Abstract
The construction industry all over the world has to face a major challenge of cost and time overruns repeatedly from commencement to completion of the project. These overruns result in huge losses in terms of cost and time. This study focusses on the in-depth analysis of the overrun factors affecting construction projects. A total of 44 overrun factors were identified from the literature and were categorized into four major categories, namely project related, management related, legal-constraints faced and site-resource related. A questionnaire was developed using these factors and was filled by 105 respondents. Relative importance index was used to rank different factors according to their criticality in overruns. For statistical analysis, Minitab was used. The most critical overrun factors identified were, namely delay in obtaining permission from authorities, poor supervision and site management, unrealistic time schedule, unforeseen ground conditions and lack of skilled professionals. This research will help researchers, engineers, project managers, construction practitioners, etc. to deal with overrun factors in an effective manner such that projects can be completed within a specific allocated cost and time.
Access provided by Autonomous University of Puebla. Download conference paper PDF
Similar content being viewed by others
Keywords
1 Introduction
Cost overrun and delay in projects is a foremost challenge associated with nearly all projects in the construction industry. Inclination of construction projects towards overruns is because of risk and uncertainties involved in these projects. In developing countries, this problem is more severe as in some projects cost and time exceed double the amount than anticipated [1]. Construction plays an important role in economic growth of a country and also considered as largest generator of employment opportunities. Despite of its importance in development of a country, it has to face many challenges. In construction industry, a project is considered as successful if it meets both the criteria of budget and deadline [2]. Construction projects that fail to meet these criteria will have to face losses in terms of cost and time. To complete the project within budget and deadline, generally quality of project delivered is sacrificed. The major reason for these overruns is the lack of knowledge regarding the factors affecting cost and time. A construction project mainly consists of two major phases, namely pre-construction phase and construction phase. There is a need of applying risk management process in both the stages of the project. Both the stages play an important role in successful completion of project objectives. First stage is mainly about planning, scheduling, deciding budget, etc. Pre-construction is considered an important stage if managed precisely ensures more profits and less uncertainties [3]. Second stage consists of implementation of the things that was planned and scheduled in first stage with continuous monitoring and controlling. Overruns can affect the project objectives in terms of cost, time, quality and productivity [4]. In this research for identification and management of overrun in construction projects, we will use framework consisting of three steps, namely identification of factors responsible for overruns, assessment of identified factors and providing mitigation measures [5]. The aim of this research is to identify critical overrun factors present in construction industry and to manage them such that it has minimum negative effects on the project cost and time.
2 Background Study
A number of factors are responsible for cost and time overruns in construction projects. Previous studies have defined cost overrun in a project as the difference between total cost required for completion of project and the estimated/budgeting cost at time of agreement or contract [6, 7]. According to the literature, time overrun is defined as difference between time required for completion of the project and time agreed in agreement or contract for delivering the completed project [8]. The results of past studies clearly state that cost and time overrun badly affects the project as well as the associated construction companies. In some case, even companies go bankrupt due to these overruns [9]. So, there is need of systematic study of these overruns which can provides clarity about the critical overrun factors involved. The first step suggested by literature is identification of factors involved in construction projects. This is an important step as without knowing what factors are involved, we cannot proceed further [10]. Next step is assessment of the identified overrun factors. This step will help us in identifying critical factors having maximum impact on overruns. Last step is suggesting mitigation measures and continuous monitoring over the construction process. For positive results, monitoring and control are important as new overrun factor can emerge at any time during the construction process.
3 Research Methodology
3.1 Overrun Factors Identification
Starting with the identification of cost and time overrun factors involved in construction projects. A total of forty-four overrun factors were identified through a detailed literature review related to cost and time overruns. Then, these factors were categorized into four major categories, namely project scope, management related, legal constraints faced and site-resource related. Project scope category consists of eight factors, management category consists of six factors, legal-constraint category and site-resource-related category consist of fifteen factors each.
3.2 Questionnaire Survey and Respondents
A questionnaire was prepared from the identified overrun factors. It consists of three parts—first part was about respondents’ profile and second part was explaining the Likert scale. A five-point Likert scale (1 = very less impact and 5 = very high impact) was used for assessing the impact of overrun factors. A total of 155 survey forms were distributed, out of which 105 completely filled survey forms were collected and used in this research. Data obtained from Likert scale was assessed in Minitab. The survey was conducted in two states of India, namely Punjab and Himachal Pradesh. This survey was filled by respondents involved in dealing with cost and time overruns. The respondents were having different roles like engineer, site supervisor, project manager, contractor and consultant. These survey forms were filled by respondents having experience of working in different parts of India. So, the results of this study can be generalized for all the construction projects. Fifty-five (52.38%) respondents were having experience of more than ten years in construction industry. Number of respondents along with their roles and years of experience are shown in Table 1.
4 Analysis of Data and Results
4.1 Analysis for Reliability of Questionnaire
Internal consistency of overrun factors and questionnaire survey reliability are important aspects to judge whether the survey results are appropriate or not [11, 12]. This was done by using a statistical software named Minitab to check Cronbach alpha. Generally, Cronbach alpha has a value between 0 and 1. Higher the value higher is the reliability and internal consistency [13]. Overall, Cronbach alpha for questionnaire was found to be 0.852, which ensures high reliability and internal consistency of data collected.
4.2 Ranking of Overrun Factors
For analysis of different overrun factors, relative importance index (RII) technique was used. This method was found appropriate for ranking of critical risk factors as compared to other methods [14,15,16]. RII was calculated by using Eq. (1)
where ai = assigned weight to ith response, ni = frequency of ith response, N = total number of respondents, A = highest weight. Value of RII indicates the impact of factor on cost and time overrun in a project. Higher the value of RII more critical the factor. RII for different categories was found using Eq. (1) and considering factors present in that category only. RII for project category was found to be 0.698, RII for management category was found to be 0.727, RII for legal-constraints faced category was found to be 0.672, and RII for site-resource related category was found to be 0.692. Similarly, Cronbach alpha for different categories was found using Minitab and considering factors present in that category only. Cronbach alpha for project category was found to be 0.723, Cronbach alpha for management category was found to be 0.810, Cronbach alpha for legal-constraints faced category was found to be 0.776, and Cronbach alpha for site-resource-related category was found to be 0.753. RII for different overrun categories along with Cronbach alpha is shown in Table 2.
After calculating RII, overrun factors were arranged in ascending order such that factor with highest RII value was ranked first and factor with lowest RII value was ranked last. The value of RII ranged between 0.8171 (high) and 0.5657 (low) for 44 overrun factors. Top five overrun factors identified in construction projects are delay in obtaining permission from authorities, poor supervision and site management, unrealistic time schedule, unforeseen ground conditions and lack of skilled professionals. RII value for different overrun factors is calculated in Table 3.
5 Discussion and Guidelines
In previous studies, very less research is done collectively on both the overrun factors, i.e. cost and time [17, 18]. This study identifies the most critical overrun factors responsible for project failures in terms of achieving its objectives within budget and time allocated. Top fifteen overrun factors categorization along with their overall ranking and ranking within category are shown in Table 4. In top fifteen overrun factors, it was found that four factors were from each project-related and management category. Two factors were from legal-constraints category, and five factors were from site-resource-related category. Top factors identified in project-related category were unrealistic time schedule, change in scope of work and rework due to error in execution. Top factors identified from management category were poor supervision and site management, poor leadership and management qualities, and slow decision-making from owner. Top factors recognized from legal-constraints category were delay in obtaining permission from authorities and penalties resulting from low qualities. Top factors identified from site-resource-related category were unforeseen ground conditions, lack of skilled professionals and extreme weather conditions.
For successful achievement of project objectives, this study suggests the following guidelines.
-
Developing the framework: A framework should be prepared project-specific for both the stages, i.e. preconstruction stage as well as construction stage.
-
Identified overrun factors: Identified overrun factors should be managed as soon as possible to decrease its negative effects and increase positive project outcomes.
-
Overrun stage: As overrun can occur in any stage from commencement till accomplishment of the project. These overrun factors should be further divided into following stages to have better understanding and control. These stages are feasibility stage, procurement stage, construction stage, operation stage and transfer stage.
-
Monitor and control: New overrun factors keep on emerging in a construction project. Overrun management is an iterative process with continuous addition of new emerged factor in management plan. This ensures better control over cost and time overruns.
6 Conclusion
The findings of this research fill the knowledge gap and discloses the critical overrun factors present in construction industry. Critical overrun factors need to be managed before it can negatively affect construction project. Poor management and execution of tasks in project will require extra resources to get back on track. So, overrun factors should be managed as soon as they emerge. Site-resource-related category was found to be most critical with five overrun factors in top fifteen. The top five factors recognized with highest value of RII were delay in obtaining permission from authorities with RII value of 0.8171, poor supervision and site management with RII value of 0.7962, unrealistic time schedule with RII value of 0.7924, unforeseen ground conditions with RII value of 0.7867 and lack of skilled professionals with RII value of 0.7790.
For different construction projects, overrun factors may slightly vary. Further scope of this study is similar identification and ranking of critical overrun factors can be done project specific, i.e. considering a particular project like building project, infrastructure project, energy project, etc. Region of project can also be considered as sometimes factors change according to the location of the project. So, this research is significant for engineers, project managers, construction practitioners, risk managers, etc. as they have to deal with cost and time overrun in construction projects.
References
Le-Hoai L, Dai Lee Y, Lee JY (2008) Delay and cost overruns in Vietnam large construction projects: a comparison with other selected countries. KSCE J Civ Eng 12(6):367–77. https://doi.org/10.1007/s12205-008-0367-7
Olawale YA, Sun M (2010) Cost and time control of construction projects: inhibiting factors and mitigating measures in practice. Constr Manage Econ 28(5):509–26. https://doi.org/10.1080/01446191003674519
Larsen JK, Shen GQ, Lindhard SM, Brunoe TD (2016) Factors affecting schedule delay, cost overrun, and quality level in public construction projects. J Manage Eng 32(1):04015032. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000391
Flyvbjerg B, Holm MS, Buhl S (2002) Underestimating costs in public works projects: error or lie? J Am Plann Assoc 68(3):279–95. https://doi.org/10.1080/01944360208976273
Assaf SA, Al-Hejji S (2006) Causes of delay in large construction projects. Int J Project Manage 24(4):349–57. https://doi.org/10.1016/j.ijproman.2005.11.010
Sharma S, Gupta AK (2019) Risk identification and management in construction projects: literature review. Int J Human Arts Soc Sci 5(6):224–231. https://doi.org/10.20469/ijhss.5.20002-6
Doloi H, Sawhney A, Iyer KC, Rentala S (2012) Analysing factors affecting delays in Indian construction projects. Int J Project Manage 30(4):479–89. https://doi.org/10.1016/j.ijproman.2011.10.004
Yang JB, Wei PR (2010) Causes of delay in the planning and design phases for construction projects. J Arch Eng 16(2):80–83. https://doi.org/10.1061/(ASCE)1076-0431(2010)16:2(80)
Kazaz A, Ulubeyli S, Tuncbilekli NA (2012) Causes of delays in construction projects in Turkey. J Civ Eng Manage 18(3):426–35. https://doi.org/10.3846/13923730.2012.698913
Doloi H (2013) Cost overruns and failure in project management: Understanding the roles of key stakeholders in construction projects. J Constr Eng Manage 139(3):267–79. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000621
Ahsan K, Gunawan I (2010) Analysis of cost and schedule performance of international development projects. Int J Project Manage 28(1):68–78. https://doi.org/10.1016/j.ijproman.2009.03.005
Sharma S, Gupta AK (2020) Identification and management of risk in building and infrastructure projects. J Constr Eng Technol Manage 10(2):1–9
Abd El-Karim MS, Mosa El Nawawy OA, Abdel-Alim AM (2017) Identification and assessment of risk factors affecting construction projects. HBRC J 13(2):202–216. https://doi.org/10.1016/j.hbrcj.2015.05.001
Sambasivan M, Deepak TJ, Salim AN, Ponniah V (2017) Analysis of delays in Tanzanian construction industry. Eng Constr Arch Manage. https://doi.org/10.1108/ECAM-09-2015-0145
Iyer KC, Jha KN (2005) Factors affecting cost performance: evidence from Indian construction projects. Int J Project Manage 23(4):283–295. https://doi.org/10.1016/j.ijproman.2004.10.003
Akintoye A (2000) Analysis of factors influencing project cost estimating practice. Constr Manage Econ 18(1):77–89. https://doi.org/10.1080/014461900370979
Kaming PF, Olomolaiye PO, Holt GD, Harris FC (1997) Factors influencing construction time and cost overruns on high-rise projects in Indonesia. Constr Manage Econ 15(1):83–94. https://doi.org/10.1080/014461997373132
Choudhry RM, Aslam MA, Hinze JW, Arain FM (2014) Cost and schedule risk analysis of bridge construction in Pakistan: establishing risk guidelines. J Constr Eng Manage 140(7):04014020. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000857
Author information
Authors and Affiliations
Corresponding author
Editor information
Editors and Affiliations
Rights and permissions
Copyright information
© 2021 The Author(s), under exclusive license to Springer Nature Singapore Pte Ltd.
About this paper
Cite this paper
Sharma, S., Gupta, A.K. (2021). Analysis of Factors Affecting Cost and Time Overruns in Construction Projects. In: Kumar Shukla, S., Raman, S.N., Bhattacharjee, B., Bhattacharjee, J. (eds) Advances in Geotechnics and Structural Engineering. Lecture Notes in Civil Engineering, vol 143. Springer, Singapore. https://doi.org/10.1007/978-981-33-6969-6_6
Download citation
DOI: https://doi.org/10.1007/978-981-33-6969-6_6
Published:
Publisher Name: Springer, Singapore
Print ISBN: 978-981-33-6968-9
Online ISBN: 978-981-33-6969-6
eBook Packages: EngineeringEngineering (R0)