the capabilities of using the data model to optimize the design, the ability to “estimate the cost and execution time of processes automatically” (P3-2) with a weight of 0.21, the first rank, capability “Assessment of compliance with the initial objectives of the project” (P3-7) with a weight of 0.195 are ranked second (Shariati et al. 2021a; Nowroozi et al. 2021). According to Fig. 9(P4), among the capabilities of joint cooperation and coordination between systems, the ability of “coordination in design and construction” (P4-1) with a weight of 0.182, the ability to “exchange design decisions with team members” (P4- 4) with a weight of 0.163 are in second place. According to the results presented in Fig. 9 (P5), among the database integration capabilities, the ability to “maintain information and integrated model design” (P5-1) with a weight of 0.26 ranks first, the ability to “integrate with the project partner through Database” (Supply Chain) (P5-3) with a weight of 0.163 are ranked second. According to the results of the diagram (9-P6), among the capabilities of buildability and detection of interferences, the ability of “rapid construction and optimization of time and cost” (P6-1) with a weight of 0.23, the ability to “accurately simulate processes in different phases Made” (P6-4) with a weight of 0.219 ranks. According to Fig. 9 (P7), among the capabilities of sustainable design and construction, the ability of “energy consumption” (P7-1) with a weight of 0.28 has gained the first rank.
Table 18 (in the “Appendix”) presents the final results including the relative weights of the main factors and sub-factors of BIM capabilities and the results of the adjustment rate of the comparisons related to the factors as well as the final ranking obtained for the factors based on the final weight. According to the results, it can be seen that the compatibility value (CR) of all matrices is less than 0.1, so all matrices of pairwise comparisons were compatible.
After evaluating and prioritizing the BIM capabilities with the FAHP method, the preferred capabilities have been identified. For this purpose, following the Pareto principle, which states that typically 80% of problems are caused by 20% of causes (Kaplow 2005), action has been taken to determine the preferred capabilities. The purpose of this step was to find the most important BIM capabilities to examine their effect on the main functions of the LC and to facilitate the presentation of suggestions and solutions in a more desirable way. Using this mechanism and based on the comparison of the final weight results for BIM capabilities, a total of the following eight capabilities were selected:
-
Illustration of the process of how the design status plan is formed at any given time (P1-3),
-
Construction and computer control of project scheduling and budgeting (P2-4),
-
Estimation of costs and process execution time automatically (P3-2),
-
Assessment of compliance with the initial objectives of the project (P3-7)
-
Coordination in design and construction (P4-1),
-
Information retention and integrated model design (P5-1),
-
Fast construction and time and cost optimization (P6-1)
-
Energy consumption (P7-1).
5.2 Analysis of the Effect of the Most Important BIM Capabilities on the Performance of LC Functions by FTopsis Method
After determining the ranking of BIM capabilities with a greater degree of importance in construction projects using the FAHP method in the previous section, this part of the data analysis to evaluate the rank of the main functions of LC (Table 2) to determine the effect of BIM capabilities on them and the most important function was discussed (Shariati et al. 2021b, c; Jahandari et al. 2021). For this purpose, the experts were asked to evaluate the importance and intensity of the effect of BIM capabilities of the main LC functions on BIM capabilities in comparison with each other, using the linguistic variables corresponding to the FTopsis method. Then, using the table, the verbal expressions were converted into corresponding fuzzy numbers, and the fuzzy decision evaluation matrices (Table 18) were collected to examine the intensity of the effect of BIM capabilities and LC functions. Next, normalized fuzzy decision matrices were compared to compare LC functions in terms of the ultimately preferred sub-capabilities extracted (not provided in the paper due to the limited number of pages). Weighted normalized fuzzy decision matrices were also obtained to compare LC functions in terms of final sub-capabilities extracted according to Table 19 (in the “Appendix”). Next, the distance from the positive, positive fuzzy solution (di +) was calculated for all BIM capabilities. Given that in the present study, all the identified claims are considered as criteria of capability and capability; therefore, the ideal fuzzy positive solution (FPIS, A *) and the fuzzy negative ideal solution (FPIS, A-) for all the preferred cases identified as v * = (0,0,0) and v- = (1,1,1). Then, the distance (.,.) Dv of each criterion from FPIS, A * and FPIS, A- is calculated, the results of which are presented in Table 20 (in the “Appendix”). Accordingly, the relevant calculations were performed to determine the distance parameters of each of the BIM capabilities from the ideal (di+) and anti-fuzzy (di−) solution extracted from the previous step, and the final results were determined according to Tables 15 and 16, respectively. Based on the values of the similarity index (CCi) obtained in Table 17, the ranking of the options is determined in descending order, to understand better, the results are shown in Fig. 10.
According to Table 16, the ability to “visualize the process of how the design status plan is formed at any given time” (P1-3) is the closest solution to the function of a teamwork culture (S1). With the initial objectives of the project “(P3-7), the closest solution to the function of continuous improvement/build based on quality (S2) and the ability of” rapid construction and optimization of time and cost “(P6-1) is the closest solution to the function of continuous improvement / Quality-based construction (S3) and “energy consumption” capability (P7-1) the closest solution to the operation of waste (S4) and the ability to “build and control computer scheduling and project budgeting” (P2-4) the closest solution to operation losses (S5).
According to the final results (Table 17) of the ranking of LC functions, if the BIM capabilities are used simultaneously in the construction project, the standardization function will perform better and will be ranked 1, similar to the solution.
6 Conclusion
This study evaluated the simultaneous role of building information modeling system (BIM) and lean construction capabilities in projects using multi-criteria fuzzy multi-criteria decision-making methods. The results showed that among the main capabilities of BIM, the ability to integrate the database with a weight of 0.201 first place, the ability to use the data model to optimize the design with a weight of 0.185-s place, the ability to schedule and budget along with the sequence of construction operations with weight 0.174 ranks third. Among the capabilities of design visualization and visualization, the ability to “visualize the process of how to form the design status plan in any moment” with a weight of 0.143 ranked first and among the capabilities of the schedule and budgeting along with the sequence of construction operations, the ability to “build And computer control of project scheduling and budgeting” with a weight of 0.272 ranked first, and among the capabilities of using the data model to optimize the design, the capability of “estimating costs and time to run processes automatically” with a weight of 0.21 ranked first, capability “Assessment of compliance with the initial objectives of the project” with a weight of 0.195, second among the capabilities of joint cooperation and coordination between systems, the ability of “coordination in design and construction” with a weight of 0.182, and among the capabilities of database integration, ability to “maintain information and integrated design of the model” with a weight of 0.26 first place, and among the capabilities of buildability and detection of interference, the ability of “rapid construction and optimization of time and cost” with a weight of 0.23 first place, and among design capabilities and sustainable construction has gained the ability of “energy consumption” (P7-1) with a weight of 0.28 first place. After evaluating and prioritizing the BIM capabilities with the FAHP method, the preferred capabilities have been identified. The results of the study of the effect of BIM capabilities on LC operation and their user synchronization with the FTOPSIS method in the studied infrastructure projects and according to the ranking based on the similarity index (CCi), it was determined that the Status of the project at any time “The closest solution to the function of teamwork culture, the ability to” assess compliance with the initial objectives of the plan “The closest solution to the function of continuous improvement/construction based on quality and the ability to” Build fast and optimize time and cost “The solution to the function of continuous improvement/construction based on the quality and capability of “energy consumption” is the closest solution to the function of waste and the capability of “computer construction and control of project scheduling and budgeting” is the closest solution to the function of waste. With simultaneous application of BIM capabilities and lean construction in the construction project, the standardization function is better and ranked 1, similar to the solution. Further research needs to examine more closely the links between building information modeling system (BIM) and lean construction performance in construction projects.
References
Abdelhamid TS, El-Gafy M, Salem O (2008) Lean construction: fundamentals and principles. Am Prof Constr J 4:8–19
Afrazi M, Lin Q, Fakhimi A (2022) Physical and numerical evaluation of mode II fracture of quasi-brittle materials. Int J Civ Eng. https://doi.org/10.1007/s40999-022-00718-z
Afrazi M, Yazdani M (2021) Determination of the effect of soil particle size distribution on the shear behavior of sand. J Adv Eng Comput 5:125. https://doi.org/10.25073/jaec.202152.331
Afrazi M, Yazdani M, Fakhimi A (2017) The numerical study of effect of an oversize particle on the shear strength of sand in Triaxial test. In: 4th international conference on recent innovations in civil engineering, architecture, and urban palnning, pp 1–14
Afrazi M, Yazdani M, Fakhimi A, Alitalesh M (2018) Numerical analysis of effective parameters in direct shear test by hybrid discrete–finite element method. Modares Civil Eng J 18(3):13–24
Afrazi M, Dehghani, M (2014) Choosing the best route variants base on Environmental parameters by means of remote sensing and GIS. In: 3rd International conference on recent advances in, railway engineering, pp. 1–15
Afshar A, Jahandari S, Rasekh H, Shariati M, Afshar A, Shokrgozar A (2020) Corrosion resistance evaluation of rebars with various primers and coatings in concrete modified with different additives. Construction and Building Materials 262:120034
Ahuja R, Sawhney A, Arif M (2014) BIM based conceptual framework for lean and green integration. In: Sustainability, green and lean, proceedings IGLC-22, Oslo, Norway
Aksamija A (2010) Analysis and computation: sustainable design in practice. Des Princ Pract Int J Annu Rev 4:291–314. https://doi.org/10.18848/1833-1874/CGP/v04i04/37919
Aksamija A, Guttman M, Rangarajan H, Meador T (2011) Parametric control of BIM elements for sustainable design in revit: linking design and analytical software applications through customization. J Res 3:32–45
Alarcón L (1997) Lean construction. Balkema Publishers, Rotterdam
Amany A, Taghizade K, Noorzai E (2020) Investigating conflicts of expert contractors using the last planner system in building information modeling process. J Eng Des Technol 18:1381–1402. https://doi.org/10.1108/JEDT-09-2019-0223
Arabnejad Khanouki MM, Ramli Sulong NH, Shariati M (2011) Behavior of through beam connections composed of CFSST columns and steel beams by finite element studying. In Advanced Materials Research 168:2329–2333
Arayici Y, Coates P, Koskela L et al (2011) Technology adoption in the BIM implementation for lean architectural practice. Autom Constr 20:189–195. https://doi.org/10.1016/j.autcon.2010.09.016
Armaghani DJ, Mirzaei F, Shariati M, Trung NT, Shariati M, Trnavac D (2020) Hybrid ANN-based techniques in predicting cohesion of sandy-soil combined with fiber. Geomech Eng 20(3):191–205
Baradaran S, Daraei M, Fatahi D (2015) Examining the readiness of Iran Transfo Rey Co., for performing the lean production system. Ind Manag J 7:15. https://doi.org/10.22059/imj.2015.53195
Bortolotti T, Romano P, Martínez-Jurado PJ, Moyano-Fuentes J (2016) Towards a theory for lean implementation in supply networks. Int J Prod Econ 175:182–196. https://doi.org/10.1016/j.ijpe.2016.02.020
Carvajal-Arango D, Bahamón-Jaramillo S, Aristizábal-Monsalve P et al (2019) Relationships between lean and sustainable construction: positive impacts of lean practices over sustainability during construction phase. J Clean Prod 234:1322–1337. https://doi.org/10.1016/j.jclepro.2019.05.216
Clemente J, Cachadinha N (2013) BIM-lean synergies in the management on MEP works in public facilities of intensive use—a case study. In: IGLC-21, 21th conference of international group for lean construction, Fortaleza, Brazil, pp 751–760
Dave B, Boddy S, Koskela L (2011) Visilean: designing a production management system with lean and BIM
Davoodnabi SM, Mirhosseini SM, Shariati M (2021) Analyzing shear strength of steel-concrete composite beam with angle connectors at elevated temperature using finite element method. Steel Compos Struct 40(6):853–868
Deng H (1999) Multicriteria analysis with fuzzy pairwise comparison. Int J Approx Reason 21:215–231. https://doi.org/10.1016/S0888-613X(99)00025-0
Eastman C, Teicholz P, Sacks R, Liston K (2011) BIM handbook: a guide to building information modeling for owners, managers, designers, engineers and contractors. Wiley, New York
Fan X, Wei G, Lin X, Wang X, Si Z, Zhang X, Shao Q, Mangin S, Fullerton E, Jiang L, Zhao W (2020) Reversible Switching of Interlayer Exchange Coupling through Atomically Thin VO2 via Electronic State Modulation. Matter 2(6):1582–1593. https://doi.org/10.1016/j.matt.2020.04.001
Gerber P, Alves T, Becerik D (2012) Extending the interaction of Building Information Modeling and Lean Construction. In: Proceedings for the 20th annual conference of the international group for lean construction
Gogus O, Boucher TO (1998) Strong transitivity, rationality and weak monotonicity in fuzzy pairwise comparisons. Fuzzy Sets Syst 94:133–144. https://doi.org/10.1016/S0165-0114(96)00184-4
Gu N, London K (2010) Understanding and facilitating BIM adoption in the AEC industry. Autom Constr 19:988–999. https://doi.org/10.1016/j.autcon.2010.09.002
Hadi KC, Zhang SF, Mahdi MS (2021) An empirical time-domain trend line-based bridge signal decomposing algorithm using Savitzky-Golay filter. Structural Control and Health Monitoring. https://doi.org/10.1002/stc.2750
Haizhao Meixiang, Gu, Jianlin Mo, Jie Qiu, Quan Yuan, Xia, (2022) Behavior of floating stone columns reinforced with geogrid encasement in model tests. Frontiers in Materials 9980851. https://doi.org/10.3389/fmats.2022.980851
Hamdi O, Leite F (2012) BIM and lean interactions from the BIM capability maturity model perspective: a case study. In: Proceedings of the 20th annual conference of the international group for lean construction
Hamidian M, Mahdi S, Hamid S (2011) Assessment of high strength and light weight aggregate concrete properties using ultrasonic pulse velocity technique. Int J Physic Sci 6(22):5261–5266
Heravi G, Kebria MF, Rostami M (2019) Integrating the production and the erection processes of pre-fabricated steel frames in building projects using phased lean management. Eng Constr Archit Manag 28:174–195. https://doi.org/10.1108/ECAM-03-2019-0133
Heravi G, Rostami M, Kebria MF (2020) Energy consumption and carbon emissions assessment of integrated production and erection of buildings’ pre-fabricated steel frames using lean techniques. J Clean Prod 253:120045. https://doi.org/10.1016/j.jclepro.2020.120045
Hosseini SS (2017) Identification and ranking the factors affecting lean manufacturing by using FAHP technique (Case study of Iran Transfo Corporation). Int Acad J Sci Eng 4:20–27
Hwang CL, Yoon K (1981) Multiple attribute decision making. Springer, Berlin
Jahandari S, Tao Z, Saberian M et al (2021) Geotechnical properties of lime-geogrid improved clayey subgrade under various moisture conditions. Road Mater Pavement Des. https://doi.org/10.1080/14680629.2021.1950816
Jahandari S, Tao Z, Saberian M, Shariati M, Li J, Abolhasani M, Rashidi M (2022) Geotechnical properties of lime-geogrid improved clayey subgrade under various moisture conditions. Road Mat Pavement Design 23(9):2057–2075
Junior SJ, Baldauf JP, Formoso CT, Tzortzopoulos P (2018) Using BIM and lean for modelling requirements in the design of healthcare projects. In: González VA (ed) 26th annual conference of the international. Group for Lean Construction (IGLC), Chennai, India
Jørgensen B, Emmitt S (2009) Investigating the integration of design and construction from a “lean” perspective. Constr Innov 9:225–240. https://doi.org/10.1108/14714170910950849
Koskela L (2000) An exploration towards a production theory and its application to construction. VTT Publ 408, Espoo 296
Kymmel W (2008) Building information modeling. McGraw-Hill, New York
de Lima Silva DF, de Almeida Filho AT (2020) Sorting with TOPSIS through boundary and characteristic profiles. Comput Ind Eng 141:106328. https://doi.org/10.1016/j.cie.2020.106328
Liu Q, Gao T, Wang J (2011) Research on application of BIM technology in construction project. In: 2011 international conference on computer science and service system (CSSS). IEEE, pp 2463–2467
Luo Z, Sinaei H, Ibrahim Z, Shariati M, Jumaat Z, Wakil K, Khorami M (2019) Computational and experimental analysis of beam to column joints reinforced with CFRP plates. Steel Compos Struct 30(3):271–280
Majedi MR, Afrazi M, Fakhimi A (2020) FEM-BPM simulation of SHPB testing for measurement of rock tensile strength. In 54th US rock mechanics/geomechanics symposium. OnePetro
Majedi MR, Afrazi M, Fakhimi A (2021) A Micromechanical Model for Simulation of Rock Failure Under High Strain Rate Loading. Int J Civ Eng 19:501–515. https://doi.org/10.1007/s40999-020-00551-2
Naghipour M, Yousofizinsaz G, Shariati M (2020) Experimental study on axial compressive behavior of welded built-up CFT stub columns made by cold-formed sections with different welding lines. Steel Compos Struct 34(3):347
Nasrollahi S, Maleki S, Shariati M, Marto A, Khorami M (2018) Investigation of pipe shear connectors using push out test. Steel and Composite Structures, An Int J 27(5):537–543
Nazari A, Soleimani Ashtiani S (2013) Analytical study of the fields of integration of Lean Mang model and building information modeling (BIM). In: 9th international conference on project management
Nguyen P, Akhavian R (2019) Synergistic effect of integrated project delivery, lean construction, and building information modeling on project performance measures: a quantitative and qualitative analysis. Adv Civ Eng 2019:1–9. https://doi.org/10.1155/2019/1267048
Nowroozi V, Hashemolhosseini H, Afrazi M, Kasehchi E (2021) Optimum design for soil nailing to stabilize retaining walls using FLAC3D. J Adv Eng Comput 5:108. https://doi.org/10.25073/jaec.202152.329
Ohno T (1988) Toyota production system: beyond large scale production. Productivity Press, Cambridge
Olson D (2003) Managerial issues of enterprise resource planning. McGraw-Hill, New York
Oskouie P, Gerber DJ, Alves T, Becerik D (2012) Extending the interaction of building information modeling and lean construction. In: 20th annual conference of the international group for lean construction
Patil SK, Kant R (2014) A fuzzy AHP-TOPSIS framework for ranking the solutions of Knowledge Management adoption in Supply Chain to overcome its barriers. Expert Syst Appl 41:679–693. https://doi.org/10.1016/j.eswa.2013.07.093
Pour AE, Afrazi M, Golshani A (2022) Experimental study of the effect of length and angle of cross-cracks on tensile strength of rock-like material. Iran J Sci Technol Trans Civ Eng. https://doi.org/10.1007/s40996-022-00891-0
Razavian L, Naghipour M, Shariati M, Safa M (2020) Experimental study of the behavior of composite timber columns confined with hollow rectangular steel sections under compression. Struct Eng Mech, An Int Journal 74(1):145–156
Rezamand A, Afrazi M, Shahidikhah M (2021) Study of convex corners' effect on the displacements induced by soil-nailed excavations Journal of Advanced Engineering and Computation 5(4):277–290
Rouhanifar S, Afrazi M (2019) Experimental study on mechanical behavior of sand-rubber mixtures. Modares Civil Eng J 19(3):83–96
Rouhanifar S, Afrazi M, Fakhimi A, Yazdani M (2021) Strength and deformation behaviour of sand-rubber mixture. Int J Geotech Eng 15(9):1078–1092
Sacks R, Radosavljevic M, Barak R (2009) The principles for bim enabled lean production management systems for construction. Innovation Construction Research Centre, Reading
Safa M, Kachitvichyanukul V (2019) Moment rotation prediction of precast beam to column connections using extreme learning machine. Structural Engineering and Mechanics, An Int J 70(5):639–647
Safa M, Sari PA, Shariati M, Suhatril M, Trung NT, Wakil K, Khorami M (2020) Development of neuro-fuzzy and neuro-bee predictive models for prediction of the safety factor of eco-protection slopes. Physica A: Statis Mech Appl 550:124046
Safa M, Shariati M, Ibrahim Z, Toghroli A, Baharom SB, Nor NM, Petković D (2016) Potential of adaptive neuro fuzzy inference system for evaluating the factors affecting steel-concrete composite beam's shear strength. Steel Compos Struct, An Int J 21(3):679–688
Salazar G, Mokbel H, Aboulezz M (2006) The building information model in the civil and environmental engineering education at WPI
Salem O, Solomon J, Genaidy A, Minkarah I (2006) Lean construction: from theory to implementation. J Manag Eng 22:168–175. https://doi.org/10.1061/(ASCE)0742-597X(2006)22:4(168)
Sedghi Y, Zandi Y, Shariati M, Ahmadi E, Azar VM, Toghroli A, Wakil K (2018) Application of ANFIS technique on performance of C and L shaped angle shear connectors. Smart Struct Syst 22(3):335–340
Shariati M, Armaghani DJ, Khandelwal M et al (2021c) Assessment of longstanding effects of fly ash and silica fume on the compressive strength of concrete using extreme learning machine and artificial neural network. J Adv Eng Comput 5:50. https://doi.org/10.25073/jaec.2021c51.308
Shariati M, Davoodnabi SM, Toghroli A et al (2021b) Hybridization of metaheuristic algorithms with adaptive neuro-fuzzy inference system to predict load-slip behavior of angle shear connectors at elevated temperatures. Compos Struct 278:114524. https://doi.org/10.1016/j.compstruct.2021.114524
Shariati M, Mafipour MS, Ghahremani B et al (2022) A novel hybrid extreme learning machine–grey wolf optimizer (ELM-GWO) model to predict compressive strength of concrete with partial replacements for cement. Eng Comput 38:757–779. https://doi.org/10.1007/s00366-020-01081-0
Shariati M, Naghipour M, Yousofizinsaz G, Toghroli A, Tabarestani NP (2020a) Numerical study on the axial compressive behavior of built-up CFT columns considering different welding lines. Steel Compos Struct 34(3):377–391
Shariati M, Shariati A, Trung NT et al (2021a) Alkali-activated slag (AAS) paste: correlation between durability and microstructural characteristics. Constr Build Mater 267:120886. https://doi.org/10.1016/j.conbuildmat.2020.120886
Shariati M, Shariati A, Trung NT, Shoaei P, Ameri F, Bahrami N, Zamanabadi SN (2021) Alkali-activated slag (AAS) paste: Correlation between durability and microstructural characteristics. Construct Build Mater 267:120886
Shariati M, Sulong NR, Suhatril M, Shariati A, Khanouki MA, Sinaei H (2013) Comparison of behaviour between channel and angle shear connectors under monotonic and fully reversed cyclic loading. Construct Build Mater 38:582–593
Shariati M, Tahmasbi F, Mehrabi P, Bahadori A, Toghroli A (2020b) Monotonic behavior of C and L shaped angle shear connectors within steel-concrete composite beams: an experimental investigation. Steel Compos Struct 35(2):237–247
Suhatril M, Osman N, Azura Sari P, Shariati M, Marto A (2019) Significance of surface eco-protection techniques for cohesive soils slope in Selangor. Malaysia. Geotech Geolo Eng 37(3):2007–2014
Tavakkoli O, Kamyab H, Shariati M, Mohamed AM, Junin R (2022) Effect of nanoparticles on the performance of polymer/surfactant flooding for enhanced oil recovery: A review. Fuel 312:122867
Tavassoli A, Mortahab MM (2008) A study of the application of lean construction method in Iran and proposing a workshop performance considering this method. In: 4th international conference on project management, Tehran, Ariana Research Group
Toghroli A, Mohammadhassani M, Suhatril M, Shariati M, Ibrahim Z (2014) Prediction of shear capacity of channel shear connectors using the ANFIS model. Steel Compos Struct 17(5):623–639
Wenfeng ZX, Bo T, Shan Y, Yueming L, Jiawei D, Lirong TY (2022) A Few Shot Classification Methods Based on Multiscale Relational Networks. Appl Sci 12(8):4059. https://doi.org/10.3390/app12084059
Xu YG, Qian C (2013) Lean cost analysis based on BIM modeling for construction project. Appl Mech Mater 457–458:1444–1447. https://doi.org/10.4028/www.scientific.net/AMM.457-458.1444
Xuan LX, De L, Zhixin T, Lirong L, Wenfeng YZ (2022) Forecasting Urban Land Use Change Based on Cellular Automata and the PLUS Model. Land 11(5):652. https://doi.org/10.3390/land11050652
Yuxi Siyu, Lu, Xia Ban, Bo Zhang, Shan Yang, Lirong Liu, Wenfeng Yin, Zheng, (2022) Adaptive control of time delay teleoperation system with uncertain dynamics. Frontiers in Neurorobotics 16928863. https://doi.org/10.3389/fnbot.2022.928863
Zahraee SM (2016) A survey on lean manufacturing implementation in a selected manufacturing industry in Iran. Int J Lean Six Sigma 7:136–148. https://doi.org/10.1108/IJLSS-03-2015-0010
Zandi Y, Shariati M, Marto A, Wei X, Karaca Z, Dao DK, Khorami M (2018) Computational investigation of the comparative analysis of cylindrical barns subjected to earthquake. Steel Compos Struct 28(4):439–447
Zhang Z, Yang F, Zhang H, Zhang T, Wang H, Xu Y, Ma Q (2021) Influence of CeO2 addition on forming quality and microstructure of TiC -reinforced CrTi4-based laser cladding composite coating. Mater Character. https://doi.org/10.1016/j.matchar.2020.110732
Author information
Authors and Affiliations
Corresponding author
Rights and permissions
Springer Nature or its licensor holds exclusive rights to this article under a publishing agreement with the author(s) or other rightsholder(s); author self-archiving of the accepted manuscript version of this article is solely governed by the terms of such publishing agreement and applicable law.
About this article
Cite this article
Moballeghi, E., Pourrostam, T., Abbasianjahromi, H. et al. Assessing the Effect of Building Information Modeling System (BIM) Capabilities on Lean Construction Performance in Construction Projects Using Hybrid Fuzzy Multi-criteria Decision-Making Methods. Iran J Sci Technol Trans Civ Eng 47, 1871–1891 (2023). https://doi.org/10.1007/s40996-022-00971-1