Introduction

Project management issues like cost overrun and time overrun impact a project arising from associated uncertainties and risks. Due to poor risk management, most of the infrastructure projects fail due to huge time and cost overrun. There is relatively very low implementation of formal project risk management methods in practice, leading to the construction industry consistently suffering from poor project performance. This paper is an attempt to develop and compare risk indices through three different risk analysis methods. Askari et al. [1] state that the increasing growth of the construction projects calls for employing effective risk management techniques. The risks involved and associated with the construction of a complex infrastructure project like underground corridor construction for metro rail operations have been studied by Sarkar and Dutta [2]. Their study has enabled in development of a risk management model which would act as a guide for developing risk mitigation strategies for ongoing and future metro rail projects in India. They have developed a questionnaire and personally interviewed the experts from the underground corridor project. In this process, they have identified the risks at various phases of the project starting from the feasibility phase to the completion of the project. Then, they have used the expected value method (EVM) to compute the effect of risky sources in terms of their impact and severity. The primary objective of this paper is to study the available methods for risk analysis and then to develop risk indices through application of some of the major risk analysis techniques like modified expected value method (MEVM), fuzzy expected value method (FEVM) and fuzzy analytic hierarchy process (FAHP). The risk indices developed through different methods have been compared, and the relative advantages and disadvantages of each method have been highlighted.

Literature Review

Project risk management is comprised of three basic processes of risk identification, risk assessment and risk response planning. All these processes need to be carried out through all phases of a project starting from feasibility through design, development and implementation. Choi et al. [3] state that risk identification is a process to acknowledge risk events and to identify the characteristics of risk events for the selected project based on the risk-related information. It is of considerable importance because the processes of risk analysis and response strategies may only be performed on the identified potential risks. Kuo and Lu [4] use fuzzy multi-criteria decision-making approach to analyse the risks of metropolitan construction projects. They state that to improve the chance of success and reduce potential risks, in the initial phase, project risks and uncertain factors should be carefully identified, assessed and monitored. Risk index is a measure of the risk severity for activities within a project according to which the necessary mitigation measures can be adopted. Sarkar et al. [5] develop risk indices for quality parameters associated with elevated corridor metro rail project of Delhi using modified analytic hierarchy process (MAHP). Further, Sarkar et al. [6] use fuzzy analytic hierarchy process (FAHP) to develop risk index for elevated corridor metro rail project of Ahmedabad. The risk index developed would act as a guide for deciding risk mitigation measures for future metro rail projects across India.

Saaty [7] explains about analytic hierarchy process (AHP). It is a multi-criteria decision-making (MCDM) management tool for complex situations. The basic approach of AHP is to break down the complex problem into numerous small and simple problems. The main uniqueness of AHP is its inherent capability of weighting a great number of different-natured factors, qualitative and quantitative, in order to make a decision, thereby producing a formal and numeric basis for solution. Mustafa and Al-Bahar [8] explain that the AHP developed by Saaty is a robust and flexible multi-criteria decision analysis methodology. Shapira and Simcha [9] also use AHP methodology for risk analysis. They explain AHP in a simplified manner. Firstly, the problem is identified and then hierarchy construction is carried out. In this step, list of attributes are generated. The attributes are organized in a hierarchy-type structure that reflects their mutual relationships. The highest level of the structure consists of the primary goal of the problem. The AHP is used for scaling the weight of the risks in each level of hierarchy with respect to risks of the next higher level. The fuzzy AHP model is often used to tackle complex decision-making that calls for subjective judgement on the basis of logical reasoning rather than simple feeling or intuition (Zou et al. [10]). Oliveros and Fayek [11] present useful application of fuzzy logic in solving a construction-related problem like delay and progress of the projects. Li and Zou [12] develop fuzzy AHP-based risk assessment methodology for public–private partnership (PPP) projects and also propose fuzzy AHP for improving the risk assessment accuracy. Rao et al. [13] use fuzzy for selection of optimal contractor for construction industry projects. The final selection is made based on the integrated score in the prequalification and bid evaluation stages. Landfill site selection in Kolkata by the use of AHP as a multi-criteria decision-making tool is carried out by Majumder et al. [14]. Fuzzy-based decision support system is developed by Srinivas et al. [15] for condition assessment and rating of bridges. Roy et al. [16] use fuzzy logic for preventive maintenance of hydropower plants so that power generation is not interrupted. Further, Eom and Paek [17] develop an environmental risk index model for general contractors to minimize third-party environmental disputes at construction sites. Also, interpretive ranking process (IRP) model is developed by Mhatre et al. [18] for critical risk factors of Indian construction industry projects.

Reviewing the available literature, it is observed that various authors have used AHP, fuzzy, EVM and fuzzy AHP methods for risk analysis of projects. But fuzzy EVM and modified EVM were not used by any of the researchers and field experts. The present research aims at developing risk index using MEVM, FEVM and FAHP for a multi-disciplinary complex infrastructure project like construction of elevated corridor for metro rail operations in Bangalore, India. This would help the project authorities in prioritizing and ranking the major identified risks and thus in adopting suitable risk mitigation measures in reducing the severities of the identified risks.

Conceptual Framework

Risk Index Calculation by Modified Expected Value Method (MEVM)

Sarkar and Dutta [2] have used EVM for underground metro project. They considered critical path method (CPM) network, which has “N” activities represented by n = (1, …, N), and “M” risk sources indicated by m = (1, …, M). They had extended the work of Nicholas [19].

The weightage of each activity is computed from the feedback by 61 experts received through the questionnaire survey:

$$\mathop \sum \limits_{m = 1}^{M} W_{mn} = 1\quad {\text{for all}}\quad n \left( {n = 1, \ldots ,N} \right).$$
(1)

The likelihood of all risk sources for each activity n can be combined and expressed as a single composite likelihood factor. The weightages of the risk sources of the activities are multiplied with their respective likelihoods to obtain the CLF for the activity. The relationship of computing the CLF as a weighted average is given below:

$$\left( {\text{CLF}} \right)_{n} = \mathop \sum \limits_{m = 1}^{M} L_{mn} \cdot W_{mn} \quad {\text{for all}} \quad n$$
(2)
$$\begin{aligned} & \left( {\text{CIF}} \right)_{n} = \mathop \sum \limits_{m = 1}^{M} I_{mn} \cdot W_{mn} \quad {\text{for all}}\quad n \\ & 0 \le I_{mn} \le 1\mathop \sum \limits_{m = 1}^{M} W_{mn} \quad {\text{for all}}\quad n \\ \end{aligned}$$
(3)

where Lmn is the likelihood of mth risk source for nth activity, Wmn weightage of mth risk source for nth activity, Imn impact of mth risk source for nth activity, CLFn composite likelihood factor for nth activity, CIFn composite impact factor for nth activity.

Further, CIF and CLF were calculated for each attribute using Eqs. (2) and (3), respectively. The severity risk value for each major activity was computed by product of CIF and CLF using Eq. 4:

$${\text{Risk severity}}_{{\left( {1, \ldots ,N} \right)}} \,{\text{by EVM}} = {\text{CLF}}_{n} \times {\text{CIF}}_{n} .$$
(4)

The risk severity was computed for each attribute using Eq. 4. Finally, risk index (RI) for every major activity was computed by product of risk severity and normalized weight of that particular activity using Eq. 5

$${\text{Risk index}}_{{\left( {1, \ldots ,N} \right)}} \,{\text{by MEVM}} = \left( {\text{risk severity}} \right)_{n} \times \left( {\text{normalized weight}} \right)_{n}$$
(5)

where “N” activities and are represented by n = (1, …, N).

Risk Index Calculation by Fuzzy Expected Value Method (FEVM)

To convert each linguistic variable into fuzzy values, there was a need to define five membership functions for risk severity. The membership functions are defined with triangular fuzzy numbers. The computation with triangular fuzzy is relatively simple in comparison with trapezoidal fuzzy. The membership functions were defined with values “very low”, “low”, “medium”, “high” and “very high” according to their likelihood and their impact of risk. The values of the linguistic scale were chosen from 0 to 5 at an increment of 1. The values of likelihood and their impact of risk range from 0 to 5 (refer Fig. 2).

The CLF and CIF values acquired from EVM method for all 24 major activity risks were used as inputs for fuzzy method by using MATLAB software to find out the risk severity by fuzzy EVM method. After the calculation of risk severity by incorporating fuzzy in EVM, RI can be computed by multiplying normalized weight with fuzzy risk severity.

Figure 1 highlights the triangular fuzzy membership function where the variable “l” indicates the extreme left value, “m” is the middle value and “n” is the extreme right value.

Fig. 1
figure 1

Triangular membership function

Figure 2 represents the triangular membership function with the linguistic scale both quantitative and qualitative. The detailed equation for fuzzy membership function is presented in Eq. (6):

$${\text{triangle}}\,\left( {x;l, m, n} \right) = \left\{ {\begin{array}{*{20}l} {0,} \hfill & {x \le l} \hfill \\ {\frac{x - l}{m - l},} \hfill & {l \le x \le m} \hfill \\ {\frac{n - x}{n - m},} \hfill & {m \le x \le n} \hfill \\ {0,} \hfill & {n \le x} \hfill \\ \end{array} } \right.$$
(6)

where x is the mean of probability (P)/impact (I)/detection (D) plotted on x axis, l leftmost value in a triangle, m middlemost value in a triangle, n rightmost value in a triangle.

Fig. 2
figure 2

Membership function with linguistic scale

Figure 3 highlights the MATLAB representation for the triangular membership function for likelihood parameter in which the membership functions were defined from “very low” to “very high” with linguistic scale chosen from 0 to 1 at an increment of 0.25.

Fig. 3
figure 3

MATLAB representation for membership function “likelihood ranges”

Further, the risk index through FEVM can be computed through the following equation:

$${\text{Risk index}}_{{\left( {1, \ldots ,N} \right)}} = \left( {\text{risk severity by FEVM}} \right)_{n} \times \left( {\text{normalized weight}} \right)_{n}$$
(7)

where “N” activities are represented by n = (1, …, N).

Risk Index Calculation by Fuzzy Analytic Hierarchy Process (FAHP)

Saaty [7] had explained about analytic hierarchy process (AHP). Shapira and Simcha [9] had explained AHP methodology in greater detail. The number of attributes, which are the major risks associated with the project, need to be identified. The second step is pairwise comparison. Importance of two attributes is compared by giving them numbers on a Satty scale (1, 3, 5, 7, 9). The third step is the formulation of synthesized matrix. This matrix is obtained from the pairwise comparison matrix. Each element of the synthesized matrix is obtained by dividing the value of the element of the pairwise comparison matrix by their respective column total. The outcome of synthesized matrix is priority vectors (PVs). These are obtained by the addition of the elements in each row of the synthesized matrix and then dividing by the number of the elements in that row. The highest value of the vector is given the maximum priority.

Relative Weight Computation

Several iterations are used to compute the eigenvector, of the comparison matrix, of which the average of normalized columns (ANC) method is the most accurate. ANC computation of vector Wx for the relative weight of the attribute in row i which is an element of the eigenvector W, for a reciprocal N × N matrix, is as follows:

$$Wx = \frac{1}{N} \mathop \sum \limits_{y = 1}^{N} \left( {Axy/\mathop \sum \limits_{l = 1}^{N} Aly} \right)$$
(8)

where n is the number of rows or columns in a square matrix, Wx the relative weight of the attribute in row x, Axy element located in row x and column y of the comparison matrix, Aly element located in row k of any normalized column x, y, l = 1, 2, …, N.

Weighted Sum Matrix

The weighted factor elements of the weighted sum matrix are obtained by multiplying each element of the pairwise comparison matrix by their respective priority vector. The weighted sum is the summation of the elements row-wise. The eigenvalues (λ) are obtained from the following relationship:

$${\text{Eigen value}} = {\text{weighted sum / PV}}$$
(9)
$${\text{Priority vectors}} = \mathop \sum \limits_{n = 1}^{N} \frac{\text{synthesized matrix }}{N}$$
(10)
$$\lambda \hbox{max} = \mathop \sum \limits_{n = 1}^{N} \frac{\lambda }{N}$$
(11)
$${\text{Consistency index}} = \left( {\lambda \hbox{max} - \, N} \right)/\left( {N - 1} \right)$$
(12)

where n is the number of attributes.

The consistency ratio (CR) is a measure for controlling the consistency of pairwise comparisons. Consistency ratio (CR) is to measure how consistent the judgements have been relative to large samples of purely random judgements. Value of consistency ratio should be less than 0.2 for more consistent judgements

$${\text{Consistency}}\,{\text{ratio}} = {\text{Consistency}}\,{\text{index/Random}}\,{\text{consistency}}\,{\text{index}}$$
(13)

where RC is the random consistency index

$$\left( {\text{PV for EV}} \right)n = \frac{{{\text{EV}}n}}{{\mathop \sum \nolimits_{n = 1}^{N} {\text{EV}}n}}$$
(14)

where n = (1, …, to N).

The responses obtained from the questionnaire survey responded by about 61 experts were in a risk rating scale of 0–1, where “0” indicates low-risk situation and “1” indicates very-high-risk situation causing huge time and cost overrun of the project. For computational simplicity, we have converted risk rating values obtained from questionnaire survey into “Satty scale” (1, 3, 5, 7, 9) with the help of which pairwise comparison matrix was constructed both for likelihood and for impact reviews. Then, synthesized matrix is constructed for both likelihood and impact reviews. The outcomes of synthesized matrix were priority vectors. These were obtained by summing up the elements in each row of the synthesized matrix and then dividing by the number of the elements in that row.

Methodology

The methodology adopted for this research is primary data research where primary data have been collected from Bangalore Metro Rail Corporation (BMRC). The risks associated and involved in the construction of the elevated corridor metro rail were identified by the personal experience of the authors and by interaction with experts and professionals associated with the construction of the metro rail projects across India. Twenty-four major risks were identified, and a questionnaire was prepared. The respondents need to respond about the likelihood, impact and weightage associated with each risk factor. A sample questionnaire is presented in “Appendix 1” section. The questionnaire was circulated to 85 experts and professionals, out of whom 61 experts and professionals responded to this study. The experts and professionals were project managers, deputy general managers, project engineers, site engineers, quality control engineers, safety engineers, supervisors, foreman and construction equipment operators. The inconsistent responses were modified by carrying out a second round of questionnaire survey through Delphi method. Finally, the responses obtained from 61 experts were analysed through MEVM, FEVM and FAHP to obtain the risk severity and risk index.

Case Study

The case study undertaken for this research work is Bangalore elevated metro rail project. The construction is being executed by IL and FS Company Limited starting from the Nayandahalli to RV college station. The length of the section under study is 4.2 km. There are four elevated stations. A total of 133 piers and 540 piles would be constructed. The weight of each segment is 14 tons. For this section, IL and FS Company Limited will produce, erect and launch 1180 segments for the viaduct from Nayandahalli to RV college station. The methodology of research work was the formulation of questionnaire. Firstly to identify the major activities and risks involved from the beginning to handing over of the project, the responses of 61 experts associated with metro rail corridor projects were used as inputs for computation of the risk severity. Two rounds of discussions were carried out with metro officials and staff including construction equipment operators, foreman, supervisors, site engineers, project engineers, site in charges, project managers, deputy general managers, quality control engineers and safety engineers. Discussion with consultants and chief engineer was also carried out for the finalization of questionnaire, rating scales and their responses. The risk assessment is carried out in terms of risk severity index and their ranks.

Analysis and Results

For the elevated corridor metro rail construction project, the risk severity of each major activity of the project is computed for all 24 major activities which are presented in Table 1. After the calculation of risk severity by EVM method, risk index was calculated by multiplying risk severity with normalized weights (Table 1).

Table 1 Final risk severity values, risk index and ranks by MEVM

Table 1 represents the final risk severity values (both qualitative and quantitative), final risk index values and ranks through MEVM of all the 24 activities involved in the construction of the elevated corridor metro rail construction project. The scale for risk severity is “0.000–0.100 (very low risk)”, “0.101–0.149 (low risk)”, “0.150–0.299 (medium risk)”, “0.300–0.350 (high risk)” and “0.351–1.000 (very high risk)”. It has been observed that through MEVM activity risks like “risks in launching girder installation and segment erection”, “risks in traffic and utility diversion”, “risks in land handover”, “feasibility and DPR risks” and “risks in segment casting” have obtained first to fifth rank, respectively, based on the risk index values. These activities need to be monitored with utmost care by the project authorities. The risk index scale ranges from 0 (very low risk) and 1 (critical risk). Risk index scale along with the classification is presented in “Appendix 2” section.

Table 2 represents the final risk severity values, final risk index and ranks computed through FEVM of 14 activities amongst the 24 activities involved in the construction of the elevated corridor metro rail project. The CLF and CIF values obtained from EVM method for all 24 major activities were used as inputs for fuzzy method by using MATLAB software (Mathworks.Matlab.R2010a). Five membership functions and 25 rules were created in software. The outputs are obtained for all 24 activities considered for this study. The scale for risk severity is “0.000–0.100 (very low risk)”, “0.101–0.299 (low risk)”, “0.300–0.569 (medium risk)”, “0.570–0.684 (high risk)” and “0.685–1.000 (very high risk)”. Through FEVM, activity risks like “risks in traffic and utility diversion”, “risks in land handover”, “risks in launching girder installation and segment erection” and “risks in segment casting” have obtained first to fifth ranks according to risk index values.

Table 2 Final risk severity values, risk index and ranks by FEVM

The risk severity, risk index and risk ranking obtained through FAHP for 14 activities amongst the 24 activities are presented in Table 3. The scale for risk severity is “0.000–0.100 (very low risk)”, “0.101–0.130 (low risk)”, “0.131–0.140 (medium risk)”, “0.141–0.145 (high risk)” and “0.146–1.000 (very high risk)”. It has been observed that through analysis by FAHP activity risks like “feasibility and DPR risks”, “risks in tender and award of contract”, “risks in land handover”, “risks in traffic and utility diversion” and “risks in shuttering works” have obtained first to fifth rank, respectively, according to the risk index values. The MATLAB representation for the activity “risks in piling work (A12)” for computation of risk severity is presented in Fig. 4.

Table 3 Final risk severity values, risk index and ranks by FAHP
Fig. 4
figure 4

MATLAB representation for risk severity for activity “risks in piling works” (FAHP)

The final risk indices computed through MEVM, FEVM and FAHP for all the 24 activity risks for the construction of the elevated corridor metro rail project are presented in Table 4. The comparison of the graphical representation of risk indices by all the three methods is presented in Fig. 5.

Table 4 Risk index comparison by MEVM, FEVM and FAHP
Fig. 5
figure 5

Risk index comparison by MEVM, FEVM and FAHP

From Table 5 and Fig. 5, it has been analysed that FAHP method is having very narrow risk severity range (0.140–0.162) and very narrow risk index range (0.0055–0.0074). Also, there is overlap of rankings and only 13 ranks for 24 activity risks can be obtained. The risk index curve of FAHP has minimum fluctuations. The risk index curve obtained through MEVM has higher fluctuations than FAHP. Further, MEVM method is having good risk severity range (0.165–0.512) and good risk index range (0.00368–0.03547). Also, 22 ranks are obtained for 24 activities. The risk index curve for FEVM method is more fluctuating than FAHP and MEVM. Further, FEVM has the widest risk severity range (0.501–0.781) and widest risk index range (0.01637–0.03978). There is only one overlap of rankings, and 23 ranks are obtained for 24 activities.

Table 5 Relative comparison of the different methods of risk analysis

In FAHP method, input values, i.e. PVs for both likelihood and impact are smaller because total of all PVs for likelihood and PVs for impact for all activities (N), should be 1 in both cases, whereas in MEVM and FEVM the values of likelihood or impact range from 0 to 1. Hence when the number of activities is more than 20, PV of likelihood or PV of impact for each activity computed would be smaller. But in case of MEVM or FEVM, likelihood or impact values ranges from 0 to 1; hence, the number of activities does not influence input values of fuzzy and also output of fuzzy in terms of final risk severity values. Hence, the final risk severity values are not affected by the number of activities in case of MEVM or FEVM. Table 5 represents the relative comparison of the different methods of risk analysis.

Conclusion

From the analysis carried out, it has been observed that FAHP method is having very narrow risk severity range (0.140–0.162) and very narrow risk index range (0.0055–0.0074). Also there is overlap of large number of risk rankings and only 13 ranks can be obtained for 24 activity risks. MEVM method is having good risk severity range (0.165–0.512) and risk index range (0.00368–0.03547). FEVM method is having widest risk severity range (0.501–0.781) and risk index range (0.01637–0.03978). Further, there is only one overlap of rankings in FEVM and 23 ranks can be obtained for 24 activity risks. It has been observed that in FEVM the computed values of risk indices predict risk severities which can be ranked according to criticality for almost all the identified activities. Thus, project authorities can easily take necessary mitigation measures to reduce the risk severities. In MEVM and FAHP, there may be overlap of rankings based on the risk indices value. Thereby, FEVM is more sensitive than MEVM and FAHP. Also, FEVM produces good results for both small and large number of activities. MEVM gives good results for up to 25 numbers of activities and FAHP gives good results up to 20 numbers of activities. Hence, FEVM appears to be the best suited method for risk management tool for elevated corridor metro rail projects.

It has been found that from MEVM, FEVM and FAHP methods, “risks in launching girder erection”, “risks in traffic and utility diversion”, “risks in land handover”, “feasibility and DPR risks”, “risks in segment casting”, “risks in tender and award of contract”, “risks in pre-stressing” and “risks in road widening and barricading work” have obtained 1–7 ranks based on their risk index values. These activities are very crucial, and therefore, utmost care has to be taken for risk mitigation of these activities. A limitation of this study is that the developed risk indices are dependent on the responses given by the respective respondents through the questionnaire survey. Risk detection parameters were not considered for the study.

Scope for Future Research

Risk detection framework needs to be integrated with the risk analysis methods for better results. As the concept is generic, similar risk indices can be developed for other infrastructure projects like underground corridor metro rail project, highway project, bus rapid transit system project and ports project.